Print Options
PrintThe Whole
Act
PrintThe Whole
Schedule
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Paragraph 67


Llinell Amser Newidiadau
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 01/11/2020.
Changes to legislation:
Communications Act 2003, Paragraph 67 is up to date with all changes known to be in force on or before 05 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
This
adran has no associated
Nodiadau Esboniadol
[67(1)Before carrying out non-emergency undertaker's works which interfere with a network, an undertaker must give the operator notice of the intention to carry out the works (“notice of proposed works”).U.K.
(2)Notice of proposed works must specify—
(a)the nature of the proposed undertaker's works,
(b)the alteration of the electronic communications apparatus which the works involve or are likely to involve, and
(c)the time and place at which the works will begin.
(3)The undertaker must not begin the proposed undertaker's works (including the proposed alteration of electronic communications apparatus) until the notice period has ended.
(4)But the undertaker's power to alter electronic communications apparatus (in carrying out the proposed undertaker's works) is subject to paragraph 68.
(5)In this paragraph—
“non-emergency undertaker's works” means any undertaker's works which are not emergency works under paragraph 71;
“notice period” means the period of 10 days beginning with the day on which notice of proposed works is given.]