![Close](/images/chrome/closeIcon.gif)
Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 202
![Help about opening options](/images/chrome/helpIcon.gif)
![Close](/images/chrome/closeIcon.gif)
Llinell Amser Newidiadau
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 03/02/2017.
Changes to legislation:
Housing and Planning Act 2016, Section 202 is up to date with all changes known to be in force on or before 16 February 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.![Help about Changes to Legislation](/images/chrome/helpIcon.gif)
![Close](/images/chrome/closeIcon.gif)
Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
202Extension of compulsory purchase time limit during challengeE+W
This
adran has no associated
Nodiadau Esboniadol
(1)After section 4 of the Compulsory Purchase Act 1965 (time limit for giving notice to treat) insert—
“4AExtension of time limit during challenge
(1)If an application is made under section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order), the three year period mentioned in section 4 is to be extended by—
(a)a period equivalent to the period beginning with the day the application is made and ending on the day it is withdrawn or finally determined, or
(b)if shorter, one year.
(2)An application is not finally determined for the purposes of subsection (1)(a) if an appeal in respect of the application—
(a)could be brought (ignoring any possibility of an appeal out of time with permission), or
(b)has been made and not withdrawn or finally determined.”
(2)After section 5A of the Compulsory Purchase (Vesting Declarations) Act 1981 (time limit for general vesting declaration) insert—
“5BExtension of time limit during challenge
(1)If an application is made under section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order), the three year period mentioned in section 5A is to be extended by—
(a)a period equivalent to the period beginning with the day the application is made and ending on the day it is withdrawn or finally determined, or
(b)if shorter, one year.
(2)An application is not finally determined for the purposes of subsection (1)(a) if an appeal in respect of the application—
(a)could be brought (ignoring any possibility of an appeal out of time with permission), or
(b)has been made and not withdrawn or finally determined.”