Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Chapter
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 162


Llinell Amser Newidiadau
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 01/08/2020
Status:
Point in time view as at 23/07/2018. This version of this provision has been superseded.

Status
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Changes to legislation:
Energy Act 2004, Section 162 is up to date with all changes known to be in force on or before 06 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
162Restrictions on making of ordinary administration ordersE+W+S
This
adran has no associated
Nodiadau Esboniadol
(1)This section applies where an ordinary administration application is made in relation to a protected energy company by a person other than the Secretary of State.
(2)The court must dismiss the application if—
(a)an energy administration order is in force in relation to the company; or
(b)an energy administration order has been made in relation to the company but is not yet in force.
(3)Where subsection (2) does not apply, the court, on hearing the application, must not exercise its powers under paragraph 13 of Schedule B1 to the 1986 Act (other than its power of adjournment) unless—
(a)notice of the application has been served both on the Secretary of State and on GEMA;
(b)a period of at least fourteen days has elapsed since the service of the last of those notices to be served; and
(c)there is no application for an energy administration order that is outstanding.
(4)Paragraph 44 of Schedule B1 to the 1986 Act (interim moratorium) does not prevent, or require the permission of the court for, the making of an application for an energy administration order.
(5)Upon the making of an energy administration order in relation to a protected energy company, the court must dismiss any ordinary administration application made in relation to that company which is outstanding.
(6)In this section “ordinary administration application” means an application in accordance with paragraph 12 of Schedule B1 to the 1986 Act.