Changes over time for: Section 58


Llinell Amser Newidiadau
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 11/01/2024.
Changes to legislation:
There are currently no known outstanding effects for the Utilities Act 2000, Section 58.

Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
58 Information to be given to customers.U.K.
This
adran has no associated
Nodiadau Esboniadol
For section 42A of the 1989 Act there is substituted—
“42A Information to be given to customers about overall performance.
(1)The Authority may make regulations requiring such information as may be specified or described in the regulations about—
(a)the standards of overall performance determined under section 40 or 40A; and
(b)the levels of performance achieved as respects those standards,
to be given by electricity suppliers or electricity distributors to customers or potential customers of electricity suppliers.
(2)Regulations under this section may include provision—
(a)specifying the form and manner in which and the frequency with which information is to be given; and
(b)requiring information about the matters mentioned in subsection (1)(a) or (b) and relating to electricity distributors to be given by electricity distributors to electricity suppliers and by electricity suppliers to their customers or potential customers.”