Chwilio Deddfwriaeth

Planning Act 2008

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

Changes to legislation:

Planning Act 2008, Cross Heading: Energy is up to date with all changes known to be in force on or before 01 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Part 3 Crossheading Energy:

Changes and effects yet to be applied to the whole Act associated Parts and Chapters:

Whole provisions yet to be inserted into this Act (including any effects on those provisions):

EnergyE+W+S

15Generating stationsE+W

(1)The construction or extension of a generating station is within section 14(1)(a) only if the generating station is or (when constructed or extended) is expected to be within subsection (2) [F1, (3), (3A) or (3B)].

(2)A generating station is within this subsection if—

(a)it is in England F2...,

[F3(aa)it does not generate electricity from wind,]

(b)it is not an offshore generating station, and

(c)its capacity is more than 50 megawatts.

(3)A generating station is within this subsection if—

(a)it is an offshore generating station, and

(b)its capacity is more than 100 megawatts.

[F4(3A)A generating station is within this subsection if—

(a)it is in Wales,

(b)it does not generate electricity from wind, and

(c)its capacity is more than 350 megawatts.

(3B)A generating station is within this subsection if—

(a)it is in waters adjacent to Wales up to the seaward limits of the territorial sea, or in the Welsh zone, and

(b)its capacity is more than 350 megawatts.]

[F5(3C)To the extent that an exempt electricity storage facility forms part of a generating station (or is expected to do so, when the generating station is constructed or extended), any capacity provided by the facility is to be disregarded for the purposes of determining whether the generating station is within subsection (2), (3), (3A) or (3B).

(3D)The construction or extension of a generating station is not within section 14(1)(a) to the extent that the generating station comprises or (when constructed or extended) is expected to comprise an exempt electricity storage facility.]

(4)An “offshore” generating station is a generating station that is—

(a)in waters in or adjacent to England F6... up to the seaward limits of the territorial sea, or

(b)in a Renewable Energy Zone, except [F7the Welsh zone or] any part of a Renewable Energy Zone in relation to which the Scottish Ministers have functions.

[F8(5)"Welsh zone” has the meaning given in section 158 of the Government of Wales Act 2006.]

[F9(6)In this section—

  • “electricity storage facility” means a facility which generates electricity from energy that—

    (a)

    was converted from electricity by that facility, and

    (b)

    is stored within that facility for the purpose of its future reconversion into electricity;

  • “exempt electricity storage facility” means an electricity storage facility which is not a pumped hydroelectric storage facility;

  • “pumped hydroelectric storage facility” means an electricity storage facility that stores the gravitational potential energy of water that has been pumped to a higher level so that its return to a lower level can be used to generate electricity.]

Textual Amendments

F1Words in s. 15(1) substituted (1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by Wales Act 2017 (c. 4), ss. 39(2), 71(4) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)

F2Words in s. 15(2)(a) omitted (1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by virtue of Wales Act 2017 (c. 4), ss. 39(3), 71(4) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)

F4S. 15(3A)(3B) inserted (31.3.2017 for specified purposes, 1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by Wales Act 2017 (c. 4), ss. 39(4), 71(2)(e) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)

F6Words in s. 15(4)(a) omitted (1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by virtue of Wales Act 2017 (c. 4), ss. 39(5)(a), 71(4) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)

F7Words in s. 15(4)(b) inserted (1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by Wales Act 2017 (c. 4), ss. 39(5)(b), 71(4) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)

F8S. 15(5) inserted (31.3.2017 for specified purposes, 1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by Wales Act 2017 (c. 4), ss. 39(6), 71(2)(e) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)

Commencement Information

I1S. 15 in force at 1.3.2010 by S.I. 2010/101, art. 4(a) (with art. 6)

16Electric linesE+W

(1)The installation of an electric line above ground is within section 14(1)(b) only if (when installed) the electric line will be—

(a)wholly in England,

(b)wholly in Wales,

(c)partly in England and partly in Wales, or

(d)partly in England and partly in Scotland, subject to subsection (2).

(2)In the case of an electric line falling within subsection (1)(d), the installation of the line above ground is within section 14(1)(b) only to the extent that (when installed) the line will be in England.

(3)The installation of an electric line above ground is not within section 14(1)(b)—

(a)if the nominal voltage of the line is expected to be less than 132 kilovolts, F10...

[F11(aa)if the length of the line (when installed) will be less than two kilometres,

(ab)if—

(i)the line will replace an existing line,

(ii)the nominal voltage of the line is expected to be greater than the nominal voltage of the existing line (but see subsection (3A)),

(iii)the height above the surface of the ground of any support for the line will not exceed the height of the highest existing support or support which is being replaced by more than 10 per cent, and

(iv)where the line is to be installed in a different position from the existing line, the distance between any new support and the existing line will not exceed 60 metres and the existing line will be removed within twelve months from the date on which the installation of the line which replaces it is complete,]

(b)to the extent that (when installed) the line will be within premises in the occupation or control of the person responsible for its installation [F12, or

(c) if section 37(1) of the Electricity Act 1989 (consent required for overhead lines) does not apply to it by virtue of the Overhead Lines (Exemption) (England and Wales) Regulations 2009 ( S.I. 2009/640 ), as amended by the Overhead Lines (Exempt Installations) (Consequential Provisions) Order 2010.]

[F13(3A)Paragraph (ab)(ii) of subsection (3) (condition that nominal voltage of line expected to be greater than nominal voltage of existing line) does not apply if any part of the line (when installed) will be within a European site or an SSSI.]

[F14(3B)The installation of an electric line above ground is not within section 14(1)(b) if the line is associated with the construction or extension of a devolved Welsh generating station granted planning permission or consented to on or after the day on which section 39 of the Wales Act 2017 comes into force and the nominal voltage of the line is expected to be no greater than 132 kilovolts.

(3C)"Devolved Welsh generating station”” means a generating station that—

(a)is in Wales and—

(i)generates electricity from wind, or

(ii)has a capacity of 350 megawatts or less; or

(b)is in waters adjacent to Wales up to the seaward limits of the territorial sea or in the Welsh zone and has a capacity of 350 megawatts or less.

(3D)"Welsh zone”” has the meaning given in section 158 of the Government of Wales Act 2006.]

[F15(4)In this section—

  • “European site” has the same meaning as in [F16the Conservation of Habitats and Species Regulations 2017 (S.I. 2017/1012)];

  • “existing line” means an electric line which—

    (a)

    has been installed or is kept installed above ground in accordance with a consent granted under section 37(1) of the Electricity Act 1989 or an order granting development consent; or

    (b)

    has been installed above ground and is an electric line to which section 37(1) of the Electricity Act 1989 does not apply by virtue of—

    (i)

    paragraph 5(4) or (5) of Schedule 17 to that Act, or

    (ii)

    the Overhead Lines (Exemption) (England and Wales) Regulations 2009 (S.I. 2009/640), as amended by the Overhead Lines (Exempt Installations) (Consequential Provisions) Order 2010;

  • “premises” includes any land, building or structure;

  • SSSI” means a site of special scientific interest notified under sections 28 to 28D of the Wildlife and Countryside Act 1981.]

17Underground gas storage facilitiesE+W

(1)Development relating to underground gas storage facilities is within section 14(1)(c) only if the development is within subsection (2), (3) or (5).

(2)Development is within this subsection if—

(a)it is the carrying out of operations for the purpose of creating underground gas storage facilities in England, or

(b)it is starting to use underground gas storage facilities in England,

and the condition in subsection (4) is met in relation to the facilities.

(3)Development is within this subsection if—

(a)it is starting to use underground gas storage facilities in Wales,

(b)the facilities are facilities for the storage of gas underground in natural porous strata,

(c)the proposed developer is a gas transporter, and

(d)the condition in subsection (4) is met in relation to the facilities.

(4)The condition is that—

(a)the working capacity of the facilities is expected to be at least 43 million standard cubic metres, or

(b)the maximum flow rate of the facilities is expected to be at least 4.5 million standard cubic metres per day.

(5)Development is within this subsection if—

(a)it is the carrying out of operations for the purpose of altering underground gas storage facilities in England, and

(b)the effect of the alteration is expected to be—

(i)to increase by at least 43 million standard cubic metres the working capacity of the facilities, or

(ii)to increase by at least 4.5 million standard cubic metres per day the maximum flow rate of the facilities.

(6)Underground gas storage facilities” means facilities for the storage of gas underground in cavities or in porous strata.

(7)In this section—

  • maximum flow rate”, in relation to underground gas storage facilities, means the maximum rate at which gas is able to flow out of the facilities, on the assumption that—

    (a)

    the facilities are filled to maximum capacity, and

    (b)

    the rate is measured after any processing of gas required on its recovery from storage;

  • working capacity”, in relation to underground gas storage facilities, means the capacity of the facilities for storage of gas underground, ignoring any capacity for storage of cushion gas.

(8)In subsection (7) “cushion gas” means gas which is kept in underground gas storage facilities for the purpose of enabling other gas stored there to be recovered from storage.

Commencement Information

I3S. 17 in force at 1.3.2010 by S.I. 2010/101, art. 4(a) (with art. 6)

18LNG facilitiesE+W

(1)The construction of an LNG facility is within section 14(1)(d) only if (when constructed) the facility will be in England and—

(a)the storage capacity of the facility is expected to be at least 43 million standard cubic metres, or

(b)the maximum flow rate of the facility is expected to be at least 4.5 million standard cubic metres per day.

(2)The alteration of an LNG facility is within section 14(1)(d) only if the facility is in England and the effect of the alteration is expected to be—

(a)to increase by at least 43 million standard cubic metres the storage capacity of the facility, or

(b)to increase by at least 4.5 million standard cubic metres per day the maximum flow rate of the facility.

(3)LNG facility” means a facility for—

(a)the reception of liquid natural gas from outside England,

(b)the storage of liquid natural gas, and

(c)the regasification of liquid natural gas.

(4)In this section—

  • maximum flow rate”, in relation to a facility, means the maximum rate at which gas is able to flow out of the facility, on the assumption that—

    (a)

    the facility is filled to maximum capacity, and

    (b)

    the rate is measured after regasification of the liquid natural gas and any other processing required on the recovery of the gas from storage;

  • storage capacity” means the capacity of the facility for storage of liquid natural gas.

(5)The storage capacity of an LNG facility is to be measured as if the gas were stored in regasified form.

Commencement Information

I4S. 18 in force at 1.3.2010 by S.I. 2010/101, art. 4(a) (with art. 6)

19Gas reception facilitiesE+W

(1)The construction of a gas reception facility is within section 14(1)(e) only if (when constructed)—

(a)the facility will be in England and will be within subsection (4), and

(b)the maximum flow rate of the facility is expected to be at least 4.5 million standard cubic metres per day.

(2)The alteration of a gas reception facility is within section 14(1)(e) only if—

(a)the facility is in England and is within subsection (4), and

(b)the effect of the alteration is expected to be to increase by at least 4.5 million standard cubic metres per day the maximum flow rate of the facility.

(3)Gas reception facility” means a facility for—

(a)the reception of natural gas in gaseous form from outside England, and

(b)the handling of natural gas (other than its storage).

(4)A gas reception facility is within this subsection if—

(a)the gas handled by the facility does not originate in England, Wales or Scotland,

(b)the gas does not arrive at the facility from Scotland or Wales, and

(c)the gas has not already been handled at another facility after its arrival in England.

(5)Maximum flow rate” means the maximum rate at which gas is able to flow out of the facility.

Commencement Information

I5S. 19 in force at 1.3.2010 by S.I. 2010/101, art. 4(a) (with art. 6)

20Gas transporter pipe-linesE+W

(1)The construction of a pipe-line by a gas transporter is within section 14(1)(f) only if (when constructed) each of the conditions in subsections (2) to (5) is expected to be met in relation to the pipe-line.

(2)The pipe-line must be wholly or partly in England.

(3)Either—

(a)the pipe-line must be more than 800 millimetres in diameter and more than 40 kilometres in length, or

(b)the construction of the pipe-line must be likely to have a significant effect on the environment.

(4)The pipe-line must have a design operating pressure of more than 7 bar gauge.

(5)The pipe-line must convey gas for supply (directly or indirectly) to at least 50,000 customers, or potential customers, of one or more gas suppliers.

(6)In the case of a pipe-line that (when constructed) will be only partly in England, the construction of the pipe-line is within section 14(1)(f) only to the extent that the pipe-line will (when constructed) be in England.

(7)Gas supplier” has the same meaning as in Part 1 of the Gas Act 1986 (c. 44) (see section 7A(11) of that Act).

Commencement Information

I6S. 20 in force at 1.3.2010 by S.I. 2010/101, art. 4(a) (with art. 6)

21Other pipe-linesE+W+S

(1)The construction of a pipe-line other than by a gas transporter is within section 14(1)(g) only if (when constructed) the pipe-line is expected to be—

(a)a cross-country pipe-line,

(b)a pipe-line the construction of which would (but for section 33(1) of this Act) require authorisation under section 1(1) of the Pipe-lines Act 1962 (c. 58) (cross-country pipe-lines not to be constructed without authorisation), and

(c)within subsection (2).

(2)A pipe-line is within this subsection if one end of it is in England or Wales and—

(a)the other end of it is in England or Wales, or

(b)it is an oil or gas pipe-line and the other end of it is in Scotland.

(3)For the purposes of section 14(1)(g) and the previous provisions of this section, the construction of a diversion to a pipe-line is treated as the construction of a separate pipe-line.

(4)But if—

(a)the pipe-line to be diverted is itself a nationally significant pipe-line, and

(b)the length of the pipe-line which is to be diverted has not been constructed,

the construction of the diversion is treated as the construction of a cross-country pipe-line, whatever the length of the diversion.

(5)For the purposes of subsection (4), a pipe-line is a nationally significant pipe-line if—

(a)development consent is required for its construction by virtue of section 14(1)(g), and has been granted, or

(b)its construction has been authorised by a pipe-line construction authorisation under section 1(1) of the Pipe-lines Act 1962 (c. 58).

(6)Diversion” means a lateral diversion of a length of a pipe-line (whether or not that pipe-line has been constructed) where the diversion is beyond the permitted limits.

(7)The permitted limits are the limits of lateral diversion permitted by any of the following granted in respect of the construction of the pipe-line—

(a)development consent;

(b)authorisation under the Pipe-lines Act 1962;

(c)planning permission.

Commencement Information

I7S. 21 in force at 1.3.2010 by S.I. 2010/101, art. 3(b) (with art. 6)

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open y Ddeddf Gyfan

Y Ddeddf Gyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open y Ddeddf Gyfan heb Atodlenni

Y Ddeddf Gyfan heb Atodlenni you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Nodiadau Esboniadol

Testun a grëwyd gan yr adran o’r llywodraeth oedd yn gyfrifol am destun y Ddeddf i esbonio beth mae’r Ddeddf yn ceisio ei wneud ac i wneud y Ddeddf yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol. Cyflwynwyd Nodiadau Esboniadol ym 1999 ac maent yn cyd-fynd â phob Deddf Gyhoeddus ac eithrio Deddfau Adfeddiannu, Cronfa Gyfunol, Cyllid a Chyfnerthiad.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill