The Greenhouse Gas Emissions Trading Scheme (Amendment) and National Emissions Inventory Regulations 2005

PART 3U.K.PROJECT APPROVAL AND AUTHORISATION TO PARTICIPATE

Approval of and authorisation of participation in project activitiesU.K.

5.—(1) [F1Subject to regulation 8A, a person wishing to be] to have a proposed project activity approved shall, in accordance with this regulation, apply to the Secretary of State for approval of the proposed project activity.

(2) [F1Subject to regulation 8A, a person wishing to be] to be authorised to participate in an Article 6 project activity shall, in accordance with this regulation, apply to the Secretary of State for such authorisation.

(3) An application under this regulation shall be made in the English language and shall contain the following information—

(a)the applicant’s name and address;

(b)a description of the project activity or proposed project activity; and

(c)any other information that the Secretary of State may require for the purpose of determining the application.

(4) Any application made under this regulation shall be made in such form as may be required by the Secretary of State.

(5) The Secretary of State may require any information included in an application under this regulation to be independently verified and a requirement under this paragraph may include a requirement for the verification to be provided by a person of a description specified by the Secretary of State.

(6) An application under paragraph (2) may be combined with an application under paragraph (1).

(7) An application made under this regulation may be withdrawn at any time before it is determined.

[F2(8) Subject to paragraph (9), an application under paragraph (1) or (2) must be accompanied by the fee set out in paragraph (10) of this regulation where that application is submitted on or before 6th April 2012.

(9) No fee is required where the application relates to a proposed project activity in one of the countries listed in the Schedule to these Regulations (List of Least Developed Countries).

(10) The fee which must be paid under paragraph (8) is—

(a)£700 for an application in respect of a proposed Article 6 project activity;

(b)£700 for an application in respect of a proposed Article 12 project activity for the production of hydro-electric power with a generating capacity of more than 20 megawatts;

(c)£250 for an application in respect of any other proposed Article 12 project activity.] 

Request for further informationU.K.

6.—(1) For the purposes of determining an application made under regulation 5, the Secretary of State may serve a notice on the applicant requesting further information as she considers necessary.

(2) The notice shall specify the information required and the time period for furnishing such further information.

(3) A notice under paragraph (1) may include a requirement for information furnished in connection with an application under regulation 5 to be independently verified and a requirement under this paragraph may include a requirement for the verification to be provided by a person of a description specified by the Secretary of State.

(4) If an applicant fails to comply with a request under paragraph (1), the Secretary of State may serve a notice on the applicant stating that the application is deemed to have been withdrawn.

Determination of applicationU.K.

7.—(1) Where an application is duly made under regulation 5 the Secretary of State shall determine whether to approve the proposed project activity or to authorise the participation in accordance with this regulation.

(2) When determining an application duly made under regulation 5, the Secretary of State may attach such conditions to an approval or authorisation as she thinks necessary.

(3) The Secretary of State shall give notice of her determination to the person who made the application within a period of two months beginning on the date on which the application was received or within such longer period as may be agreed in writing with the applicant.

(4) For the purposes of calculating the period of two months mentioned in paragraph (3), no account shall be taken of any period beginning on the date on which notice is served under regulation 6(1) and ending on the date on which the applicant furnishes the further information.

(5) The Secretary of State may not approve a proposed project activity to be carried out in the United Kingdom.

(6) The Secretary of State may only approve a proposed project activity if she is satisfied that—

(a)where a proposed project activity is to be undertaken in a country which has signed a Treaty of Accession with the European Union, the baseline used for determining the emissions reductions from the project activity complies with the body of common rights and obligations which binds all Member States within the European Union, including the temporary derogations set out in that Treaty; and

(b)in relation to a proposed project activity for the production of hydro-electric power with a generating capacity of more than 20 megawatts, the development of the proposed project activity will respect the criteria and guidelines identified in the Report produced by the World Commission on Dams on 16th November 2000 entitled “Dams and Development – A New Framework for Decision-Making(1)”.

(7) The Secretary of State may only authorise the applicant’s participation in a proposed project activity if she is satisfied that to do so would be consistent with article 11b(5) of the Emissions Trading Directive.

Agreement with devolved administrations on project approvalU.K.

8.  The power of the Secretary of State to determine an application under regulation 7 is exercisable—

(a)in so far as an application under regulation 5(1) relates to a Scottish applicant, only with the agreement of the Scottish Ministers;

(b)in so far as an application under regulation 5(1) relates to a NI applicant, only with the agreement of the Department of the Environment; and

(c)in so far as an application under regulation 5(1) relates to a Welsh applicant, only with the agreement of the National Assembly for Wales.

[F3Exercise of Functions by the Environment AgencyU.K.

8A.(1) On or after 1st June 2011 applications under regulation 5 must be submitted to the Environment Agency.

(2) Subject to paragraphs (3) and (4), the functions of the Secretary of State under regulations 5, 6, 7 and 8 of these Regulations in respect of any such application submitted on or after 1st June 2011 must be exercised by the Environment Agency and in such a case the references to the Secretary of State in regulations 5, 6, 7 and 8 of these Regulations should be read as references to the Environment Agency.

(3) The Environment Agency must consult the Secretary of State as soon as reasonably practicable before determining—

(a)an application under regulation 5 in relation to a proposed Article 6 project activity which is not of a type—

(i)which has been approved by the Secretary of State or the Environment Agency on or before the date on which the application is submitted; or

(ii)in respect of which participation has been authorised by the Secretary of State or the Environment Agency on or before the date on which the application is submitted;

(b)an application under regulation 5 in relation to any proposed project activity which the Environment Agency reasonably considers to be novel, contentious or controversial;

(c)an application under regulation 5 in relation to any proposed project activity for the production of hydro-electric power with a generating capacity of more than 20 megawatts.

(4) The Secretary of State may require the Environment Agency to refer an application under regulation 5 to the Secretary of State for the Secretary of State to decide in accordance with this Part.]

AppealsU.K.

9.—(1) A person may appeal to the Secretary of State against the refusal of an application made under regulation 5 or against any conditions attached to an approval or authorisation notified under regulation 7.

(2) Where an appeal is made under this regulation, the Secretary of State may affirm, reverse or vary her decision.

(3) Schedule 2 of the 2005 Regulations shall apply in relation to an appeal under this regulation as if—

(a)the reference to “regulation 32 or 33” in paragraph 1 of that Schedule were to this regulation;

(b)references to “appeal body” were to the Secretary of State;

(c)paragraph 2(1) contained a new paragraph (h) as follows—

(h)in the case of an appeal under regulation 9(1) of the Greenhouse Gas Emissions Trading Scheme (Amendment) and National Emissions Inventory Regulations 2005, before the expiry of 6 months beginning with the date of the notice which is the subject matter of the appeal.; and

(d)the references to “regulation 33” in paragraph 3(2) and (6) were to this regulation.

(4) The Secretary of State may—

(a)appoint any person to exercise on her behalf, with or without payment, the function of determining an appeal under this regulation or any matter or question involved in such an appeal; or

(b)refer any matter or question involved in an appeal under this regulation to such person as she may appoint for the purpose, with or without payment.

(5) Schedule 3 of the 2005 Regulations shall have effect with respect to appointments under paragraph (4)(a) as if references in paragraph 1 of that Schedule to “regulation 34(2)(a)” were references to paragraph (4)(a) of this regulation.

(1)

ISBN 1 85383 798 9.