Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Regulation 25
Regulation 35(n)
1. This Schedule applies in relation to every mining waste operation.
2.—(1) In this Schedule—
“relevant emergency planner” means, in relation to an application for a mining waste facility that is located in—
London, the London Fire and Emergency Planning Authority;
an area where there is a fire and civil defence authority, that authority;
the Isles of Scilly, the Council of the Isles of Scilly;
an area in the rest of England, the county council for that area or where there is no county council for that area, the district council for that area;
an area in Wales, the county council or county borough council for that area.”;
“waste management plan” means a plan of the type described in Article 5(1) of the Mining Waste Directive which has the objectives in Article 5(2) and contains the elements and information set out in Article 5(3) of that Directive.
(2) When interpreting the Mining Waste Directive for the purposes of this Schedule—
(a)except where otherwise defined in this paragraph, an expression defined in Part 1 of these Regulations has the meaning given in that Part;
(b)“permit” means an environmental permit; and
(c)the competent authority is the regulator.
3.—(1) The regulator must require that every application for the grant or variation of an environmental permit in relation to a mining waste operation involving a mining waste facility to which Article 7 of the Mining Waste Directive applies includes—
(a)the information specified in Article 7(2) of that Directive; and
(b)where Article 6 of the Directive applies, the information mentioned in the second sentence of the third paragraph of Article 6(3).
(2) Where the regulator receives an application for the grant or variation of an environmental permit and that application includes the information required under sub-paragraph (1)(b), the regulator must immediately forward the information to the relevant emergency planner.
(3) The regulator must require that every application for the grant or variation of an environmental permit in relation to any other mining waste operation includes a waste management plan.
(4) For the purposes of this paragraph, the regulator may accept a waste management plan produced pursuant to other legislation which complies with Articles 5(1) to (4) of the Mining Waste Directive if it has been reviewed and amended in accordance with Article 5(4) of that Directive.
(5) In this paragraph—
“application for the grant of an environmental permit” means an application made under regulation 13(1) of these Regulations;
“application for the variation of an environmental permit” means an application made by an operator under regulation 20(1) of these Regulations.
4. The regulator must periodically review an environmental permit relating to a mining waste facility if Article 7 of the Mining Waste Directive applies in respect of that facility and any of the circumstances in Article 7(4) of the Directive apply in relation to it.
5. The regulator must exercise its functions so as to ensure compliance with Article 9 of the Mining Waste Directive in respect of any mining waste facility to which Article 7 does not apply.
6. The regulator must inspect every mining waste facility to which Article 7 of the Mining Waste Directive applies so as to comply with the requirements of Article 17(1) of that Directive.
7. The regulator must exercise its relevant functions so as to ensure compliance with the following requirements of the Mining Waste Directive—
(a)Article 2(4);
(b)Article 4;
(c)Article 5(4) and (6);
(d)Article 6(2), the first and second paragraphs of Article 6(3), the first paragraph of Article 6(4) to the extent that it relates to plans prepared under the first paragraph of Article 6(3) and the second paragraph of Article 6(4) to the extent that it relates to the regulator's functions;
(e)Article 7(1) and Article 7(3)(a);
(f)Article 10;
(g)Article 11;
(h)Article 12;
(i)Article 13;
(j)Article 14 (1) to (3);
(k)Article 17(2);
(l)Article 24(1).
8.—(1) The regulator must exercise its functions under the public participation provisions in relation to mining waste facilities to which Article 7 of the Mining Waste Directive applies so as to meet the requirements of Article 8 of that Directive.
(2) In this paragraph, “public participation provisions” means regulations 26, 29 and 59, and paragraphs 6 and 8 of Schedule 5 to these Regulations.
9.—(1) The regulator must exercise its functions to ensure that the requirements mentioned in the first paragraph of Article 2(3) of the Mining Waste Directive do not apply to the substances mentioned in that paragraph where they result from an operation mentioned in that paragraph, to the extent allowed by that paragraph.
(2) The regulator must waive the requirements of the Mining Waste Directive in relation to the deposit of the substances mentioned in the second paragraph of Article 2(3) of that Directive as long as the regulator is satisfied that the requirements of Article 4 of that Directive are met.
(3) The regulator must waive the requirements mentioned in the third paragraph of Article 2(3) of the Mining Waste Directive in relation to the waste mentioned in that paragraph to the extent allowed by that paragraph.
10.—(1) The regulator must set out any reasoned decision under Article 12(2)(c) of the Mining Waste Directive in a closure notice served on the operator.
(2) A closure notice must, in addition to stating the regulator's reasons for requiring initiation of the closure procedure, specify —
(a)the steps the operator is required to take to initiate the procedure; and
(b)the period within which they must be taken.
(3) The regulator may withdraw a closure notice at any time by further notice served on the operator.
(4) Closure of a mining waste facility does not relieve the operator of liability under the conditions of the environmental permit in relation to the facility.
(5) The regulator must exercise its functions so as to ensure compliance with Article 14(4) of the Mining Waste Directive.
11. The regulator must maintain and make available to the public an inventory of closed mining waste facilities so as to ensure compliance with Article 20 of the Mining Waste Directive.
12.—(1) The regulator must ensure that it is informed of developments in best available techniques.
(2) In this paragraph, “best available techniques” has the meaning given in Article 2(11) of the IPPC Directive.
13.—(1) Following an application under regulation 13(1), the regulator must not grant an environmental permit in relation to a mining waste facility to which Article 7 applies if use of the site as a mining waste facility requires a planning permission and no such permission is in force.
(2) Where—
(a)a mining waste operation is the subject of an environmental permit;
(b)that operation has been granted planning permission subject to conditions (“planning conditions”), and
(c)there is an inconsistency between the conditions imposed by the environmental permit (“environmental permit conditions”) and those imposed by the planning conditions,
the environmental permit conditions prevail.
(3) In this paragraph, “planning permission” means planning permission under the Town and Country Planning Act 1990 M1 and includes—
(a)a certificate under section 191 of that Act, and
(b)an established use certificate under section 192 of that Act, as originally enacted, which continues to have effect for the purposes of subsection (4) of that section.
14.—(1) The regulator must not grant an application for an environmental permit relating to a Category A mining waste facility until it has been notified by the relevant emergency planner that it has the information necessary to enable it to draw up an external emergency plan.
(2) The regulator must refuse an application for an environmental permit relating to a Category A mining waste facility that is an existing mining waste facility upon receipt of a notice by the relevant emergency planner stating that the operator has not provided the information necessary to enable the relevant emergency planner to draw up an external emergency plan.
(3) In this paragraph, “external emergency plan” means a plan as required under the third paragraph of Article 6(3) of the Mining Waste Directive that has the objectives specified in the first paragraph of Article 6(4) of that Directive.”
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys