The Energy Performance of Buildings (Certificates and Inspections) (England and Wales) Regulations 2007

Power to require production of documentsE+W

This adran has no associated Memorandwm Esboniadol

39.—(1) An authorised officer of an enforcement authority may require a person who appears to him to be or to have been subject to any of the duties under regulation 5, 9(2), 10, 16(2), 21(1), or 23 to produce for inspection a copy of—

(a)a valid energy performance certificate and recommendation report;

(b)an advisory report; and

(c)an inspection report.

[F1(1A) An authorised officer of an enforcement authority may require a person who appears to him to have been subject to the duty under regulation 5A(3) to produce for inspection a copy of any request made in accordance with regulation 5A(5)(d).]

(2) [F2The powers conferred by paragraphs (1) and (1A) include] power to take copies of any document produced for inspection.

(3) A requirement under this regulation may not be imposed more than six months after the last day on which the person concerned was subject to such a duty in relation to the building.

(4) It is the duty of a person subject to such a requirement to comply with it within the period of seven days beginning with the day after that on which it is imposed.

(5) A person is not required to comply with such a requirement if he has a reasonable excuse for not complying with the requirement.