Utilities Act 2000

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

Changes over time for: Section 44

 Help about opening options

Alternative versions:

Changes to legislation:

Utilities Act 2000, Section 44 is up to date with all changes known to be in force on or before 30 May 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to the whole Act associated Parts and Chapters:

Whole provisions yet to be inserted into this Act (including any effects on those provisions):

  • s. 5(3A) inserted by 2023 c. 52 s. 197(2)
  • s. 33(1)(f) word omitted by 2018 c. 14 s. 6(10)(a) (This amendment not applied to legislation.gov.uk. The word "or" is already omitted present (19.7.2018) by virtue of 2018 c. 21, ss. 11(2), 13(2))

44 Duty to connect on request.U.K.

This adran has no associated Nodiadau Esboniadol

For sections 16 and 17 of the 1989 Act (duty to supply on request and exceptions to that duty) there are substituted—

Duties of electricity distributorsU.K.
16 Duty to connect on request.

(1)An electricity distributor is under a duty—

(a)to make a connection between a distribution system of his and any premises, when required to do so by—

(i)the owner or occupier of the premises; or

(ii)an authorised supplier acting with the consent of the owner or occupier of the premises,

for the purpose of enabling electricity to be conveyed to or from the premises;

(b)to make a connection between a distribution system of his and any distribution system of another authorised distributor, when required to do so by that authorised distributor for the purpose of enabling electricity to be conveyed to or from that other system.

(2)Any duty under subsection (1) includes a duty to provide such electric lines or electrical plant as may be necessary to enable the connection to be used for the purpose for which it is required.

(3)The duties under this section shall be performed subject to such terms as may be agreed under section 16A for so long as the connection is required.

(4)In this section and sections 16A to 23—

(a)any reference to making a connection includes a reference to maintaining the connection (and continuing to provide the necessary electric lines or electrical plant);

(b)any reference to requiring a connection includes a reference to requiring the connection to be maintained (and the continued provision of the necessary electric lines and electrical plant); and

(c)any reference to the provision of any electric line or electrical plant is a reference to the provision of such a line or an item of electrical plant either by the installation of a new one or by the modification of an existing one.

(5)The duties under this section are subject to the following provisions of this Part and any regulations made under those provisions.

16A Procedure for requiring a connection.

(1)Where a person requires a connection to be made by an electricity distributor in pursuance of section 16(1), he shall give the distributor a notice requiring him to offer terms for making the connection.

(2)That notice must specify—

(a)the premises or distribution system to which a connection to the distributor’s system is required;

(b)the date on or by which the connection is to be made; and

(c)the maximum power at which electricity may be required to be conveyed through the connection.

(3)The person requiring a connection shall also give the distributor such other information in relation to the required connection as the distributor may reasonably request.

(4)A request under subsection (3) shall be made as soon as practicable after the notice under subsection (1) is given (if not made before that time).

(5)As soon as practicable after receiving the notice under subsection (1) and any information requested under subsection (3) the distributor shall give to the person requiring the connection a notice—

(a)stating the extent (if any) to which his proposals are acceptable to the distributor and specifying any counter proposals made by him;

(b)specifying any payment which that person will be required to make under section 19(1) or regulations under section 19(2);

(c)specifying any security which that person will be required to give under section 20; and

(d)stating any other terms which that person will be required to accept under section 21.

(6)A notice under subsection (5) shall also contain a statement of the effect of section 23.

17 Exceptions from duty to connect.

(1)Nothing in section 16(1) requires an electricity distributor to make a connection if and to the extent that—

(a)he is prevented from doing so by circumstances not within his control;

(b)circumstances exist by reason of which his doing so would or might involve his being in breach of regulations under section 29, and he has taken all such steps as it was reasonable to take both to prevent the circumstances from occurring and to prevent them from having that effect; or

(c)it is not reasonable in all the circumstances for him to be required to do so.

(2)Without prejudice to the generality of subsection (1) an electricity distributor is not required to make a connection if—

(a)making the connection involves the distributor doing something which, without the consent of another person, would require the exercise of a power conferred by any provision of Schedule 3 or 4;

(b)the distributor’s licence does not provide for that provision to have effect in relation to him; and

(c)any necessary consent has not, at the time the request is made, been given.

(3)Subsection (1)(c) does not permit an electricity distributor to disconnect any premises or distribution system to which a connection is being maintained by him unless the distributor gives—

(a)where the connection is to premises, to the occupier or to the owner if the premises are not occupied;

(b)where the connection is to another distribution system, to the person who is authorised by a licence or exemption to run that system,

not less than seven working days’ notice of his intention to disconnect the premises or distribution system.

Commencement Information

I1S. 44 wholly in force at 1.10.2001; s. 44 not in force at Royal Assent see s. 110(2); s. 44 in force at 1.10.2001 by S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open y Ddeddf Gyfan

Y Ddeddf Gyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Nodiadau Esboniadol

Testun a grëwyd gan yr adran o’r llywodraeth oedd yn gyfrifol am destun y Ddeddf i esbonio beth mae’r Ddeddf yn ceisio ei wneud ac i wneud y Ddeddf yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol. Cyflwynwyd Nodiadau Esboniadol ym 1999 ac maent yn cyd-fynd â phob Deddf Gyhoeddus ac eithrio Deddfau Adfeddiannu, Cronfa Gyfunol, Cyllid a Chyfnerthiad.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill