- Y Diweddaraf sydd Ar Gael (Diwygiedig)
- Gwreiddiol (a wnaed Fel)
Dyma’r fersiwn wreiddiol (fel y’i gwnaed yn wreiddiol).
9. No person may carry out a regulated activity at an installation except to the extent authorised by a permit held by the operator of the installation.
10.—(1) The operator of an installation (other than an excluded installation) may apply to the regulator for a greenhouse gas emissions permit to carry out a regulated activity at the installation.
(2) The operator of an excluded installation may apply to the regulator for an excluded installation emissions permit to carry out a regulated activity at the installation.
(3) However, an application may not be made—
(a)under paragraph (1) or (2) where a permit has already been granted in respect of the installation and continues to have effect; or
(b)under paragraph (2) where an excluded installation emissions permit has been granted in respect of the installation and has been surrendered or revoked.
(4) Following an application under paragraph (1) or (2), the permit must be granted if the regulator is satisfied that—
(a)the application is duly made, and
(b)at the time that the permit is granted (or, if later, has effect) the applicant will be capable of monitoring and reporting emissions from the installation in accordance with—
(i)the monitoring and reporting requirements of the greenhouse gas emissions permit, or
(ii)the monitoring and reporting conditions of the excluded installations permit,
but must otherwise be refused.
(5) A permit may be granted under this regulation in respect of more than one installation on the same site, provided that they are operated by the same operator.
(6) Paragraph 1 of Schedule 4 makes further provision about applications for permits.
(7) Paragraph 2 of Schedule 4 makes provision about the contents of greenhouse gas emissions permits, and paragraph 3 of Schedule 5 makes provision about the contents of excluded installation emissions permits.
11.—(1) The regulator must review a permit before the end of the period of five years beginning with the date on which the permit was granted, and afterwards at intervals not exceeding five years.
(2) The regulator may, by giving notice to the operator, vary a permit at any time and may in particular make any variation of the permit that the regulator considers necessary in consequence of—
(a)a review under paragraph (1);
(b)any report made by the operator under Article 69 of the Monitoring and Reporting Regulation; or
(c)any notification as mentioned in paragraph 2(7)(b) of Schedule 4 (notification of planned changes in operation etc).
(3) The regulator may by giving notice to the operator vary a permit where the operator—
(a)applies to the regulator for such a variation pursuant to a provision of the permit; or
(b)has failed to comply with a requirement of the permit to apply for such a variation.
(4) The regulator may by giving notice to the operator vary a permit in order to comply with regulator’s duty under—
(a)regulation 88(6); or
(b)any of the following provisions of Schedule 5—
(i)paragraph 2(1);
(ii)paragraph 3(3);
(iii)paragraph 6(5) or (6);
(iv)paragraph 7(4)(b), (6)(b) or (7)(b);
(v)paragraph 8(6).
(5) A notice given under paragraph (2), (3)(b) or (4) may specify a period within which a fee for the variation of the permit must be paid.
(6) The regulator may by giving notice to the operator replace a permit with a consolidated permit applying to the same regulated activities, and containing the same or equivalent provisions, in the following circumstances—
(a)where the permit has been varied;
(b)where there is more than one permit applying to installations on the same site operated by the same operator.
12.—(1) Subject to paragraph (6), the holder of a permit (“the current operator”) and another person may jointly apply to the regulator for the permit to be transferred to that other person (“the new operator”).
(2) An application may also be made under paragraph (1) for the partial transfer of a permit; and for that purpose a “partial transfer” is a transfer in respect of—
(a)some only of the installations to which the permit relates; or
(b)some only of the parts of an installation to which the permit relates.
(3) Paragraph 3 of Schedule 4 makes further provision about the transfer, or partial transfer, of a permit.
(4) Subject to paragraph 3(2)(b) of Schedule 4, an application under paragraph (1) must be granted if the regulator is satisfied that—
(a)the application is duly made, and
(b)the new operator will (from the relevant date) be the operator of the installation and will be capable of monitoring and reporting emissions from the installation in accordance with—
(i)the monitoring and reporting requirements of the greenhouse gas emissions permit, or
(ii)the monitoring and reporting conditions of the excluded installations emissions permit,
but must otherwise be refused.
(5) For the purposes of paragraph (4), the relevant date is the date mentioned in paragraph 3(6), (8) or (10) of Schedule 4 as the case may be.
(6) An application for the transfer (or partial transfer) of a permit may not be made in respect of any installation (or part of an installation) that has ceased operation.
13.—(1) Subject to paragraph (4), if an installation has ceased operation the operator must apply to the regulator to surrender the permit authorising regulated activities at the installation.
(2) Such an application must be made within the period specified by paragraph (3), or such longer period as may be agreed with the regulator.
(3) The period specified is, in the case of an installation that has ceased operation by virtue of meeting the condition in—
(a)paragraph 7(1)(b) or (c) of Schedule 6, one month beginning with the date on which the installation ceased operation;
(b)paragraph 7(1)(d) of Schedule 6, one month following the end of the relevant period (as defined by paragraph 7(5) of that Schedule).
(4) The application need not be made where—
(a)the permit authorises regulated activities at more than one installation, some of which have not ceased operation; and
(b)by the end of the period mentioned in paragraph (2), the operator has applied to vary that permit so that it no longer applies to any of those installations that have ceased operation.
(5) Where the carrying out of regulated activities at an installation mentioned in paragraph (6) has been suspended, but the installation has not ceased operation, the operator may at any time make an application under paragraph (1) but is not obliged to do so.
(6) Those installations are—
(a)an excluded installation; or
(b)an installation that, by virtue of Article 10a(3) of the Directive, is not eligible for an allocation.
(7) If the application under paragraph (1) is granted, the notice of determination given to the operator (“notice of surrender”) takes effect on the date specified in the notice.
(8) Paragraph 4 of Schedule 4 makes further provision about the surrender of permits.
14.—(1) The regulator—
(a)may at any time revoke a permit by serving on the operator a notice to that effect (a “revocation notice”), and in particular may do so if the operator has failed to pay a fee for the subsistence of the permit; and
(b)must do so where the regulator becomes aware that the operator has failed to comply with regulation 13(1) to (3).
(2) A revocation notice takes effect—
(a)28 days after the date on which it is served; or
(b)if a later date is specified in the notice, on that date.
(3) Paragraph 5 of Schedule 4 makes further provision about the revocation of permits.
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys