51 Time for performance of connection etc. duties.E+W
(1)A water undertaker shall not be in breach of a duty imposed by virtue of the service of a connection notice unless—
(a)in the case of a duty to lay any service pipe or to connect any service pipe to which such a duty relates, it has failed to lay that pipe or to make that connection as soon as reasonably practicable after the relevant day;
(b)in the case of a duty to connect a service pipe the whole of which has already been laid when the notice is served on the undertaker, it has failed to make the connection before the end of the period of fourteen days beginning with the relevant day.
(2)In any case in which a water undertaker is subject to any such duty as is mentioned in subsection (1)(a) above, it shall be presumed, unless the contrary is shown in relation to that case, that the period of twenty-one days beginning with the relevant day is the period within which it is reasonably practicable for a water undertaker—
(a)to lay so much of any service pipe; and
(b)to fit such stopcock,
as it is necessary to lay or fit in that case for connecting a water main in a street with a service pipe at the boundary of any premises which abut on the part of the street where the main is situated.
(3)Where—
(a)a connection notice is served in respect of any premises; and
(b)at the time when the notice is served, the customer’s part of the service pipe to those premises has not been laid,
the duties of the undertaker under sections 45 and 46 above shall not arise by virtue of that notice until the person serving the notice, having obtained the necessary consents from the owners and occupiers of any affected land, has, at his own expense, laid so much of the service pipe as it is necessary, for the purpose of making the connection, to lay otherwise than in a street or in land mentioned in subsections (3) to (5) of section 46 above.
(4)In subsection (3) above the reference to the customer’s part of the service pipe to any premises is a reference to so much of the service pipe to those premises as falls to be laid otherwise than by the water undertaker in pursuance of section 46 above.
(5)Where—
(a)a person who has served a connection notice on a water undertaker has failed to comply with his obligation under section 45(3)(a) above to supplement that notice with information required by the undertaker; and
(b)that requirement was made by the undertaker at such a time before the end of the period within which the undertaker is required to comply with the duties imposed by virtue of the notice as gave that person a reasonable opportunity to provide the required information within that period,
the undertaker may delay its compliance with those duties until a reasonable time after the required information is provided.
(6)In this section “the relevant day”, in relation to a duty imposed on a water undertaker by virtue of a connection notice, means the day after whichever is the latest of the following days, that is to say-
(a)the day on which the notice was served on the undertaker;
(b)in a case where it is necessary for the person serving the notice to lay any service pipe after serving the notice, the day on which a notice stating that the pipe has been laid is served on the undertaker;
(c)the day on which all such conditions are satisfied as the undertaker has, under sections 47 to 50 above, made conditions of its compliance with that duty.