32(1)Section 36 (consent for construction etc. of generating stations) is amended as follows.
(2)In subsection (1) after “subsections” insert “(1A) to”.
(3)After subsection (1) insert—
“(1A)So far as relating to the construction or extension of a generating station, subsection (1) is subject to section 33(1) of the Planning Act 2008 (exclusion of requirement for other consents for development for which development consent required).
(1B)So far as relating to the operation of a generating station, subsection (1) does not apply if the operation is authorised by an order granting development consent under the Planning Act 2008.”