84 Measures necessary where apparatus affected by major works.E+W
(1)Where an undertaker’s apparatus in a street is or may be affected by major highway works, major bridge works or major transport works, the highway, bridge or transport authority concerned and the undertaker shall take such steps as are reasonably required—
(a)to identify any measures needing to be taken in relation to the apparatus in consequence of, or in order to facilitate, the execution of the authority’s works,
(b)to settle a specification of the necessary measures and determine by whom they are to be taken, and
(c)to co-ordinate the taking of those measures and the execution of the authority’s works,
so as to secure the efficient implementation of the necessary work and the avoidance of unnecessary delay.
(2)The Secretary of State may issue or approve for the purposes of this section a code of practice giving practical guidance as to the matters mentioned in subsection (1) and the steps to be taken by the authority and the undertaker.
(3)Any dispute between the authority and the undertaker as to any of the matters mentioned in subsection (1) shall, in default of agreement, be settled by arbitration.
(4)If the authority or the undertaker fails to comply with an agreement between them as to any of those matters, or with the decision of the arbitrator under subsection (3), the authority or undertaker shall be liable to compensate the other in respect of any loss or damage resulting from the failure.
Modifications etc. (not altering text)
C1Pt. 3 modified (22.3.2005) by The Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), art. 3(1)(2) (with art. 51)
C2Pt. 3 modified (26.8.2005) by The River Tyne (Tunnels) Order 2005 (S.I. 2005/2222), arts. 1, 8(7) (with arts. 45(1), 48, Sch. 10 paras. 21, 29)
C3Pt. 3 modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), arts. 1, 3(1) (with arts. 3(5), 15(3))
C4Pt. 3 applied (11.1.2006) by The Cambridgeshire Guided Busway Order 2005 (S.I. 2005/3523), arts. 1, 3(1) (with art. 52)
C5Pt. 3 modified (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 3(1) (with art. 51, Sch. 10 paras. 68, 85)
C6Pt. 3 applied (with modifications) (9.4.2013) by The Hinkley Point C (Nuclear Generating Station) Order 2013 (S.I. 2013/648), arts. 1, 9 (with arts. 48, 68, 79)
C7Pt. 3 modified (9.1.2014) by The National Grid (King’s Lynn B Power Station Connection) Order 2013 (S.I. 2013/3200), arts. 1, 9(1)
C8Pt. 3 applied (with modifications) (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(9) (with arts. 57, 58, Sch. 11 para. 19)
C9Pt. 3 modified (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(1)(2) (with arts. 57, 58, Sch. 11 para. 19)
C10Pt. 3 restricted (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), art. 1, Sch. 12 Pt. 2 para. 3 (with arts. 12, 13, Sch. 12 Pt. 1 paras. 6(3), 19, Pt. 2 paras. 3, 6, 13, Pt. 3 para. 5, Pt. 4 para. 4, Pt. 5 para. 4)
C11Pt. 3 modified (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 10(5), 11(4)
C12Pt. 3 modified (12.1.2016) by The London Underground (Bank Station Capacity Upgrade) Order 2015 (S.I. 2015/2044), arts. 1, 4(1)(2)
C13Pt. 3 applied (with modifications) (2.8.2016) by The Midland Metro (Wolverhampton City Centre Extension) Order 2016 (S.I. 2016/684), arts. 1, 5(1)(2) (with arts. 46, 47, Sch. 8 para. 2(7), Sch. 9 para. 4, Sch. 10 para. 12(2))
C14Pt. 3 modified (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 9(2)
C15Pt. 3 modified (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 12(1) (with art. 31)
C16Pt. 3 applied (with modifications) (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 12(1)(2) (with art. 3(1))
C17Pt. 3 modified (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 13(1)(2) (with art. 37)
C18Pt. 3 modified (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 10(1)(2) (with art. 5, Sch. 27 para. 36)
C19Pt. 3 modified (2.6.2022) by The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022 (S.I. 2022/549), arts. 1, 11(1)(2) (with arts. 6, 34)
C20Pt. 3 modified (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 15(1) (with arts. 62, 76, 87)
Pt. 3 modified (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 10(1)(2) (with arts. 4, 53)
C21Ss. 54-106 applied (28.2.2013) by The Rookery South (Resource Recovery Facility) Order 2011 2013 (S.I. 2013/680), art. 10(3)
C22Ss. 54-106 applied (9.4.2013) by The Lancashire County Council (Torrisholme to the M6 Link (A683 Completion of Heysham to M6 Link Road)) Order 2013 (S.I. 2013/675), arts. 1, 9(2)
C23Ss. 54-106 applied (15.6.2013) by The Galloper Wind Farm Order 2013 (S.I. 2013/1203), arts. 1, 13(3) (with arts. 11, 12)
C24Ss. 54-106 applied (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 1, 9(3) (with art. 30)
C25Ss. 54-106 applied (7.7.2014) by The East Anglia ONE Offshore Wind Farm Order 2014 (S.I. 2014/1599), arts. 1, 8(3) (with arts. 37, 38, Sch. 9 para. 19)
C26Ss. 54-106 applied (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), arts. 1, 15(3) (with arts. 7(6), 12, 13, Sch. 12 Pt. 1 para. 19, Sch. 12 Pt. 2 para. 6, sch. 12 Pt. 3 para. 5, Sch. 12 Pt. 4 para. 4, Sch. 12 Pt. 5 para. 4)
C27Ss. 54-106 applied (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 10(4), 11(5) (with arts. 55, 56)
C28Ss. 54-106 applied (2.10.2014) by The North Killingholme (Generating Station) Order 2014 (S.I. 2014/2434), arts. 1, 9(3) (with arts. 6, 9(4), 13, Sch. 8 Pt. 1 para. 6, Sch. 8 Pt. 3 paras. 4(3), 6, 17, Sch. 8 Pt. 5 para. 9)
C29Ss. 54-106 applied (29.10.2014) by The Able Marine Energy Park Development Consent Order 2014 (S.I. 2014/2935), art. 15(3) (with arts. 30(4), 53)
C30Ss. 54-106 applied (28.11.2014) by The Walney Extension Offshore Wind Farm Order 2014 (S.I. 2014/2950), arts. 1, 10(3) (with arts. 38, 39)
C31Ss. 54-106 applied (7.1.2015) by The Willington C Gas Pipeline Order 2014 (S.I. 2014/3328), arts. 1, 10(3)
C32Ss. 54-106 applied (2.2.2015) by The Northumberland County Council (A1 – South East Northumberland Link Road (Morpeth Northern Bypass)) Development Consent Order 2015 (S.I. 2015/23), arts. 1, 9(2)
C33Ss. 54-106 applied (26.2.2015) by The Cornwall Council (A30 Temple to Higher Carblake Improvement) Order 2015 (S.I. 2015/147), arts. 1, 9(3)
C34Ss. 54-106 applied (11.3.2015) by The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015 (S.I. 2015/318), arts. 1, 13(3) (with arts. 8(5), 35, 40, 41, Sch. 12 Pt. 1 paras. 4, 9(2), 10, Pt. 2 paras. 4(2)(3), 19, Pt. 4 paras. 3, 4, 16)
C35Ss. 54-106 applied (1.4.2015) by The Knottingley Power Plant Order 2015 (S.I. 2015/680), arts. 1, 10(3) (with art. 7(6), Sch. 8 para. 10)
C36Ss. 54-106 applied (23.6.2015) by The Norfolk County Council (Norwich Northern Distributor Road (A1067 to A47(T))) Order 2015 (S.I. 2015/1347), arts. 1, 9(2)
C37Ss. 54-106 applied (30.6.2015) by The Swansea Bay Tidal Generating Station Order 2015 (S.I. 2015/1386), arts. 1, 9(3) (with arts. 51, 53)
C38Ss. 54-106 applied (7.8.2015) by The Preesall Underground Gas Storage Facility Order 2015 (S.I. 2015/1561), arts. 1, 9(3) (with art. 44)
C39Ss. 54-106 applied (14.8.2015) by The Progress Power (Gas Fired Power Station) Order 2015 (S.I. 2015/1570), arts. 1, 10(3)
C40Ss. 54-106 applied (26.8.2015) by The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (S.I. 2015/1592), arts. 1, 14(3) (with arts. 35, 40, 41)
C41Ss. 54-106 applied (19.11.2015) by The Ferrybridge Multifuel 2 Power Station Order 2015 (S.I. 2015/1832), arts. 1(2), 9(3)
C42Ss. 54-106 applied (30.12.2015) by The Port Talbot Steelworks Generating Station Order 2015 (S.I. 2015/1984), arts. 1, 9(3) (with art. 26)
C43Ss. 54-106 applied (with modifications) (25.3.2016) by The Thorpe Marsh Gas Pipeline Order 2016 (S.I. 2016/297), arts. 1, 12(3) (with art. 39)
C44Ss. 54-106 applied (2.8.2016) by The Meaford Gas Fired Generating Station Order 2016 (S.I. 2016/779), arts. 1, 11(3)
C45Ss. 54-106 applied (10.8.2016) by The York Potash Harbour Facilities Order 2016 (S.I. 2016/772), arts. 1, 10(3) (with arts. 35, 36)
C46Ss. 54-106 applied (19.8.2016) by The North Wales Wind Farms Connection Order 2016 (S.I. 2016/818), arts. 1, 10(5) (with art. 35)
C47Ss. 54-106 applied (with modifications) (15.9.2016) by The River Humber Gas Pipeline Replacement Order 2016 (S.I. 2016/853), arts. 1, 11(3) (with art. 43)
C48Ss. 54-106 applied (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 11(3)
C49Ss. 54-106 applied (27.9.2016) by The Triton Knoll Electrical System Order 2016 (S.I. 2016/880), arts. 1(2), 8(3) (with arts. 39, 40, Sch. 8 para. 19)
C50Ss. 54-106 applied (18.3.2017) by The North London Heat and Power Generating Station Order 2017 (S.I. 2017/215), arts. 1, 10(3)
C51Ss. 54-106 applied (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 10(3) (with art. 31)
C52Ss. 54-106 applied (5.4.2017) by The Keuper Underground Gas Storage Facility Order 2017 (S.I. 2017/433), arts. 1, 10(4)
C53S. 84: functions made exercisable concurrently (8.5.2017) by The West Midlands Combined Authority (Functions and Amendment) Order 2017 (S.I. 2017/510), arts. 1(2), 9(1)(a)(2)
C54Ss. 54-106 applied (8.8.2017) by The Wrexham Gas Fired Generating Station Order 2017 (S.I. 2017/766), arts. 1, 10(3)
C55Ss. 54-106 applied (29.8.2017) by The East Anglia THREE Offshore Wind Farm Order 2017 (S.I. 2017/826), arts. 1, 8(3) (with arts. 5(9), 36, 37, Sch. 8 para. 34)
C56Ss. 54-106 applied (12.10.2018) by The Eggborough Gas Fired Generating Station Order 2018 (S.I. 2018/1020), arts. 1, 8(3) (with arts. 6, 42)
C57Ss. 54-106 applied (3.4.2019) by The Millbrook Gas Fired Generating Station Order 2019 (S.I. 2019/578), arts. 1, 9(3)
C58Ss. 54-106 applied (10.10.2019) by The Abergelli Power Gas Fired Generating Station Order 2019 (S.I. 2019/1268), arts. 1, 9(3)
C59Ss. 54-106 applied (25.10.2019) by The Drax Power (Generating Stations) Order 2019 (S.I. 2019/1315), arts. 1, 9(3)
C60Ss. 54-106 applied (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 11(3) (with art. 3(1))
C61Ss. 54-106 applied (14.4.2020) by The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020 (S.I. 2020/325), arts. 1, 10(4) (with art. 7)
C62Ss. 54-106 applied (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), arts. 1, 11(3) (with art. 7)
C63Ss. 54-106 applied (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 12(3) (with art. 37)
C64Ss. 54-106 applied (1.9.2020) by The Immingham Open Cycle Gas Turbine Order 2020 (S.I. 2020/847), arts. 1, 9(3) (with Sch. 9 para. 144)
C65Ss. 83-85: functions made exercisable concurrently (30.1.2021) by The West Yorkshire Combined Authority (Election of Mayor and Functions) Order 2021 (S.I. 2021/112), arts. 1(2), 22(1)(a)(2)(6)
C66Ss. 54-106 applied (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 12(3) (with art. 5, Sch. 27 para. 36)
C67Ss. 54-106 applied (22.12.2021) by The Morlais Demonstration Zone Order 2021 (S.I. 2021/1478), arts. 1, 7, Sch. 10 para. 2 (with arts. 15, 50, Sch. 11 para. 29)
C68Ss. 54-106 applied (10.3.2022) by The Thurrock Flexible Generation Plant Development Consent Order 2022 (S.I. 2022/157), arts. 1, 11(3) (with Sch. 8 Pt. 6 para. 19)
C69Ss. 54-106 applied (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 14(4) (with arts. 15, 62, 76, 87)
C70Ss. 54-106 applied (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 14(3) (with arts. 4, 53)
C71S. 84(1)(3)(4) excluded (27.11.1992) by S.I. 1992/2984, art. 10
S. 84(1)(3)(4): functions of a local authority made exercisable by, or by employees of, such person as may be authorised in that behalf by the local highway authority whose function it is (23.7.1999) by S.I. 1999/2106, art. 2, Sch. 2 para. 4(b)
Commencement Information
I1S. 84 wholly in force: s. 84(1)(3)(4) in force at 1.1.1993 see s. 170(1) and S.I. 1992/2984, art. 2(2), Sch. 2; s. 84(2) in force at 14.7.1992 by S.I. 1992/1686, art. 3, Sch.