Planning Act 2008

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

 Help about opening options

Dewisiadau AgorExpand opening options

Changes over time for: Cross Heading: Water

 Help about opening options

No versions valid at: 18/06/2013

Alternative versions:

Status:

Point in time view as at 18/06/2013. This version of this cross heading contains provisions that are not valid for this point in time. Help about Status

Changes to legislation:

Planning Act 2008, Cross Heading: Water is up to date with all changes known to be in force on or before 05 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Yn ddilys o 01/01/2018

WaterE+W

27Dams and reservoirsE+W

(1)The construction of a dam or reservoir is within section 14(1)(m) only if—

(a)the dam or reservoir (when constructed) will be in England,

(b)the construction will be carried out by one or more water undertakers, and

(c)the volume of water to be held back by the dam or stored in the reservoir is expected to exceed 10 million cubic metres.

(2)The alteration of a dam or reservoir is within section 14(1)(m) only if—

(a)the dam or reservoir is in England,

(b)the alteration will be carried out by one or more water undertakers, and

(c)the additional volume of water to be held back by the dam or stored in the reservoir as a result of the alteration is expected to exceed 10 million cubic metres.

(3)Water undertaker” means a company appointed as a water undertaker under the Water Industry Act 1991 (c. 56).

28Transfer of water resourcesE+W

(1)Development relating to the transfer of water resources is within section 14(1)(n) only if—

(a)the development will be carried out in England by one or more water undertakers,

(b)the volume of water to be transferred as a result of the development is expected to exceed 100 million cubic metres per year,

(c)the development will enable the transfer of water resources—

(i)between river basins in England,

(ii)between water undertakers' areas in England, or

(iii)between a river basin in England and a water undertaker's area in England, and

(d)the development does not relate to the transfer of drinking water.

(2)In this section—

  • river basin” means an area of land drained by a river and its tributaries;

  • water undertaker” means a company appointed as a water undertaker under the Water Industry Act 1991;

  • water undertaker's area” means the area for which a water undertaker is appointed under that Act.

Yn ôl i’r brig

Options/Cymorth

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?