Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Preliminary accreditationE+W+S

This adran has no associated Memorandwm Esboniadol

9.[F1(1) This article applies where a person (“the prospective FIT generator”)—

(a)proposes to construct or operate an eligible installation (other than an extension) which, when commissioned, will—

(i)use anaerobic digestion;

(ii)be a hydro generating station; or

(iii)be a wind or solar photovoltaic installation, and have a declared net capacity of more than 50 kilowatts; and

(b)makes an application in writing to the Authority for preliminary accreditation, which is received by the Authority on or before 30th September 2015] [F2or on or after 8th February 2016] [F3but on or before 31st March 2019].

(2) [F4Subject to article 8B, the] Authority must, [F5upon receiving the application referred to in paragraph (1)(b),] grant preliminary accreditation in respect of that installation if the Authority is satisfied that—

(a)the conditions in paragraphs (3) and (4) are met; and

(b)the installation would, if commissioned, receive accreditation under Chapter 1 of this Part were an application to be made for such accreditation [F6and, for this purpose, applications for preliminary accreditation are to be considered under article 5(1A)(a) in the same way as applications for the accreditation of eligible installations mentioned in that sub-paragraph.]

(3) The conditions in this paragraph are that the application for preliminary accreditation—

(a)specifies—

(i)the eligible low-carbon energy source to be used by the installation;

(ii)the total installed capacity and declared net capacity of the installation;

(iii)the location of the installation;

(iv)whether the installation is to have a grid connection;

[F7(v)where the installation will be a solar photovoltaic installation with a total installed capacity of 250kW or more, whether or not the installation will be stand-alone solar photovoltaic;]

[F7(vi)whether or not the installation will be owned by a community organisation;]

(b)is accompanied by documentary evidence, issued on or before the date of the application, of the satisfaction of the conditions in paragraph (4); and

(c)includes such other information as may be required by the Authority.

(4) The conditions in this paragraph are that—

(a)either—

(i)planning permission has been granted for the installation on or before the date of the application for preliminary accreditation; or

(ii)the Authority is satisfied that planning permission is not required for the installation;

(b)if the installation is to have a grid connection, either—

(i)the prospective FIT generator has entered into a grid connection agreement on or before the date of the application; or

(ii)the Authority is satisfied that a grid connection agreement is not required for the grid connection of the installation;

(c)if the installation is a hydro generating station in England and Wales, the Authority is satisfied that each of the licences and consents mentioned in paragraph (5)—

(i)has been granted for the installation on or before the date of the application; or

(ii)is not required for the installation; F8...

(d)if the installation is a hydro generating station in Scotland, the Authority is satisfied that an authorisation under the Water Environment (Controlled Activities)(Scotland) Regulations 2011 M1 for each of the matters mentioned in paragraph (6)—

(i)has been granted for the installation on or before the date of the application; or

(ii)is not required for the installation[F9; and]

[F10(e)if the application for preliminary accreditation specifies that the installation will be owned by a community organisation, the installation will be so owned.]

(5) The licences and consents referred to in paragraph (4)(c) are—

(a)an abstraction licence under section 24 of the Water Resources Act 1991 M2;

(b)an impounding works licence under section 25 of the Water Resources Act 1991 M3; and

(c)consent under section 109(1) of the Water Resources Act 1991 M4.

(6) The matters referred to in paragraph (4)(d) are—

(a)abstraction;

(b)impounding works; and

(c)any other engineering works required for the installation.

(7) The Authority may attach such conditions as it considers appropriate in granting preliminary accreditation.

(8) [F11Subject to [F12paragraphs (8ZA) and (8A)],] preliminary accreditation shall be valid—

(a)for solar photovoltaic installations, for 6 months beginning with the date on which the application for preliminary accreditation was [F13treated as received] by the Authority;

(b)for wind and anaerobic digestion installations, for 1 year beginning with the date on which the application for preliminary accreditation was [F13treated as received] by the Authority; and

(c)for hydro generating stations, for 2 years beginning with the date on which the application for preliminary accreditation was [F13treated as received] by the Authority.

[F14(8ZA) Where under paragraph (8)(b) or (c) preliminary accreditation would otherwise cease to be valid on or after 1st March 2020, preliminary accreditation shall be valid—

(a)for wind and anaerobic digestion installations, for 24 months beginning with the date on which the application for preliminary accreditation was treated as received by the Authority; and

(b)for hydro generating stations, for 36 months beginning with the date on which the application for preliminary accreditation was treated as received by the Authority.]

[F15(8A) [F16Subject to paragraph (8AA), where] the installation will be owned by a community organisation, preliminary accreditation shall be valid—

(a)for solar photovoltaic installations, for 12 months;

(b)for wind and anaerobic digestion installations, for 18 months; and

(c)for hydro generating stations, for 30 months,

beginning with the date on which the application for preliminary accreditation was [F17treated as received] by the Authority.]

[F18(8AA) Where under paragraph (8A) preliminary accreditation would otherwise cease to be valid on or after 1st March 2020, preliminary accreditation shall be valid—

(a)for solar photovoltaic installations, for 24 months beginning with the date on which the application for preliminary accreditation was treated as received by the Authority;

(b)for wind and anaerobic digestion installations, for 30 months beginning with the date on which the application for preliminary accreditation was treated as received by the Authority; and

(c)for hydro generating stations, for 42 months beginning with the date on which the application for preliminary accreditation was treated as received by the Authority.]

[F19(8B) For the purposes of paragraphs (8) [F20, (8ZA), (8A) and (8AA)], an application for preliminary accreditation is treated as received by the Authority on the date on which it is treated as received under article 8B(4)(a).]

(9) The Authority must give notice to the applicant of—

(a)its decision on an application for preliminary accreditation of an installation;

(b)where preliminary accreditation is granted—

(i)the dates on which the validity of the preliminary accreditation starts and ends;

(ii)the tariff date which will apply to the installation if it is accredited under article 10(2); and

(iii)any conditions attached to the preliminary accreditation, and the date on which they take effect; and

(c)where preliminary accreditation is refused, reasons for the refusal [F21and, where the reason for not granting preliminary accreditation is that article 8B applies, the date of the start of the next tariff period within which the application will be determined by the Authority in accordance with this article.]

(10) In this article—

grid connection agreement” means an agreement in writing with a transmission licence holder or distribution licence holder for the making of a grid connection; and “transmission licence holder or distribution licence holder” means the holder of a licence under section 6(1)(b) or 6(1)(c) of the 1989 Act M5;

planning permission” has the same meaning as in—

(a)

the Town and Country Planning Act 1990 M6, in relation to England and Wales;

(b)

the Town and Country Planning (Scotland) Act 1997 M7, in relation to Scotland.

Textual Amendments

F2Words in art. 9(1)(b) inserted (15.1.2016) by The Feed-in Tariffs (Amendment) (No. 3) Order 2015 (S.I. 2015/2045), arts. 1, 8(a) (with art. 24)

F4Words in art. 9(2) substituted (15.1.2016) by The Feed-in Tariffs (Amendment) (No. 3) Order 2015 (S.I. 2015/2045), arts. 1, 8(b) (with art. 24)

F7Art. 9(3)(a)(v)(vi) inserted (1.4.2015) by The Feed-in Tariffs (Amendment) Order 2015 (S.I. 2015/35), arts. 1, 4(a)

F8Word in art. 9(4)(c)(ii) omitted (1.4.2015) by virtue of The Feed-in Tariffs (Amendment) Order 2015 (S.I. 2015/35), arts. 1, 4(b)

F9Word in art. 9(4)(d) substituted (1.4.2015) by virtue of The Feed-in Tariffs (Amendment) Order 2015 (S.I. 2015/35), arts. 1, 4(c)

F13Words in art. 9(8) substituted (31.3.2016) by The Feed-in Tariffs (Amendment) Order 2016 (S.I. 2016/319), arts. 1, 4(4)(a)

F17Words in art. 9(8A) substituted (31.3.2016) by The Feed-in Tariffs (Amendment) Order 2016 (S.I. 2016/319), arts. 1, 4(4)(a)

Marginal Citations

M21991 c.57. Section 24 was amended by the Environment Act 1995 (c.25), Schedule 22, paragraph 128, the Water Act 2003, section 60(1), and S.I. 1996/593, Schedule 2, paragraph 8.

M31991 c.57. Section 25 was amended by the Water Act 2003, sections 2 and 60(1) and Schedule 9, Part 1.

M41991 c.57. Section 109(1) was amended by the Environment Act 1995 (c.25), Schedule 22, paragraph 128.

M5Section 6(1)(b) of the 1989 Act was substituted by the Energy Act 2004 (c.20), section 136(1). Section 6(1)(c) was substituted by the Utilities Act 2000 (c.27), section 30, and amended by the Energy Act 2004 (c.20), Schedule 23, Part 1.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill