Part IIIE+W Control over development

Modifications etc. (not altering text)

C1Pt. III (ss. 55-106) except ss. 76, 90(2)(5) applied (with modifications) (17.7.1992) by S.I. 1992/1492, regs. 2(1)(b), 3-11

Pt. III (ss. 55-106): power to modify conferred (10.11.1993) by 1993 c. 28, s. 171(1)(a); S.I. 1993/2762, art. 3

Pt. III (ss. 55-106) applied (5.11.1993) by 1993 c. 42, s. 24(1) (with ss. 2, 30(1), Sch. 2 para.9)

Pt. III (ss. 55-106) extended (1.11.1995) by 1995 c. 25, s. 96(2) (with ss. 7(6), 115, 117); S.I. 1995/2765, art. 2

Pt. III (ss. 55-106) modified (1.4.1996) by 1994 c. 19, s. 20(3), Sch. 5 Pt. III paras. 15(1), 20 (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2

Pt. III (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 9(1)(2)

Pt. III (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 51

Pt. III (ss. 55-106) modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), art. 20(1)

Enterprise zone schemesE+W

89 Effect on planning permission of modification or termination of scheme.E+W

(1)Modifications to an enterprise zone scheme do not affect planning permission under the scheme in any case where the development authorised by it has been begun before the modifications take effect.

(2)When an area ceases to be an enterprise zone, planning permission under the scheme shall cease to have effect except in a case where the development authorised by it has been begun.