Chwilio Deddfwriaeth

Electricity Act 1989

Status:

Point in time view as at 31/12/2020. This version of this provision has been superseded. Help about Status

Close

Status

You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.

Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.

Changes to legislation:

Electricity Act 1989, Section 25 is up to date with all changes known to be in force on or before 25 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

25 Orders for securing compliance.E+W+S

(1)Subject to subsections (2)[F1, [F2(4A) to] (5A)] and section 26 below, where [F3the Authority] is satisfied that a [F4regulated person] is contravening, or is likely to contravene, any relevant condition or requirement, [F5it] shall by a final order make such provision as is requisite for the purpose of securing compliance with that condition or requirement.

(2)Subject to [F6subsections [F2(4A) to] (5A)] below, where it appears to [F3the Authority]

(a)that a [F4regulated person] is contravening, or is likely to contravene, any relevant condition or requirement; and

(b)that it is requisite that a provisional order be made,

[F5it] shall (instead of taking steps towards the making of a final order) by a provisional order make such provision as appears to him requisite for the purpose of securing compliance with that condition or requirement.

(3)In determining for the purposes of subsection (2)(b) above whether it is requisite that a provisional order be made, [F3the Authority] shall have regard, in particular—

(a)to the extent to which any person is likely to sustain loss or damage in consequence of anything which, in contravention of the relevant condition or requirement, is likely to be done, or omitted to be done, before a final order may be made; and

(b)to the fact that the effect of the provisions of this section and section 27 below is to exclude the availability of any remedy (apart from under those provisions or for negligence) in respect of any contravention of a relevant condition or requirement.

(4)Subject to [F6subsections [F7(4A) to] (5A)] and section 26 below, [F3the Authority] shall confirm a provisional order, with or without modifications, if—

(a)[F5it] is satisfied that the [F4regulated person] to whom the order relates is contravening, or is likely to contravene, any relevant condition or requirement; and

(b)the provision made by the order (with any modifications) is requisite for the purpose of securing compliance with that condition or requirement.

[F8(4A)Before making a final order or making or confirming a provisional order, the Authority shall consider whether it would be more appropriate to proceed under the Competition Act 1998.

(4B)The Authority shall not make a final order or make or confirm a provisional order if it considers that it would be more appropriate to proceed under the Competition Act 1998.]

(5)[F3the Authority] shall not make a final order or make or confirm a provisional order in relation to a [F4regulated person] if [F5it] is satisfied—

(a)that the duties imposed on him by section [F93A to 3C] preclude the making or, as the case may be, the confirmation of the order;

F10(b). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F10(c). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F11(d). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

[F12(5A)The Authority is not required to make a final order or make or confirm a provisional order if it is satisfied—

(a)that the [F4regulated person] has agreed to take and is taking all such steps as it appears to the Authority for the time being to be appropriate for the [F4regulated person] to take for the purpose of securing or facilitating compliance with the condition or requirement in question; or

(b)that the contraventions were or the apprehended contraventions are of a trivial nature.]

(6)Where [F3the Authority] [F13decides that it would be more appropriate to proceed under the Competition Act 1998 or ] is satisfied as mentioned in [F6subsections (5) [F14or] (5A)] above, [F5it] shall—

(a)serve notice that [F5it] [F15has so decided or] is so satisfied on the [F4regulated person]; and

(b)publish the notice in such manner as [F5it] considers appropriate for the purpose of bringing the matters to which the notice relates to the attention of persons likely to be affected by them.

(7)A final or provisional order—

(a)shall require the [F4regulated person] to whom it relates (according to the circumstances of the case) to do, or not to do, such things as are specified in the order or are of a description so specified;

(b)shall take effect at such time, being the earliest practicable time, as is determined by or under the order; and

(c)may be revoked at any time by [F3the Authority].

(8)In this Part—

  • final order” means an order under this section other than a provisional order;

  • provisional order” means an order under this section which, if not previously confirmed in accordance with subsection (4) above, will cease to have effect at the end of such period (not exceeding three months) as is determined by or under the order;

  • [F16“regulated person” means a person who is one or more of the following—

    (a)

    a licence holder;

    (b)

    a distribution exemption holder;

    (c)

    a supply exemption holder;

    (d)

    an electricity undertaking which is a relevant producer or supplier;]

    (e)

    F17...

  • relevant condition”, in relation to a [F4regulated person], means any condition of [F18any licence held by that person];

  • relevant requirement”, in relation to a [F4regulated person],

  • (a)

    [F19means any duty or other requirement imposed on [F20that person under a provision specified in Schedule 6A as a relevant provision in respect of that person]] F21...

    (b)

    F21...

[F22(9)In paragraph (a) of the definition of “relevant requirement” in subsection (8), the reference to a provision specified in Schedule 6A is to be treated as including a provision of the predecessor of the Electricity Regulation that was specified in that Schedule immediately before the coming into force of the Electricity and Gas (Internal Markets) Regulations 2020.]

Textual Amendments

F1Words in s. 25(1) substituted (1.10.2001) by 2000 c. 27, s. 60(2)(7); S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)

F3Words substituted (20.12.2000) by virtue of Utilities Act 2000 (c. 27), s 3(2); S.I. 2000/3343, art. 2, Sch.

F5Word substituted (20.12.2000) by virtue of Utilities Act 2000 (c. 27), s 3(2); S.I. 2000/3343, art. 2, Sch.

F6Words in s. 25(2)(4)(6) substituted (1.10.2001) by 2000 c. 27, s. 60(3)(7); S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)

F9Words in s. 25(5)(a) substituted (20.12.2000) by 2000 c. 27, ss. 108, 110(2), Sch. 6 Pt. II para. 27; S.I. 2000/3343, art. 2, Sch. (subject to transitional provisions in arts. 3-15) (as amended by S.I. 2001/1780, art. 2)

F10S. 25(5)(b)(c) repealed (1.10.2001) by 2000 c. 27, ss. 60(4)(7), 108, Sch. 8; S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)

F12S. 25(5A) inserted (1.10.2001) by 2000 c. 27, s. 60(5)(7); S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)

F17Words in s. 25(8) omitted (31.12.2020) by virtue of S.I. 2019/530, reg. 54(a) (as substituted by The Electricity and Gas etc. (Amendment) (EU Exit) Regulations 2020 (S.I. 2020/1016), regs. 1(2), 3(22))

F21Words in s. 25(8) omitted (31.12.2020) by virtue of S.I. 2019/530, reg. 54(b) (as substituted by The Electricity and Gas etc. (Amendment) (EU Exit) Regulations 2020 (S.I. 2020/1016), regs. 1(2), 3(22))

Modifications etc. (not altering text)

C3Ss. 25-28 applied (with modifications) (S.) (1.4.2007) by The Renewables Obligation (Scotland) Order 2007 (S.S.I. 2007/267), arts. 1(1), 31

C4S. 25: power to amend conferred (18.12.2013) by Energy Act 2013 (c. 32), ss. 38(c), 156(3)

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Part

The Whole Part you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Part as a PDF

The Whole Part you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open y Ddeddf Gyfan

Y Ddeddf Gyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open y Ddeddf Gyfan heb Atodlenni

Y Ddeddf Gyfan heb Atodlenni you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Asesiadau Effaith

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill