- Y Diweddaraf sydd Ar Gael (Diwygiedig)
- Pwynt Penodol mewn Amser (01/10/2016)
- Gwreiddiol (Fel y'i Deddfwyd)
No versions valid at: 01/10/2016
Point in time view as at 01/10/2016. This version of this provision is not valid for this point in time.
Infrastructure Act 2015, Section 52 is up to date with all changes known to be in force on or before 30 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
Yn ddilys o 06/04/2017
(1)The Electricity Act 1989 is amended in accordance with this section.
(2)In section 19 (power to recover expenditure)—
(a)omit subsections (2) and (3);
(b)after subsection (3) insert—
“(3A)Schedule 5B (reimbursement of persons who have met expenses) has effect.”;
(c)in subsection (4), after “this section” insert “ and Schedule 5B ”.
(3)After Schedule 5A insert—
1(1)The Secretary of State may, by regulations, make provision entitling the relevant electricity distributor to exercise the reimbursement powers in cases where conditions A, B, C and D are met.
(2)Condition A is met if any electric line or electrical plant is provided for the purpose of making a connection (the “first connection”)—
(a)between premises and a distribution system, or
(b)between two distribution systems.
(3)Condition B is met if a payment in respect of first connection expenses is made by one or more of the following persons—
(a)a person requiring the first connection in pursuance of section 16(1);
(b)a person who otherwise causes the first connection to be made (including by means of contractual arrangements).
(4)Condition C is met if any electric line or electric plant provided for the purpose of making the first connection is used for the purpose of making another connection (the “second connection”)—
(a)between premises and a distribution system, or
(b)between two distribution systems.
(5)Condition D is met if the second connection is made within the prescribed period after the first connection was made.
(6)“First connection expenses” are any expenses reasonably incurred by a person in providing any electric line or electric plant for the purpose of making the first connection.
(7)It does not matter whether the first connection, or the second connection, is made by an electricity distributor or a person of another description.
2(1)The “reimbursement powers” are—
(a)the power to demand a reimbursement payment from—
(i)a person requiring the second connection in pursuance of section 16(1), or
(ii)a person who otherwise causes the second connection to be made (including by means of contractual arrangements); and
(b)the power to apply the reimbursement payment in making such payments as may be appropriate towards reimbursing any persons for any payments they were previously required to make in respect of first connection expenses (whether that requirement arose by virtue of paragraph (a) or otherwise).
(2)A “reimbursement payment” is a payment, of such amount as may be reasonable in all the circumstances, in respect of first connection expenses.
3(1)The Secretary of State must consult the Authority before making regulations under this Schedule.
(2)Regulations under this Schedule may make provision requiring relevant electricity distributors to exercise a reimbursement power (whether in all cases or in cases provided for in the regulations).
(3)Regulations under this Schedule may make provision for the relevant electricity distributor to establish or estimate the amount of first connection expenses — or an amount of any aspect of those expenses — in cases where that distributor is not the person who made the first connection.
(4)Regulations under sub-paragraph (3) may not require any person to supply the relevant electricity distributor with information about any expenses incurred.
(5)Regulations under sub-paragraph (3) may provide for an estimate of an amount of first connection expenses to be calculated by a relevant electricity distributor by reference only to a combination of—
(a)expenses which that distributor would incur if that distributor were making the connection at the time of the estimate, and
(b)changes in prices since the time when the connection was actually made.
4(1)In this Schedule—
“first connection” has the meaning given in paragraph 1;
“first connection expenses” has the meaning given in paragraph 1;
“reimbursement payment” has the meaning given in paragraph 2;
“reimbursement powers” has the meaning given in paragraph 2;
“relevant electricity distributor”, in relation to the exercise of a reimbursement power, means—
in a case where the first connection was made between premises and a distribution system, the electricity distributor that (at the time of the exercise of the power) operates that distribution system;
in a case where the first connection was made between two distribution systems, the electricity distributor that (at the time of the exercise of the power) operates the distribution system into which the first connection has been, or is expected to be, incorporated.
(2)A reference in this Schedule to a payment in respect of first connection expenses includes a reference to such a payment made in pursuance of section 19(1).”
(4)In section 16 (duty to connect on request), in subsection (4), after “23” insert “ and Schedule 5B ”.
(5)In section 16A (procedure for requiring a connection), in subsection (5)(b)—
(a)omit “or regulations under section 19(2)”;
(b)after “19(2)” insert “ or regulations under Schedule 5B ”.
(6)In section 23 (determination of disputes)—
(a)after subsection (1) insert—
“(1ZA)This section also applies to any dispute arising under regulations under Schedule 5B between—
(a)an electricity distributor, and
(b)a person in respect of whom the electricity distributor exercises the reimbursement powers conferred by the regulations.”;
(b)after subsection (1C) insert—
“(1D)No dispute arising under regulations under Schedule 5B may be referred to the Authority after the end of the period of 12 months beginning with the time when the second connection (within the meaning of Schedule 5B) is made.”;
(c)after subsection (2) insert—
“(2A)Where a dispute arising under regulations under Schedule 5B falls to be determined under this section, the Authority may give directions as to the circumstances in which, and the terms on which, an electricity distributor is to make or (as the case may be) to maintain the second connection (within the meaning of Schedule 5B) pending the determination of the dispute.”;
(d)in subsection (4), after “(2)” insert “ , (2A) ”.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
Y Ddeddf Gyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Testun a grëwyd gan yr adran o’r llywodraeth oedd yn gyfrifol am destun y Ddeddf i esbonio beth mae’r Ddeddf yn ceisio ei wneud ac i wneud y Ddeddf yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol. Cyflwynwyd Nodiadau Esboniadol ym 1999 ac maent yn cyd-fynd â phob Deddf Gyhoeddus ac eithrio Deddfau Adfeddiannu, Cronfa Gyfunol, Cyllid a Chyfnerthiad.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys