Print Options
PrintThe Whole
Act
PrintThe Whole
Schedule
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Paragraph 1


Llinell Amser Newidiadau
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 01/04/2010
Status:
Point in time view as at 22/07/2008.
Changes to legislation:
Electricity Act 1989, Paragraph 1 is up to date with all changes known to be in force on or before 06 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
1(1)An application for a consent under section 36 or 37 of this Act shall be in writing and shall describe by reference to a map the land to which the application relates, that is, the land—E+W+S
(a)on which the generating station is proposed to be constructed, extended or operated; or
(b)across which the electric line is proposed to be installed or kept installed.
(2)An application for a consent under section 37 of this Act shall also state—
(a)the length of the proposed line and its nominal voltage; and
(b)whether all necessary wayleaves have been agreed with owners and occupiers of land proposed to be crossed by the line,
and shall be supplemented, if the Secretary of State so directs, by such additional information as may be specified in the direction.
(3)The Secretary of State may by regulations make provision for determining the fees to be paid on applications for consent under section 36 or 37 of this Act, and the circumstances in which they are to be paid.
(4)Any sums received by the Secretary of State under this paragraph shall be paid into the Consolidated Fund.