Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 46
Llinell Amser Newidiadau
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 01/09/2004.
Changes to legislation:
Utilities Act 2000, Section 46 is up to date with all changes known to be in force on or before 25 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
46 Power to recover expenditure.U.K.
This
adran has no associated
Nodiadau Esboniadol
(1)Section 19 of the 1989 Act (power to recover expenditure) is amended as follows.
(2)In subsection (1) for “a public electricity supplier”, “supplier” and “supply of electricity” there is substituted respectively “ an electricity distributor ”, “ distributor ” and “ connection ”.
(3)For subsection (2) there is substituted—
“(2)The Secretary of State may, after consultation with the Authority, make provision by regulations for entitling an electricity distributor to require a person requiring a connection in pursuance of section 16(1) to pay to the distributor, in respect of any expenses reasonably incurred in providing any electric line or electrical plant used for the purpose of making the connection, such amount as may be reasonable in all the circumstances if—
(a)the connection is required within the prescribed period after the provision of the line or plant; and
(b)a person (“the initial contributor”) has made a payment to the distributor in respect of those expenses, the line or plant having been provided for the purpose of making a connection to any premises or distribution system as required by that person.”
(4)In subsection (3) for “a public electricity supplier” there is substituted “ an electricity distributor. ”
(5)In subsection (4) for the words from “maintaining” to the end there is substituted “ continuing to provide it ”.