Prohibition of resumption of mineral workingE+W
3 F1[( 1 )Where it appears to the mineral planning authority—E+W
(a)that development of land—
(i)consisting of the winning and working of minerals; or
(ii)involving the depositing of mineral waste,
has occurred; but
(b)the winning and working or depositing has permanently ceased,
the mineral planning authority may by order—
(i)prohibit the resumption of the winning and working or the depositing; and
(ii)impose, in relation to the site, any such requirement as is specified in sub-paragraph (3).
(2)The mineral planning authority may assume that the winning and working or the depositing has permanently ceased only when—
( a )no winning and working or depositing has occurred, to any substantial extent, at the site for a period of at least two years; and
( b )it appears to the mineral planning authority, on the evidence available to them at the time when they make the order, that resumption of the winning and working or the depositing to any substantial extent at the site is unlikely.
(3)The requirements mentioned in sub-paragraph (1) are—
(a)a requirement to alter or remove plant or machinery which was used for the purpose of the winning and working or the depositing or for any purpose ancillary to that purpose;
(b)a requirement to take such steps as may be specified in the order, within such period as may be so specified, for the purpose of removing or alleviating any injury to amenity which has been caused by the winning and working or depositing, other than injury due to subsidence caused by underground mining operations;
(c)a requirement that any condition subject to which planning permission for the development was granted or which has been imposed by virtue of any provision of this Act shall be complied with; and
(d)a restoration condition.]
(4)If—
(a)an order under this paragraph includes a restoration condition; or
(b)a restoration condition has previously been imposed in relation to the site by virtue of any provision of this Act,
the order under this paragraph may include any such aftercare condition as the mineral planning authority think fit.
(5)Paragraphs 2(3) to (9) and 3 to 6 of Schedule 5 apply in relation to an aftercare condition imposed under this paragraph as they apply to such a condition imposed under paragraph 2 of this Schedule.
Textual Amendments
F1Sch. 9 para. 3(1)-(3) substituted (25.9.1991) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), ss. 21, 84(2)-(4)(5), Sch. 1 para. 15(6)(with s. 84(5)); S.I. 1991/2067, art. 3 (subject to art. 4)
Modifications etc. (not altering text)
C1Sch. 9 para. 3 modified (22.7.2008) by The Town and Country Planning (Environmental Impact Assessment) (Mineral Permissions and Amendment) (England) Regulations 2008 (S.I. 2008/1556), reg. 4(3)-(5)
C2Sch. 9 para. 3 modified (E.) (24.8.2011) by The Town and Country Planning (Environmental Impact Assessment) Regulations 2011 (S.I. 2011/1824), regs. 1(1), 52(3)
C3Sch. 9 para. 3(1) modified (E.) (24.8.2011) by The Town and Country Planning (Environmental Impact Assessment) Regulations 2011 (S.I. 2011/1824), regs. 1(1), 52(4)
C4Sch. 9 para. 3(2)(a)(b) modified (E.) (24.8.2011) by The Town and Country Planning (Environmental Impact Assessment) Regulations 2011 (S.I. 2011/1824), regs. 1(1), 52(5)
4(1)An order under paragraph 3 shall not take effect unless it is confirmed by the Secretary of State, either without modification or subject to such modifications as he considers expedient.E+W
(2)Where a mineral planning authority submit such an order to the Secretary of State for his confirmation under this paragraph, the authority shall serve notice of the order—
(a)on any person who is an owner or occupier of any of the land to which the order relates, and
(b)on any other person who in their opinion will be affected by it.
(3)The notice shall specify the period within which any person on whom the notice is served may require the Secretary of State to give him an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for that purpose.
(4)If within that period such a person so requires, before the Secretary of State confirms the order he shall give such an opportunity both to him and to the mineral planning authority.
(5)The period referred to in sub-paragraph (3) must not be less than 28 days from the service of the notice.
(6)Where an order under paragraph 3 has been confirmed by the Secretary of State, the mineral planning authority shall serve a copy of the order on every person who was entitled to be served with notice under sub-paragraph (2).
(7)When an order under paragraph 3 takes effect any planning permission for the development to which the order relates shall cease to have effect.
(8)Sub-paragraph (7) is without prejudice to the power of the mineral planning authority, on revoking the order, to make a further grant of planning permission for development consisting of the winning and working of minerals [F2or involving the depositing of mineral waste].
Textual Amendments
F2Words in Sch. 9 para. 4(8) inserted (25.9.1991) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 21, Sch. 1 para. 15(7)(with s. 84(5)); S.I. 1991/2067, art. 3 (subject to art. 4)
Modifications etc. (not altering text)
C5Sch. 9 para. 4(7) modified (22.7.2008) by The Town and Country Planning (Environmental Impact Assessment) (Mineral Permissions and Amendment) (England) Regulations 2008 (S.I. 2008/1556), reg. 4(6)
C6Sch. 9 para. 4(7) modified (E.) (24.8.2011) by The Town and Country Planning (Environmental Impact Assessment) Regulations 2011 (S.I. 2011/1824), regs. 1(1), 52(6)