Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
9.—(1) Subject to paragraph 10, a notified body shall assess an application made by a manufacturer for the issue of—
(a)a certificate of conformity;
(b)a design or type examination certificate; or
(c)a notification of approval of the manufacturer's quality system,
in accordance with the Annex applicable to the relevant conformity assessment procedure in respect of a beltweigher.
(2) In determining such an application, the notified body—
(a)shall have regard to the actual or usual environment of the beltweigher; and
(b)may have regard to any other standards or other technical criteria appearing to it to be relevant.
(3) Where, in the opinion of the notified body, the beltweigher to which an application relates is compliant with the essential requirements, it shall issue a certificate or notification in accordance with paragraph 12.
(4) Where, in the opinion of the notified body, the beltweigher to which the application relates is not compliant with the essential requirements, it shall issue a notice to the applicant in accordance with paragraph 15.
(5) Where a certificate or notification under sub-paragraph (3) is issued by a United Kingdom notified body, it shall send a copy to the Secretary of State.
10.—(1) A notified body shall not accept an application for a certificate or notification in respect of a beltweigher unless the application—
(a)is in writing, in English or another language acceptable to that notified body;
(b)is accompanied by all relevant documentation, in which all writing is in English or another language acceptable to that notified body; and
(c)includes particulars of which applicable standards the manufacturer has applied or proposes to apply in respect of the instrument.
(2) A notified body shall not be required to determine an application for a certificate or notification where the manufacturer has not—
(a)granted the notified body access to an instrument to which the application relates or the production facilities for the instrument (including, where applicable, the production facilities envisaged in relation to a representative instrument) to the extent that the notified body reasonably requests; and
(b)made available to the notified body such information as it may reasonably require to determine the application.
(3) A notified body shall not be required to carry out the functions referred to in regulation 7(4) (d) if—
(a)the person making the application has not submitted with the application the amount of the fee which the notified body requires to be submitted with the application pursuant to regulation 11; or
(b)the notified body reasonably believes that, having regard to the number of applications made to it pursuant to its designation which are outstanding, it will be unable to commence the required work within three months of receiving the application.
11.—(1) A notified body may, in exercising its functions—
(a)arrange for some other person to carry out any test, assessment or inspection on its behalf; or
(b)require the applicant to satisfy another person with respect to any matter at the applicant's expense.
(2) But nothing in sub-paragraph (1) authorises a notified body to rely on the opinion of another person with regard to whether a beltweigher is compliant with any of the essential requirements.
(3) Nothing in these Regulations shall preclude a person referred to in sub-paragraph (1)(a) or (1)(b) from charging any fee in respect of any work undertaken by him in pursuance of those sub-paragraphs.
12. A certificate or notification issued by a notified body shall be in writing and, in addition to the requirements provided for in the relevant conformity assessment procedure, shall—
(a)be in English;
(b)give the name and address—
(i)of the applicant;
(ii)where the applicant is not the manufacturer, of the manufacturer;
(c)be signed by or on behalf of the notified body and give the identification number of the notified body;
(d)bear—
(i)the date of issue; and
(ii)the number of the certificate or notification;
(e)give particulars of the relevant beltweigher (where applicable, in relation to each variant) to which it relates sufficient to identify it, and shall state whether the instrument to which it relates is a single item or a representative, or if it covers a number of variants of that instrument; and
(f)certify that the instrument to which it relates is compliant with the essential requirements.
13.—(1) A certificate or notification may be unconditional or may be subject to such conditions as the notified body considers appropriate.
(2) Such conditions may include—
(a)a limitation on the environment for which the beltweigher is stated to be suitable; or
(b)a requirement that the instrument is only to be installed at a specific site.
(3) The conditions imposed pursuant to sub-paragraph (1) may be varied in accordance with paragraph 15 by the notified body which issued the certificate or notification and such variation may include the imposition of new conditions or the removal of conditions.
14. The notified body which issued the certificate or notification shall withdraw that certificate or notification in accordance with paragraph 15, if it appears that the beltweigher to which it relates is not compliant with the essential requirements.
15.—(1) Where a notified body is minded to—
(a)refuse to issue a certificate or notification;
(b)vary a certificate or notification (other than at the request of the person to whom it was given); or
(c)withdraw a certificate or notification,
it shall give to the applicant or the person to whom the certificate or notification was given a notice in writing—
(i)giving reasons for the refusal, variation or withdrawal;
(ii)specifying the date on which the refusal, variation or withdrawal is to take effect; and
(iii)giving the applicant or person the opportunity to make representations within 21 days from the date of the notice and stating that the notified body shall consider any representations made to it within that period by that applicant or person.
(2) Where a notified body, having considered representations made to it under sub-paragraph (1), remains of the opinion that—
(a)an application for a certificate or notification should be refused; or
(b)a certificate or notification should be varied or withdrawn,
it shall inform the applicant, or the person to whom the certificate or notification was given, of that decision in writing and give that applicant or person information about the judicial remedies available to him.
(3) Where a notice under sub-paragraph (1) is given by a United Kingdom notified body it shall send a copy of that notice to the Secretary of State.
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys