Print Options
PrintThe Whole
Act
PrintThe Whole
Schedule
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Paragraph 9


Llinell Amser Newidiadau
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 01/01/2013.
Changes to legislation:
Electricity Act 1989, Paragraph 9 is up to date with all changes known to be in force on or before 09 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
9(1)This paragraph applies to meters used for ascertaining the quantity of electricity supplied to any premises.E+W+S
(2)The register of a meter to which this paragraph applies shall be admissible in any proceedings as evidence of the quantity of electricity supplied through it.
(3)Where electricity has been supplied for any period through such a meter which is of an approved pattern or construction and is installed in an approved manner, the register of the meter shall be presumed to have been registering for that period—
(a)within the prescribed margins of error; and
(b)in the case of a meter used in connection with an exempt supply, within any agreed margins of error,
unless the contrary is proved.
(4)Where a meter to which this paragraph applies has been operating for any period—
(a)within the prescribed margins of error; and
(b)in the case of a meter used in connection with an exempt supply, within any agreed margins of error,
the meter shall be conclusively presumed to have been correctly registering for that period the quantity of electricity supplied through it.
(5)The report of a meter examiner on any question relating to such a meter shall be admissible in evidence in any proceedings in which that question is raised; and any conclusions in the report as to the accuracy of the meter when it was tested shall be presumed to be correct unless the contrary is proved.