Chwilio Deddfwriaeth

The Building Regulations 2010

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

 Help about opening options

Dewisiadau AgorExpand opening options

Changes over time for: Section 44

 Help about opening options

Status:

Point in time view as at 25/04/2024. There are multiple versions of this provision on screen. These apply to different geographical extents. Help about Status

Changes to legislation:

There are currently no known outstanding effects for the The Building Regulations 2010, Section 44. Help about Changes to Legislation

CommissioningE

This adran has no associated Memorandwm Esboniadol

44.—(1) This regulation applies to building work in relation to which paragraph F1(2) of Schedule 1 imposes a requirement, but does not apply to the provision or extension of any fixed system for mechanical ventilation or any associated controls where testing and adjustment is not possible.

(2) This regulation also applies to building work in relation to which paragraph L1(b) of Schedule 1 imposes a requirement, but does not apply to the provision or extension of any fixed building service where testing and adjustment is not possible or would not affect the energy efficiency of that fixed building service.

(3) Where this regulation applies the person carrying out the work shall, for the purpose of ensuring compliance with paragraph F1(2) or L1(b) of Schedule 1, give to the [F1building control authority] a notice confirming that the fixed building services have been commissioned in accordance with a procedure approved by the Secretary of State.

[F2(4) The notice must be given—

(a)in the case where the building work is higher-risk building work for which an application for a completion certificate is required, to the regulator with the application;

(b)in any other case, to the building control authority—

(i)not later than the date on which the notice required by regulation 16(4) is required to be given; or

(ii)where that regulation does not apply, not more than 30 days after completion of the work.

(5) Where the regulator is the building control authority by virtue of section 91ZB of the Act (the regulator: building control authority for other work), it must send a copy of each notice it receives under this regulation in relation to a building to the local authority for the area in which the building is situated.]

Extent Information

E1This version of this provision applies to England only; a separate version has been created for Wales only

Textual Amendments

Modifications etc. (not altering text)

CommissioningW

44.—(1) This regulation applies to building work in relation to which paragraph F1(2) of Schedule 1 imposes a requirement, but does not apply to the provision or extension of any fixed system for mechanical ventilation or any associated controls where testing and adjustment is not possible.

(2) This regulation also applies to building work in relation to which paragraph L1(b) of Schedule 1 imposes a requirement, but does not apply to the provision or extension of any fixed building service where testing and adjustment is not possible or would not affect the energy efficiency of that fixed building service.

(3) Where this regulation applies the person carrying out the work shall, for the purpose of ensuring compliance with paragraph F1(2) or L1(b) of Schedule 1, give to the local authority a notice confirming that the fixed building services have been commissioned in accordance with a procedure approved by the Secretary of State.

(4) The notice shall be given to the local authority—

(a)not later than the date on which the notice required by regulation 16(4) is required to be given; or

(b)where that regulation does not apply, not more than 30 days after completion of the work.

Extent Information

E2This version of this provision applies to Wales only; a separate version has been created for England only

Modifications etc. (not altering text)

C4Reg. 44 applied (with modifications) (1.10.2010) by The Building (Approved Inspectors etc.) Regulations 2010 (S.I. 2010/2215), regs. 1, 20(1)(6) (as amended (W.) (25.4.2024) by S.I. 2024/447, regs. 1(1), 3(h)(j) (with reg. 6))

Yn ôl i’r brig

Options/Cymorth

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?