84 Measures necessary where apparatus affected by major works.E+W
(1)Where an undertaker’s apparatus in a street is or may be affected by major highway works, major bridge works or major transport works, the highway, bridge or transport authority concerned and the undertaker shall take such steps as are reasonably required—
(a)to identify any measures needing to be taken in relation to the apparatus in consequence of, or in order to facilitate, the execution of the authority’s works,
(b)to settle a specification of the necessary measures and determine by whom they are to be taken, and
(c)to co-ordinate the taking of those measures and the execution of the authority’s works,
so as to secure the efficient implementation of the necessary work and the avoidance of unnecessary delay.
(2)The Secretary of State may issue or approve for the purposes of this section a code of practice giving practical guidance as to the matters mentioned in subsection (1) and the steps to be taken by the authority and the undertaker.
(3)Any dispute between the authority and the undertaker as to any of the matters mentioned in subsection (1) shall, in default of agreement, be settled by arbitration.
(4)If the authority or the undertaker fails to comply with an agreement between them as to any of those matters, or with the decision of the arbitrator under subsection (3), the authority or undertaker shall be liable to compensate the other in respect of any loss or damage resulting from the failure.
Modifications etc. (not altering text)
C1Pt. 3 modified (22.3.2005) by The Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), art. 3(1)(2) (with art. 51)
C2Pt. 3 modified (26.8.2005) by The River Tyne (Tunnels) Order 2005 (S.I. 2005/2222), arts. 1, 8(7) (with arts. 45(1), 48, Sch. 10 paras. 21, 29)
C3Pt. 3 modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), arts. 1, 3(1) (with arts. 3(5), 15(3))
C4Pt. 3 applied (11.1.2006) by The Cambridgeshire Guided Busway Order 2005 (S.I. 2005/3523), arts. 1, 3(1) (with art. 52)
C5Pt. 3 modified (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 3(1) (with art. 51, Sch. 10 paras. 68, 85)
C6Pt. 3 applied (with modifications) (9.4.2013) by The Hinkley Point C (Nuclear Generating Station) Order 2013 (S.I. 2013/648), arts. 1, 9 (with arts. 48, 68, 79)
C7Pt. 3 modified (9.1.2014) by The National Grid (King’s Lynn B Power Station Connection) Order 2013 (S.I. 2013/3200), arts. 1, 9(1)
C8Pt. 3 applied (with modifications) (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(9) (with arts. 57, 58, Sch. 11 para. 19)
C9Pt. 3 modified (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(1)(2) (with arts. 57, 58, Sch. 11 para. 19)
C10Pt. 3 restricted (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), art. 1, Sch. 12 Pt. 2 para. 3 (with arts. 12, 13, Sch. 12 Pt. 1 paras. 6(3), 19, Pt. 2 paras. 3, 6, 13, Pt. 3 para. 5, Pt. 4 para. 4, Pt. 5 para. 4)
C11Pt. 3 modified (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 10(5), 11(4)
C12Ss. 54-106 applied (28.2.2013) by The Rookery South (Resource Recovery Facility) Order 2011 2013 (S.I. 2013/680), art. 10(3)
C13Ss. 54-106 applied (9.4.2013) by The Lancashire County Council (Torrisholme to the M6 Link (A683 Completion of Heysham to M6 Link Road)) Order 2013 (S.I. 2013/675), arts. 1, 9(2)
C14Ss. 54-106 applied (15.6.2013) by The Galloper Wind Farm Order 2013 (S.I. 2013/1203), arts. 1, 13(3) (with arts. 11, 12)
C15Ss. 54-106 applied (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 1, 9(3) (with art. 30)
C16Ss. 54-106 applied (7.7.2014) by The East Anglia ONE Offshore Wind Farm Order 2014 (S.I. 2014/1599), arts. 1, 8(3) (with arts. 37, 38, Sch. 9 para. 19)
C17Ss. 54-106 applied (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), arts. 1, 15(3) (with arts. 7(6), 12, 13, Sch. 12 Pt. 1 para. 19, Sch. 12 Pt. 2 para. 6, sch. 12 Pt. 3 para. 5, Sch. 12 Pt. 4 para. 4, Sch. 12 Pt. 5 para. 4)
C18Ss. 54-106 applied (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 10(4), 11(5) (with arts. 55, 56)
C19Ss. 54-106 applied (2.10.2014) by The North Killingholme (Generating Station) Order 2014 (S.I. 2014/2434), arts. 1, 9(3) (with arts. 6, 9(4), 13, Sch. 8 Pt. 1 para. 6, Sch. 8 Pt. 3 paras. 4(3), 6, 17, Sch. 8 Pt. 5 para. 9)
C20Ss. 54-106 applied (29.10.2014) by The Able Marine Energy Park Development Consent Order 2014 (S.I. 2014/2935), art. 15(3) (with arts. 30(4), 53)
C21Ss. 54-106 applied (28.11.2014) by The Walney Extension Offshore Wind Farm Order 2014 (S.I. 2014/2950), arts. 1, 10(3) (with arts. 38, 39)
C22Ss. 54-106 applied (7.1.2015) by The Willington C Gas Pipeline Order 2014 (S.I. 2014/3328), arts. 1, 10(3)
C23Ss. 54-106 applied (2.2.2015) by The Northumberland County Council (A1 – South East Northumberland Link Road (Morpeth Northern Bypass)) Development Consent Order 2015 (S.I. 2015/23), arts. 1, 9(2)
C24Ss. 54-106 applied (26.2.2015) by The Cornwall Council (A30 Temple to Higher Carblake Improvement) Order 2015 (S.I. 2015/147), arts. 1, 9(3)
C25S. 84(1)(3)(4) excluded (27.11.1992) by S.I. 1992/2984, art. 10
S. 84(1)(3)(4): functions of a local authority made exercisable by, or by employees of, such person as may be authorised in that behalf by the local highway authority whose function it is (23.7.1999) by S.I. 1999/2106, art. 2, Sch. 2 para. 4(b)
Commencement Information
I1S. 84 wholly in force: s. 84(1)(3)(4) in force at 1.1.1993 see s. 170(1) and S.I. 1992/2984, art. 2(2), Sch. 2; s. 84(2) in force at 14.7.1992 by S.I. 1992/1686, art. 3, Sch.