Print Options
PrintThe Whole
Act
PrintThe Whole
Schedule
PrintThis
Cross Heading
only
Changes over time for: Cross Heading: Notice of proposed enforcement


Llinell Amser Newidiadau
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 27/05/1997.
Changes to legislation:
Town and Country Planning (Scotland) Act 1997, Cross Heading: Notice of proposed enforcement is up to date with all changes known to be in force on or before 10 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
Notice of proposed enforcementS
13(1)This paragraph applies where before the relevant date any person proposes to take steps for enforcing a planning control in the case of such works or such a use as is mentioned in section 251(1).S
(2)Subject to sub-paragraph (4), unless a compliance determination application has been made in relation to the land which has not been finally determined, that person shall serve on every owner and occupier of the land not less than 28 days’ notice of the proposal, and if within that period any person makes such an application in relation to the land and within 7 days of making it serves on the person proposing to take steps as aforesaid notice that the application has been made, no steps for enforcing the control shall be taken until the final determination of the application.
(3)If such an application has been made which has not been finally determined, no such steps shall be taken until the final determination of it.
(4)No notice shall be required under sub-paragraph (2) if steps for enforcing a planning control in the case of any works on land are begun within 28 days of the final determination of a compliance determination application in relation to the land.
(5)For the purpose of this paragraph a compliance determination application shall be treated as having been finally determined notwithstanding that a subsequent application may be made under paragraph 9.