Chwilio Deddfwriaeth

The Greenhouse Gas Emissions Trading Scheme Regulations 2005 (revoked)

Changes over time for: Section 22

 Help about opening options

Version Superseded: 31/12/2007

Status:

Point in time view as at 01/01/2012. This version of this provision has been superseded. Help about Status

Close

Status

You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.

Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.

Changes to legislation:

There are currently no known outstanding effects for the The Greenhouse Gas Emissions Trading Scheme Regulations 2005 (revoked), Section 22. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Application for an allocation from the new entrant reserve

This adran has no associated Memorandwm Esboniadol

22.—(1) Where an approved national allocation plan provides for a new entrant reserve in the scheme phase to which it relates, an operator of an installation may apply to the regulator for an allocation of allowances in respect of that installation from the new entrant reserve.

[F1(1A) However, an operator of an installation may not apply to the regulator under paragraph (1) for an allocation of allowances in respect of the production of nitric acid if any such production has been carried out at the installation prior to 30th June 2010.]

(2) Subject to paragraph (3), an application under paragraph (1) shall be combined with an application for a greenhouse gas emissions permit under regulation 8(1) or an application for a variation of a greenhouse gas emissions permit under regulation 14(2).

(3) Paragraph (2) shall not apply where an application under paragraph (1) relates to—

(a)an installation in respect of which an operator made an application for a greenhouse gas emissions permit under regulation 8(1) before the date on which the approved NAP Regulations enter into force; or

(b)a change in operation in respect of which an operator made an application for a variation of a greenhouse gas emissions permit under regulation 14(2) before the date on which the approved NAP Regulations enter into force.

(4) An application under paragraph (1) shall contain such information as the regulator may reasonably require for the purpose of determining the application in accordance with the provisions of the approved national allocation plan and, except where paragraph F2... (7) applies, shall be accompanied by the fee prescribed in Schedule 5 in respect of such application.

F3(5) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F3(6) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(7) Where an application under paragraph (1)F4...relates to an offshore installation, the fee prescribed in Schedule 5 in respect of the application shall be payable within the period of 28 days beginning on the date on which the regulator serves a notice on the operator requesting payment of the fee.

(8) If an operator fails to comply with paragraph (7) the regulator may refuse the application.

(9) The regulator may, by notice to the applicant, require him to furnish such further information specified in the notice, within the period so specified, as the regulator may require for the purpose of determining the application and if the applicant fails to furnish the specified information within the period specified, the application shall, if the regulator gives notice to the applicant that it treats the application as having been withdrawn, be deemed to have been withdrawn at the end of that period.

[F5(10) Subject to paragraph (11), the regulator must give notice under paragraph (13) of its determination of an application under paragraph (1) within a period of two months beginning on the date on which the application is received by the regulator, or within such longer period as may be agreed in writing by the applicant.]

(11) For the purposes of calculating the period of two months mentioned in paragraph (10) no account shall be taken of—

(a)any period beginning with the date on which notice is served on the applicant under paragraph (9) and ending on the date on which the applicant furnishes the information specified in the notice;

(b)any period beginning with the date on which notice is served on the applicant under regulation 8(5) or 14(6) in respect of an application with which an application under paragraph (1) is combined in accordance with paragraph (2).

(12) If the regulator fails to give notice of its determination of an application under paragraph (1) within the period allowed by paragraph (10), the application shall, if the operator notifies the regulator that it treats the application as having been refused, be deemed to have been refused.

(13) Where an application under paragraph (1) is duly made to the regulator, the regulator shall, in accordance with the provisions of the approved national allocation plan—

(a)determine the eligible allocation subject to such conditions as the regulator considers appropriate to comply with the approved national allocation plan;

(b)determine the eligible allocation and, subject to paragraph (14), allocate allowances to the operator in respect of the installation to which the application relates; or

(c)reject the application,

by serving a notice on the operator and, in the case of a determination under sub-paragraph (b), on the registry administrator.

(14) Where the eligible allocation is greater than the number of available allowances, a notice under paragraph (13)(b) shall allocate the available allowances and the regulator may make additional allocations of allowances under paragraph (13)(b) if additional allowances subsequently become available in the new entrant reserve in accordance with the approved national allocation plan until the number of allowances allocated under paragraph (13)(b) equals the eligible allocation.

(15) A notice under paragraph (13)(a) shall–

(a)specify the conditions applying to the determination;

(b)require the operator to notify the regulator if any of the information provided in the application or provided to the regulator in response to a request for further information under paragraph (9) changes; and

(c)where the approved national allocation plan provides for allowances from the new entrant reserve to be reserved for an installation in respect of which an application under paragraph (1) has been made, indicate whether, and, if so, how many allowances have been reserved in respect of the installation.

(16) Where it appears to the regulator, whether as a result of a notification in accordance with a condition imposed pursuant to paragraph (13)(a) or otherwise, that the approved national allocation plan requires a variation of any of the provisions of the notice served on the operator under paragraph (13)(a), the regulator shall serve a further notice under paragraph (13)(a) on the operator varying the provisions of the previous notice.

(17) Where it appears to the regulator, whether as a result of a notification in accordance with a condition imposed pursuant to paragraph (13)(a) or otherwise, that it would no longer be consistent with the approved national allocation plan for an allocation of allowances to be made in respect of an installation to which a notice under paragraph (13)(a) relates, the regulator shall serve a further notice on the operator rejecting the application.

(18) Subject to paragraph (19), where the regulator is satisfied that all the conditions specified in a notice under paragraph (13)(a) are met, the regulator shall serve a notice on the operator and the registry administrator allocating allowances in respect of the installation.

(19) Where the eligible allocation is greater than the number of available allowances, a notice under paragraph (18) shall allocate the available allowances and the regulator may make additional allocations of allowances under paragraph (18) if additional allowances subsequently become available in the new entrant reserve in accordance with the approved national allocation plan until the number of allowances allocated under paragraph (18) equals the eligible allocation.

(20) A notice under paragraph (13)(b) or (18) shall specify—

(a)the operator and installation identification code of the installation in respect of which the allocation is made and the permit identification code of the greenhouse gas emissions permit which relates to that installation;

(b)the allocation of allowances to the operator in respect of the installation including the number of allowances to be issued in each remaining year or part year of the phase in relation to which the allocation is made and the date on which the allowances will be issued in the year in which the notice is served.

(21) A notice under paragraph (13)(b) or (18) shall be an instruction to the registry administrator for the purposes of [F6the automatic national allocation plan table change process in] [F7Article 37(1) and 40(3)] of the Registries Regulation.

(22) Where an application under regulation 15(1) specifies that an application under paragraph (1) in respect of the installation relates to the transferred unit, any allocation of allowances under paragraph (13)(b) or (18) made after the transfer takes effect shall be allocated to the proposed transferee.

(23) For the purposes of this regulation—

eligible allocation” means the amount of allowances which may be allocated in respect of an installation under the provisions of the approved national allocation plan subject to the number of available allowances;

available allowances” means allowances in the new entrant reserve which are available for allocation in accordance with the approved national allocation plan;

[F8“new entrant reserve” does not include any late installation element (as defined in an approved national allocation plan) of the new entrant reserve;]

proposed transferee” and “transferred unit” shall have the same meaning as in regulation 15(1) and (4).

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill