The Rookery South (Resource Recovery Facility) Order 2011

Article 2

SCHEDULE 1AUTHORISED DEVELOPMENT AND REQUIREMENTS

PART 1AUTHORISED DEVELOPMENT

In Central Bedfordshire

  • A nationally significant infrastructure project as defined in sections 14(1)(a) and 15 of the 2008 Act comprising:

  • Work No. 1 An electricity generating station with a nominal gross electrical output capacity of 65 MWe fuelled by waste and including—

    (a)

    three waste processing streams each comprising a reciprocating grate, furnace, boiler and associated air pollution control system;

    (b)

    transformer compound;

    (c)

    an administration building;

    (d)

    a tipping hall;

    (e)

    refuse bunkering;

    (f)

    a flue gas treatment facility;

    (g)

    flues or stack;

    (h)

    turbines and turbine hall;

    (i)

    air cooled condensers;

    (j)

    a facility to enable steam pass-outs and/or hot water pass-outs; and

    (k)

    a visitor centre/education facility; and

    associated development within the meaning of section 115(2) of the Act comprising—

  • Work No. 2 A post-combustion materials recovery facility for the purpose of treating incinerator bottom ash produced by the electricity generating station comprised in Work No. 1 and including—

    (a)

    a screened ash/aggregate yard;

    (b)

    buildings housing apparatus and necessary plant for separation of co-mingled metals from incinerator bottom ash and grading of such ash;

    (c)

    a separation lagoon;

    (d)

    an administration building;

    (e)

    a weigh bridge; and

    (f)

    a foul water pump house;

  • Work No. 3 A drainage channel to be constructed on an east - west alignment linking with a drainage channel to be constructed pursuant to a review of old minerals permissions bearing statutory reference number BC/CM/2000/08;

  • Work No. 4 An extension to the attenuation pond to be constructed pursuant to a review of old minerals permissions bearing statutory reference number BC/CM/2000/08;

In the Borough of Bedford and in Central Bedfordshire

  • Work No. 5A A new access road commencing at the north-east corner of Work No. 2 and running in a Northerly direction to a new junction with Green Lane, Stewartby;

  • Work No. 5B A new access road commencing at the north-west corner of Work No. 1 and running in a Northerly direction to a junction with Work No. 5A;

  • Work No. 6A A grid connection consisting of one or more cables laid in a trench commencing at a point on the Northern side of Work No. 1 and running in a Northerly direction to the vicinity of the new junction with Green Lane created as part of Work No. 5A;

  • Work No. 6B A grid connection consisting of one or more cables laid beneath the Marston Vale Railway Line and connecting with Works No. 6A and 6C;

  • Work No. 6C A grid connection consisting of one or more cables connecting Work No. 6B to Work No. 6D at a point on Green Lane in the vicinity of the existing access to Stewartby Water Sports Club;

  • Work No. 6D A grid connection consisting of one or more cables laid in a trench on Green Lane Stewartby and connecting Work No. 6C to Works No. 6E and 6G at a point at the junction of Green Lane and Copart Access Road, Marston Moretaine;

  • Work No. 6E A grid connection consisting of one or more cables laid in a trench from the junction of Green Lane and the Copart Access Road, Marston Moretaine to the junction of the Copart Access Road and the C94;

  • Work No. 6F A grid connection laid consisting of one or more cables connecting Work No. 6E to the proposed Marston Grid Substation west of the A421 Trunk Road in Marston Moretaine;

  • Work No. 6G A grid connection consisting of one or more cables laid in a trench from the junction of Green Lane and the Copart Access Road, Marston Moretaine to the existing Marston Road Primary Substation;

  • Work No. 6H A grid connection consisting of one or more cables laid in a trench from the junction of Works No. 6F and 6E to the existing Marston Road Primary Substation;

  • Work No. 7A A work for the improvement of the entrance to the Marston Vale Millennium Country Park to the West of the Green Lane Level Crossing;

  • Work No. 7B A work for the creation of new site access works, including new footways to the East of Green Lane Level Crossing;

  • Work No. 7C A work comprising a footway and cycleway link crossing the new access road comprised in Work No. 5A and linking Green Lane and the circular path passing around Rookery North Pit to be constructed pursuant to a review of old minerals permissions bearing statutory reference number BC/CM/2000/08;

  • Work No. 8A An improvement to Green Lane comprising the improvement of the carriageway and footway including the provision of facilities for cyclists West of Green Lane Level Crossing;

  • Work No. 8B An improvement to Green Lane comprising the improvement of the carriageway and footway including the provision of facilities for cyclists East of Green Lane Level Crossing; and

  •   

  • Work No. 9 An improvement to Green Lane Level Crossing including a widening of the carriageway, alterations to footways and the installation of full barriers and associated improvements to Green Lane, Stewartby;

    and in connection with such works and to the extent that they do not otherwise form part of any such work, further associated development shown on the plans referred to in the requirements including—

    (a)

    weighbridges and security gatehouses;

    (b)

    internal site roads and vehicle parking facilities;

    (c)

    workshops and stores;

    (d)

    bunds, embankments, swales, landscaping and boundary treatments;

    (e)

    pipes for steam pass outs and/or hot water pass outs within the Order limits;

    (f)

    habitat creation;

    (g)

    the provision of footpaths, cycleways and footpath linkages;

    (h)

    water supply works, foul drainage provision, surface water management systems and culverting; and

    (i)

    whether or not shown on the plans referred to in the requirements, the demolition of all or part of the redundant conveyor structure within the Order limits.

PART 2REQUIREMENTS

Interpretation

In this Part of this Schedule—

“the approved development plans” mean the plans submitted with the application on 4 August 2010 or later and listed at requirement 6;

“by-products” includes incinerator bottom ash aggregate and ferrous and non-ferrous metal compounds;

“commercially operate” means operate the authorised development for commercial processing of waste and production of electricity for transmission to the national electricity grid following completion of hot commissioning and “commercial operation” and “commercially operated” shall be construed accordingly;

“heavy goods vehicle” means—

(a)

a heavy goods vehicle of 7.5 tonnes gross vehicle weight or more; and

(b)

any other vehicle designed for the transport of waste including refuse collection vehicles;

“low level restoration scheme” means the scheme for the restoration of Rookery North and Rookery South Pits which has been developed as a part of the review of old minerals permissions application which was submitted to Bedford Borough Council and Central Bedfordshire Council on 5 June 2009 and bears statutory reference number BC/CM/2000/08.

Time limits

1.  The authorised development may commence no later than the expiration of 5 years beginning with the date that this Order comes into force.

Type of waste to be treated

2.  The waste permitted to be incinerated in Work No. 1 must be limited to waste categorised as residual municipal waste and residual commercial and industrial waste and materials derived therefrom.

Commencement

3.  Notice of commencement of the authorised development must be given to the relevant planning authorities within 7 days beginning with the date that the authorised development is commenced.

Incineration, operation, etc.

4.  Notice of commencement of—

(a)incineration at the authorised development, and

(b)commercial operation of the authorised development,

must be given to the relevant planning authorities within 7 days beginning with the date that incineration commences and the authorised development is first commercially operated respectively.

Detailed design approval

5.  Except where the authorised development is carried out in accordance with the plans listed in requirement 6, no authorised development may commence until details of the layout, scale and external appearance of Works No. 1, 2, 5A, 5B, 7A, 7B and 9 comprised in the authorised development so far as they do not accord with the approved development plans have been submitted to and approved by the relevant planning authorities. The authorised development must be carried out in accordance with the approved details.

6.—(1) The authorised development must be carried out in accordance with the approved development plans bearing references 2.1 to 2.4 and 2.11 to 2.35 and strategies listed in this requirement (unless otherwise approved in writing by the relevant planning authorities and the altered development accords with the principles of the design and access statement and falls within the Order limits)—

  • Application Site Plan/the Order limits plan (drawing number: 2807LO/Order/007) (application document reference 2.1)

  • Works Plan: Key Plan (drawing number 2807LO/Order/001) (application document reference 2.2)

  • Works Plan: 1 of 2 (drawing number 2807LO/Order/001.1) (application document reference 2.3)

  • Works Plan: 2 of 2 (drawing number 2807LO/Order/001.2) (application document reference 2.4)

  • The rights of way plan (drawing number: 3052LO/SK010) (application document reference 2.11 Rev A)

  • EfW Facility South Elevation (drawing number: B3250-P1100) (application document reference 2.12)

  • EfW Facility North Elevation (drawing number: B3250-P1101) (application document reference 2.13)

  • EfW Facility East Elevation (drawing number: B3250-P1103) (application document reference 2.14)

  • EfW Facility West Elevation (drawing number: B3250-P1103) (application document reference 2.15)

  • EfW Facility East Sectional Elevation (drawing number: B3250-P1104) (application document reference 2.16)

  • EfW Facility West Sectional Elevation (drawing number: B3250-P1105) (application document reference 2.17)

  • Secondary Buildings Elevations - MRF (drawing number: B3250-P1106) (application document reference 2.18)

  • RRF Tertiary Buildings Elevations (drawing number: B3250-P1107) (application document reference 2.19)

  • RRF North and South Elevations (drawing number: B3250-P1300) (application document reference 2.20)

  • RRF East and West Elevations (drawing number: B3250-P1301) (application document reference 2.21)

  • RRF Site Section (drawing number: B3250-P1302) (application document reference 2.22)

  • RRF Boundary Details (drawing number: B3250-P1310) (application document reference 2.23)

  • RRF Elevation & Section Key Plan (drawing number: B3250-P1320) (application document reference 2.24)

  • RRF Roof Plan (drawing number: B3250-P1330) (application document reference 2.25)

  • Proposed access road existing footpath width at level crossing (drawing number: 210010_18) (application document reference 2.26)

  • Proposed access road with proposed 2.5m, footpath at level crossing (drawing number: 210010_20) (application document reference 2.27)

  • Proposed access to The Rookery Resource Facility Proposed cross section (drawing number: 210010_19) (application document reference 2.28)

  • Level Crossing (drawing number: RX_DR_GL_LC_03) (application document reference 2.29)

  • Lighting Layout & Strategy Operational Area (drawing number: 9V3657-7003) (application document reference 2.30)

  • Landscape Strategy & Key Plan (drawing number: 2807LO/PA002RevB) (application document reference 2.31B)

  • Operational Area Masterplan and Green Lane Country Park & RRF Entrance (drawing number: 2807LO/PA/007) (application document reference 2.32)

  • Planting Strategy - Wider Site (drawing number: 2807LO/PA/004_RevB) (application document reference 2.33B)

  • Planting Strategy: Operations Area and Indicative Scheme Layout for Green Lane Country Park & RRF Entrance (drawing number: 2807LO/PA/005RevA) (application document reference 2.34A)

  • Trees to be removed/retained (drawing number: 2897LO/PA/008) (application document reference 2.35)

  • Surface Water Drainage Strategy (drawing number 21780/076/002 Rev B)

  • Foul Water Drainage Strategy (drawing numbers 21780/077/001 Rev C and 21780/077/002 Rev D).

(2) Where any alternative details are approved pursuant to this requirement and requirements 5 or 30, those details are to be deemed to be substituted for the corresponding approved details set out in this requirement.

BREEAM Rating

7.—(1) No part of the authorised development may commence until─

(a)a pre-construction stage consultation with the Building Research Establishment (BRE) (in accordance with the BRE’s requirements for such consultation) has been carried out; and

(b)proposals identifying the range of options to achieve the BRE Environmental Assessment Methodology (BREEAM) rating specified in the consultation response, which must in any event (and in the absence of a consultation response) be of no less a standard than “good” have been submitted to and approved in writing by Central Bedfordshire Council.

(2) The authorised development must be carried out in accordance with the details approved pursuant to requirement 7(1). Any variation of the BREEAM rating must be agreed with BRE and submitted to Central Bedfordshire Council for approval in writing.

Provision of landscaping

8.—(1) No part of the authorised development may commence until a detailed landscaping scheme and associated working programme (which accords with the landscape strategy submitted with the application) has been submitted to and approved in writing by the relevant planning authorities.

(2) The landscaping scheme must include details of—

(a)the location, number, species, size and planting density of proposed planting;

(b)the retention of existing vegetation along the route of Work No. 5A specified in that scheme;

(c)a planting design in the vicinity of the attenuation pond and site access proposals within the Order land;

(d)any importation of materials and other operations to ensure plant establishment;

(e)proposed finished ground levels;

(f)planting and hard landscaping within the operational areas of the authorised development and the vehicular and pedestrian access, parking and circulation areas;

(g)the green wall and brown roofs to be constructed as part of the authorised development, including the method of construction, plant types, sizing and spacing, and the measures proposed for maintenance of those walls and roofs;

(h)minor structures such as signage, refuse or other units, and furniture;

(i)signage and cycle parking facilities at the site access on Green Lane;

(j)proposed and existing functional services above and below ground, including power and communications cables and pipelines, manholes and supports;

(k)the specified standard to which the works will be undertaken; and

(l)a timetable for the implementation of all hard and soft landscaping works.

Implementation and maintenance of landscaping

9.—(1) All landscaping works must be carried out in accordance with the detailed landscaping scheme approved under requirement 8 and to the specified standard in accordance with the relevant recommendations of appropriate British Standards or other recognised codes of good practice.

(2) Any tree or shrub planted as part of the detailed landscaping scheme approved under requirement 8 that, within a period of 5 years after planting, is removed, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted, unless otherwise approved by the relevant planning authority.

(3) The green wall that is part of the landscaping scheme approved under requirement 8(1) must be maintained in accordance with the approved landscaping scheme following its installation for the duration of the period of commercial operation of the authorised development.

Highway accesses

10.—(1) The highway works comprised in Works No. 8A and 8B to Green Lane, including the two pedestrian crossings and the footway running parallel to and south of Green Lane and the first 10 metres chainage of the access road comprised in Work No. 5A from its junction with Green Lane (including the pedestrian crossing that forms part of the junction in those Works), must be completed prior to the commencement of Works No. 1 and 2.

(2) The access road comprised in Work No. 5A (including the pedestrian crossing that forms part of the junction in those Works) must be constructed to base course for a minimum distance of 100 metres chainage from the section of the access road that has been completed in accordance with requirement 10(1) prior to the commencement of Works No. 1 and 2. The access road must be laid out in accordance with the approved access plans. The remainder of the route of the access road must be surfaced with crushed stone or other temporary materials appropriate for the purposes of constructing the authorised development.

(3) The works comprised in Works No. 5A and 5B must be substantially completed to the standard specified in the Design Manual for Roads and Bridges and in accordance with the approved access plans (application document references 2.26 and 2.28) set out in requirement 6(1) as certified by an appropriate certifying professional prior to incineration of waste in Work No. 1.

(4) The commencement of Work No. 1 must not take place until a scheme to provide wheel cleaning facilities for heavy goods vehicles and provision for road cleaning in relation to construction of the authorised development has been submitted to and approved in writing by Central Bedfordshire Council. The scheme must include details of the measures and location for the wheel cleaning facilities and details of how cleaning of the highway will be secured so as to remove mud and other debris that may be carried on to it from the authorised development.

Fencing and other means of site perimeter enclosure

11.—(1) No part of the authorised development may commence until details of all proposed permanent fences, walls or other means of enclosure according with boundary details shown on drawing B3250-P1310 (application document reference no. 2.23) including the acoustic fence adjacent to the ramp serving the tipping hall comprised in Work No. 1 have been submitted to and approved in writing by Central Bedfordshire Council.

(2) All construction sites must remain securely fenced at all times during construction of the authorised development.

(3) All temporary fencing must be removed on completion of the authorised development.

(4) All perimeter fences, walls or other means of site perimeter enclosure for the authorised development approved in accordance with paragraph (1) must be completed prior to commencement of commercial operation in accordance with the approved details.

Surface and foul water drainage

12.—(1) Except where the authorised development is constructed in accordance with the approved drainage strategies, details of the surface and foul water drainage system (including means of pollution control and information demonstrating compliance with the best practice for sustainable drainage schemes) must be submitted to and approved in writing by Central Bedfordshire Council. Unless otherwise agreed in writing by Central Bedfordshire Council, such details must accord with the principles of the drainage strategy submitted with the application, making provision for the construction of Work No. 3, and must be implemented in accordance with the approved details.

(2) The drainage strategy must provide that all drains provided as part of the authorised development must, where necessary and appropriate, contain trap gullies or interceptors.

Land stability

13.—(1) No part of the authorised development may commence until a written scheme to deal with land stability has been submitted to and approved in writing by Central Bedfordshire Council.

(2) The scheme must include an investigation and assessment report, prepared by a specialist consultant approved by Central Bedfordshire Council, to identify the extent of any land stability matters, and the remedial measures to be taken to render the land fit for its intended purpose.

(3) Land stabilisation must be carried out in accordance with the approved scheme unless otherwise agreed in writing by Central Bedfordshire Council.

Contamination and groundwater

14.—(1) No part of the authorised development may commence until a scheme to deal with the contamination of any land, including groundwater, which is likely to cause significant harm to persons or pollution of controlled waters or the environment has been submitted to and approved in writing by Central Bedfordshire Council.

(2) The scheme must include an investigation and assessment report, prepared by a specialist consultant approved by Central Bedfordshire Council, to identify the extent of any contamination and the remedial measures to be taken to render the land fit for its intended purpose, together with a management plan which sets out long-term measures with respect to any contaminants remaining on the site.

(3) Remediation must be carried out in accordance with the approved scheme unless otherwise agreed in writing by Central Bedfordshire Council.

Archaeology

15.—(1) No part of the authorised development may commence until a written scheme of archaeological investigation has been submitted to and approved in writing by the relevant planning authorities.

(2) The archaeological investigation must be carried out in accordance with the approved scheme unless otherwise agreed in writing by the relevant planning authorities.

Code of construction practice

16.  All construction works must be undertaken in accordance with the code of construction practice unless otherwise agreed in writing by the relevant planning authorities.

Control of noise during construction and operational phase

17.  During construction the daytime free field noise level as a result of the construction of the authorised development at any residential location must not exceed 55 dB LAeq, 1 hour unless otherwise agreed in writing by Central Bedfordshire Council.

18.—(1) Except in case of an emergency, or with the prior written agreement of Central Bedfordshire Council, the Rating Level as defined in BS4142:1997 of the noise emitted from the operation of the authorised development must not exceed the free field noise levels listed in the following table—

Location

Daytime (0700-2300) dB L

Aeq 1 hour

Night-time (2300-0700) dB L

Aeq 5 minutes
Stewartby Way, Stewartby3535
South Pillinge Farm3935
Pillinge Farm Cottages3535

(2) Compliance with these limits must be demonstrated by noise measurements at locations closer to the Order limits selected to allow measurement of noise from the authorised development to be made without significant influence of noise from other sources. Noise levels must be calculated for these locations in accordance with the propagation methodology in ISO 9613 and agreed with the relevant planning authorities.

19.—(1) No part of the authorised development may commence until a written scheme providing for the monitoring of noise generated during the construction and operation of the authorised development has been submitted to and approved in writing by Central Bedfordshire Council.

(2) The scheme must specify the locations at which noise will be monitored and the method of noise measurement (which must be in accord with BS 4142, an equivalent successor standard or other agreed noise measurement methodology appropriate to the circumstances).

(3) The scheme must be implemented to establish baseline noise conditions.

(4) This monitoring programme must be subject to periodic reviews to establish the frequency of noise monitoring and the need for continued monitoring.

(5) Throughout the operational lifetime of the development the monitoring programme must be reviewed following any change in plant, equipment or working practices likely to affect noise conditions and any such change shall be notified in writing to Central Bedfordshire Council; or following a written request by Central Bedfordshire Council in relation to a noise related complaint.

(6) Such review must be submitted to Central Bedfordshire Council for its written approval within 4 weeks of the notification or request.

20.—(1) In any case where the noise levels specified in requirement 18 or otherwise agreed in writing for monitoring locations is exceeded because of an emergency, the undertaker must notify Central Bedfordshire Council in writing of the nature of the emergency within 2 working days, the reasons for exceeding the noise limit and its expected duration.

(2) If the period of excess noise is expected to last for more than 24 hours then the undertaker must inform any community liaison panel or any other consultative body established as a result of the authorised development, the relevant planning authorities and adjoining occupiers or land users.

(3) Notification of the excess, the reasons for it and its expected duration must also be posted on the undertaker’s internet web site.

21.  Except in an emergency, the undertaker must give at least three working days’ written notice to Central Bedfordshire Council of any proposed operation of emergency pressure valves or similar equipment. Where steam purging is to take place, the undertaker must give 3 working days’ prior written notice to local residents and businesses by informing any community liaison panel or any other consultative body established in respect of the authorised development as well as the relevant planning authorities. Notification of the incident, the reasons for it and its expected duration must also be posted on the undertaker’s internet web site.

22.  So far as reasonably practicable, steam purging may only take place between the hours of 0900-1700 Mondays-Saturdays and not on any Sunday or Bank Holiday.

23.—(1) Prior to the commencement of construction for the building envelope to contain Work No. 1 an acoustic design report must be submitted to and approved in writing by Central Bedfordshire Council.

(2) The report must detail─

(a)the noise control measures that are proposed to be included in the design of the building envelope;

(b)acoustic barriers;

(c)predicted sound power levels and noise emissions from the air cooled condensers; and

(d)acoustic attenuation measures for internal plant and equipment.

(3) The measures must be installed in accord with the approved scheme prior to commencement of operation of the authorised development and retained and maintained afterwards in accordance with the manufacturers’ specifications unless Central Bedfordshire Council gives its written consent to any variation.

(4) The acoustic design report must demonstrate compliance with requirements 18 and 19.

Construction hours

24.  Construction work (which for the purpose of this requirement does not include non-intrusive activities such as electrical installation and internal fit out works) may not take place other than between 0700 and 1900 hours on weekdays and 0700 and 1300 hours on Saturdays, excluding public holidays, unless otherwise agreed in writing by Central Bedfordshire Council.

Combined Heat and Power

25.  A facility must be provided and maintained within Work No. 1 to enable steam pass-outs and/or hot water pass-outs and reserve space for the provision of water pressurisation, heating and pumping systems for off-site users of process or space heating and its later connection to such systems.

Delivery hours and traffic management

26.—(1) No heavy goods vehicle transporting municipal waste or commercial and industrial waste may enter or leave the authorised development at any time on a Sunday, Christmas Day, New Year’s Day or Easter Day (unless otherwise approved in writing by Central Bedfordshire Council).

(2) No heavy goods vehicle transporting municipal waste or commercial and industrial waste may enter or leave Work No. 1 except on Monday to Saturday between the hours of 0700 to 2300.

(3) No heavy goods vehicle transporting by-products may enter or leave Work No. 2 except on the following days and prescribed times—

(a)Monday to Friday between the hours of 0700 to 1800;

(b)Saturday between the hours of 0700 to 1400.

(4) No heavy goods vehicle may enter or leave the lorry park except between the hours of 0700 to 2300 on Monday to Saturday.

(5) This requirement applies except where such a movement as it describes is—

(a)an abnormal load;

(b)associated with an emergency; or

(c)carried out with the written approval of Central Bedfordshire Council.

CCTV

27.—(1) No part of the authorised development may commence until a scheme for the installation of a CCTV camera (or cameras) to monitor the entrance to the site from Green Lane has been submitted to and approved in writing by Central Bedfordshire Council. The scheme must include details of—

(a)the column(s) and camera(s) to be used;

(b)the viewing area covered;

(c)the capability for remote access viewing; and

(d)the ability to record live footage.

(2) The approved CCTV scheme must be installed prior to commencement of incineration of waste in Work No. 1 and must be operated afterwards in accordance with the approved scheme unless otherwise agreed in writing by Central Bedfordshire Council.

Loads to be covered

28.  All heavy goods vehicles carrying bulk materials or waste into and out of the site of the authorised development during the construction, operational and decommissioning phases of development must be covered unless the load is otherwise enclosed, except when required to inspect incoming loads of waste.

Restoration

29.—(1) On the 32nd anniversary of the commencement of operation of the authorised development or on the cessation of the commercial operation of the development, whichever is earlier, the applicant must inform Central Bedfordshire Council as to whether it intends to maintain the authorised development in its then current state, refurbish it or demolish the facility and restore the land.

(2) In the event that it is intended to refurbish the authorised development details of external changes must be submitted to Central Bedfordshire Council for approval in writing. Any such refurbishment must be implemented in accordance with the approved details.

(3) In the event that it is not intended to maintain the authorised development (whether by carrying out changes authorised under requirement 29(2) or otherwise) the authorised development must be removed.

(4) Prior to any demolition of the authorised development demolition details must be submitted to Central Bedfordshire Council for approval in writing.

(5) The details must include—

(a)the structures and buildings to be demolished or retained;

(b)the phasing of demolition and means of removal of demolition materials; and

(c)the proposed condition of the land following restoration (including whether the land will be in the condition authorised by the Low Level Restoration Scheme approved under statutory reference BC/CM/2000/08) or an alternative scheme approved by Central Bedfordshire Council depending upon the condition of the land).

(6) The demolition must be carried out in accordance with the approved details following cessation of commercial operation of the authorised development unless otherwise agreed in writing by Central Bedfordshire Council.

Amendments to approved details

30.  With respect to any requirement which requires the authorised development to be carried out in accordance with details approved by the relevant planning authorities or either of them, the approved details are to be taken to include any amendments that may subsequently be approved in writing by the relevant planning authorities or either of them as the case may be.

Low level restoration scheme

31.  No part of the authorised development may commence until the works comprising phase 1 of the low level restoration scheme, which has been authorised by Bedford Borough Council and Central Bedfordshire Council as a part of the review of old minerals permission with reference number BC/CM/2000/08, have been carried out so as to provide an engineered site for the authorised development.

Incinerator bottom ash processing and storage

32.  No incinerator bottom ash or other combustion residues produced at any other generating station may be accepted at or processed in Work No. 2 of the authorised development.

33.  No by-products stored at Work No. 2 comprised in the authorised development may exceed 10 metres in height from the surface of the yard comprised in Work No. 2.

34.—(1) Work No. 2 must not be commercially operated until a written scheme for the management and mitigation of dust emissions has been submitted to and approved in writing by Central Bedfordshire Council.

(2) The approved scheme for the management and mitigation of dust emissions must be implemented and maintained for the duration of the operation of the authorised development.

Lighting strategy

35.—(1) No part of the authorised development may commence until a detailed lighting strategy (which accords with the approved lighting strategy listed in requirement 6(1) and described in the design and access statement) has been submitted to and approved in writing by Central Bedfordshire Council.

(2) The approved lighting strategy must be implemented in accordance with the approved details prior to the commencement of incineration of waste in Work No. 1 of the authorised development and must be maintained afterwards for the duration of commercial operation of the authorised development.

(3) Where construction of Work No. 2 has not been completed prior to the incineration of waste in Work No. 1 the relevant elements of the approved lighting strategy relating to Work No. 2 must be implemented in accordance with the approved details prior to commercial operation of Work No. 2 and must be maintained afterwards for the duration of the operation of the authorised development.

Connection to the national grid

36.—(1) No incineration of waste in Work No. 1 may take place, apart from during commissioning, until a grid connection comprised in Works No. 6A, 6B, 6C, 6D, 6E, 6F, 6G and 6H has been installed and is capable of transmitting electricity generated by Work No. 1.

(2) No waste may then be incinerated in Work No. 1 unless electricity is being generated by Work No. 1 except during periods of maintenance, inspection or repair or at the direction of the holder of a licence under section 6(1)(b) or (c) of the Electricity Act 1989 who is entitled to give such direction in relation to transmission of electricity from Work No. 1 to the national grid.

Visibility requirements at Green Lane/C94 junction

37.—(1) No part of the authorised development may commence until a scheme which overcomes the substandard visibility splay to the left on exit at the junction of Green Lane with the C94 has been submitted to and approved in writing by Bedford Borough Council and implemented on site in accordance with the approved details.

(2) Visibility requirements at either the existing junction or any new or realigned junction must accord with the requirements set out in the Design Manual for Roads and Bridges.

Vehicle movements

38.—(1) The total number of heavy goods vehicles importing or exporting waste, incinerator bottom ash aggregate or flue gas treatment residues to and from the authorised development must not exceed 594 movements per day.

(2) Records of such vehicle movements must be kept by the undertaker and provided to Central Bedfordshire Council every 6 months.

(3) The records must specify the following—

(a)number of vehicles both entering and leaving the authorised development; and

(b)time and date of vehicles both entering and leaving the authorised development.

Travel plan

39.—(1) The authorised development may not be commercially operated except in accordance with the travel plan which, prior to the approval of the travel plan referred to in requirement 39(2), means the travel plan submitted with the application together with the addendum headed “Interim Travel Plan SoCG Appendix” unless otherwise agreed in writing by the relevant planning authorities.

(2) A full travel plan must be submitted to the relevant planning authorities for approval in writing prior to the expiration of 6 months from the date on which the authorised development is first commercially operated. Following such approval that travel plan must be implemented in accordance with the approved details.

(3) A review of the travel plan must be carried out on each anniversary of the date of commencement of commercial operation of the authorised development and an annual travel plan report including any revisions to the travel plan deemed necessary as a result of the review must be submitted to the relevant planning authorities for written approval. Following approval of the revisions to the travel plan by the relevant planning authorities the authorised development must be operated in accordance with the revised travel plan.

Ecological management scheme

40.—(1) No part of the authorised development may commence until a written ecological management scheme has been submitted to and approved in writing by the relevant planning authorities.

(2) The ecological management scheme must include details of—

(a)the protection of species covered by wildlife legislation, including great crested newts and reptiles, from activities associated with the authorised development;

(b)measures to sustain favourable conditions for stoneworts and invertebrate communities;

(c)the control of quality and quantity of water released from the authorised development to the drainage channels and attenuation pond in Rookery South Pit;

(d)the rotational management of water bodies and other wetland habitats within Rookery Pits;

(e)the management of woodland and scrub planting to maximise the habitat mosaic so as to complement woodland objectives in the wider area;

(f)how the lighting strategy referred to at requirement 35 avoids or minimises the use and effect of lighting;

(g)a strategy for ecological management of vegetated surfaces to include brown roofs associated with the Work No. 1;

(h)a programme for implementation of the proposed measures;

(i)details of ongoing maintenance; and

(j)an annual reporting protocol.

(3) The approved ecological management scheme must be implemented and maintained during commercial operation of the authorised development unless otherwise agreed in writing by the relevant planning authorities.

Residual Waste Acceptance Scheme

41.—(1) Incineration of waste in Work No. 1 must not take place except in accordance with the Residual Waste Acceptance Scheme dated 8 July 2011.

(2) On a date no later than the anniversary of the commencement of incineration of waste in Work No. 1 in each year, a written report in respect of a review of the effectiveness of the scheme must be submitted to Central Bedfordshire Council for approval in writing together with proposals for such revised, additional or substituted measures as appear to be necessary.

(3) Following approval of the alterations to the scheme by Central Bedfordshire Council incineration of waste in Work No. 1 must take place in accordance with the altered scheme.

(4) The purpose of altering the scheme is to ensure that the scheme continues to address changes in waste management, and that Work No. 1 is used only for the incineration of residual waste.

Article 10

SCHEDULE 2STREETS SUBJECT TO STREET WORKS

(1)

Area

(2)

Street subject to street works

Bedford Borough and Central BedfordshireGreen Lane, Stewartby between a point at its junction with Footpath 4 to the south of Stewartby and its junction with the existing C94
Green Lane Level Crossing, Stewartby
The Copart Access Road, Marston Moretaine from its junction with Green Lane, Marston Moretaine to its junction with the C94
Central BedfordshireThe C94 within the Order limits
Footpath 72 from its junction with Green Lane or west of Green Lane Level Crossing and its junction with the Copart Access Road, Marston Mortaine

Article 11

SCHEDULE 3PUBLIC RIGHTS OF WAY

PART 1PUBLIC RIGHTS OF WAY EXTINGUISHED

(1)

Area

(2)

Right of way extinguished

(3)

Extent to which extinguished

Central BedfordshireFootpath No. 4 west of Rookery South PitExisting footpath between points X1 and X2
Footpath No. 17 East of the western boundary of the Marston Vale railway lineExisting footpath between points X3 and X4
All footpaths, bridleways and other rights of way affecting the area of the Rookery shown shaded grey on the rights of way planWithin the area shaded grey on the rights of way plans

PART 2RIGHTS OF WAY CREATED OR IMPROVED

(1)

Area

(2)

Existing or new right

(3)

New status

Central BedfordshireA new combined footpath and cycleway between points N1 and N2Footpath with cycle rights
A new combined footpath and cycleway between points N3 and N4Footpath with cycle rights
A new combined footpath and cycleway between points N5 and N6Footpath with cycle rights
Footpath 72 to be upgraded to include cycle rights between points I1 and I2Footpath with cycle rights
Bedford BoroughFootpath to be upgraded to include cycle rights between points I8 and I9Footpath with cycle rights
Bedford Borough and Central BedfordshireFootpath to be upgraded to include cycle rights between points I3 and, thence by a circular route via points I4-I7 to Point I3Footpath with cycle rights

Article 12

SCHEDULE 4STREETS TO BE TEMPORARILY STOPPED UP

(1)

Area

(2)

Street to be temporarily stopped up

(3)

Extent of temporary stopping up

Bedford Borough and Central BedfordshireThe Copart Access Road, Marston MoretaineWithin the Order limits

Article 13

SCHEDULE 5ACCESS TO WORKS

(1)

Area

(2)

Description of access

Bedford BoroughAn improved access to Green Lane Stewartby at or near to point A

Article 25

SCHEDULE 6LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

(1)

Area

(2)

Number of land shown on land plan

(3)

Purpose for which temporary possession may be taken

Central Bedfordshire52, 72, 73, 74, 75, 76, 77Carrying out and maintaining landscaping, tree planting and ecological improvements
Bedford Borough and Central Bedfordshire1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 29/1, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63Installation, retention and maintenance of electricity transmission line and the improvement of highways and public rights of way

Article 33

SCHEDULE 7PROTECTION OF NETWORK RAIL INFRASTRUCTURE LIMITED

1.  The following provisions of this Schedule shall have effect unless otherwise agreed in writing between the undertaker and Network Rail and, in the case of paragraph 15, any other person on whom rights or obligations are conferred by that paragraph.

2.  In this Schedule—

“construction” includes execution, placing, alteration and reconstruction and “construct” and “constructed” have corresponding meanings;

“the engineer” means an engineer appointed by Network Rail for the purposes of this Order;

“network licence” means the network licence, as the same is amended from time to time, granted to Network Rail Infrastructure Limited by the Secretary of State in exercise of his powers under section 8 of the Railways Act l993;

“Network Rail” means Network Rail Infrastructure Limited and any associated company of Network Rail Infrastructure Limited which holds property for railway purposes, and for the purpose of this definition “associated company” means any company which is (within the meaning of section 1159 of the Companies Act 2006) the holding company of Network Rail Infrastructure Limited, a subsidiary of Network Rail Infrastructure Limited or another subsidiary of the holding company of Network Rail Infrastructure Limited;

“plans” includes sections, designs, design data, software, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of railway property;

“railway operational procedures” means procedures specified under any access agreement (as defined in the Railways Act 1993) or station lease;

“railway property” means any railway belonging to Network Rail Infrastructure Limited and—

(a)

any station, land, works, apparatus and equipment belonging to Network Rail Infrastructure Limited or connected with any such railway; and

(b)

any easement or other property interest held or used by Network Rail Infrastructure Limited for the purposes of such railway or works, apparatus or equipment; and

“specified work” means so much of any of the authorised development as is situated upon, across, under, over or within 15 metres of, or may in any way adversely affect, railway property.

3.—(1) Where under this Schedule Network Rail is required to give its consent, agreement or approval in respect of any matter, that consent, agreement or approval is subject to the condition that Network Rail complies with any relevant railway operational procedures and any obligations under its network licence or under statute.

(2) In so far as any specified work or the acquisition or use of railway property is or may be subject to railway operational procedures, Network Rail shall—

(a)co-operate with the undertaker with a view to avoiding undue delay and securing conformity as between any plans approved by the engineer and requirements emanating from those procedures; and

(b)use their reasonable endeavours to avoid any conflict arising between the application of those procedures and the proper implementation of the authorised development pursuant to this Order.

4.—(1) The undertaker shall not exercise the powers conferred by articles 16, 17, 18, 20 or 25 or the powers conferred by section 11(3) of the 1965 Act (powers of entry) in respect of any railway property unless the exercise of such powers is with the consent of Network Rail.

(2) The undertaker shall not in the exercise of the powers conferred by this Order prevent pedestrian or vehicular access to any railway property, unless preventing such access is with the consent of Network Rail.

(3) The undertaker shall not exercise the powers conferred by sections 271 or 272 of the 1990 Act (extinguishment of rights of statutory undertakers and electronic code communications operators: preliminary notices), or article 27, in relation to any right of access of Network Rail to railway property, but such right of access may be diverted with the consent of Network Rail.

(4) The undertaker shall not under the powers of this Order acquire or use or acquire new rights over any railway property except with the consent of Network Rail.

(5) Prior to commencement of construction of the authorised project the undertaker and Network Rail shall, having regard to the undertaker’s timetable for development, agree in writing a programme for the implementation of any works approved by Network Rail to the railway crossing of the Bletchley Bedford railway line at Green Lane, Stewartby, Bedford and the undertaker will thereafter comply with the provisions of the programme.

(6) Where Network Rail is asked to give its consent or agreement pursuant to this paragraph, such consent or agreement shall not be unreasonably withheld but may be given subject to reasonable conditions.

5.—(1) The undertaker shall before commencing construction of any specified work supply to Network Rail proper and sufficient plans of that work for the reasonable approval of the engineer and the specified work shall not be commenced except in accordance with such plans as have been approved in writing by the engineer or settled by arbitration.

(2) The approval of the engineer under sub-paragraph (1) shall not be unreasonably withheld, and if by the end of the period of 28 days beginning with the date on which such plans have been supplied to Network Rail the engineer has not intimated disapproval of those plans and the grounds of disapproval the undertaker may serve upon the engineer written notice requiring the engineer to intimate approval or disapproval within a further period of 28 days beginning with the date upon which the engineer receives written notice from the undertaker. If by the expiry of the further 28 days the engineer has not intimated approval or disapproval, the engineer shall be deemed to have approved the plans as submitted.

(3) If by the end of the period of 28 days beginning with the date on which written notice was served upon the engineer under sub-paragraph (2), Network Rail gives notice to the undertaker that Network Rail desires itself to construct any part of a specified work which in the opinion of the engineer will or may affect the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker desires such part of the specified work to be constructed, Network Rail shall construct it with all reasonable dispatch on behalf of and to the reasonable satisfaction of the undertaker in accordance with the plans approved or deemed to be approved or settled under this paragraph, and under the supervision (where appropriate and if given) of the undertaker.

(4) When signifying approval of the plans the engineer may specify any protective works (whether temporary or permanent) which in the engineer’s opinion should be carried out before the commencement of the construction of a specified work to ensure the safety or stability of railway property or the continuation of safe and efficient operation of the railways of Network Rail or the services of operators using the same (including any relocation de-commissioning and removal of works, apparatus and equipment necessitated by a specified work and the comfort and safety of passengers who may be affected by the specified works), and such protective works as may be reasonably necessary for those purposes shall be constructed by Network Rail or by the undertaker, if Network Rail so desires, and such protective works shall be carried out at the expense of the undertaker in either case with all reasonable dispatch and the undertaker shall not commence the construction of the specified works until the engineer has notified the undertaker that the protective works have been completed to his reasonable satisfaction.

6.—(1) Any specified work and any protective works to be constructed by virtue of paragraph 5(4) shall, when commenced, be constructed—

(a)with all reasonable dispatch in accordance with the plans approved or deemed to have been approved or settled under paragraph 5;

(b)under the supervision (where appropriate and if given) and to the reasonable satisfaction of the engineer;

(c)in such manner as to cause as little damage as is possible to railway property; and

(d)so far as is reasonably practicable, so as not to interfere with or obstruct the free, uninterrupted and safe use of any railway of Network Rail or the traffic thereon and the use by passengers of railway property.

(2) If any damage to railway property or any such interference or obstruction shall be caused by the carrying out of, or in consequence of the construction of a specified work, the undertaker shall, notwithstanding any such approval, make good such damage and shall pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may sustain by reason of any such damage, interference or obstruction.

(3) Nothing in this Schedule shall impose any liability on the undertaker with respect to any damage, costs, expenses or loss attributable to the negligence of Network Rail or its servants, contractors or agents or any liability on Network Rail with respect of any damage, costs, expenses or loss attributable to the negligence of the undertaker or its servants, contractors or agents.

7.  The undertaker shall—

(a)at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and

(b)supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing it.

8.  Network Rail shall at all times afford reasonable facilities to the undertaker and its agents for access to any works carried out by Network Rail under this Schedule during their construction and shall supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them.

9.—(1) If any permanent or temporary alterations or additions to railway property are reasonably necessary in consequence of the construction of a specified work, or during a period of 24 months after the completion of that work in order to ensure the safety of railway property or the continued safe operation of the railway of Network Rail, such alterations and additions may be carried out by Network Rail and if Network Rail gives to the undertaker reasonable notice of its intention to carry out such alterations or additions (which shall be specified in the notice), the undertaker shall pay to Network Rail the reasonable cost of those alterations or additions including, in respect of any such alterations and additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by Network Rail in maintaining, working and, when necessary, renewing any such alterations or additions.

(2) If during the construction of a specified work by the undertaker, Network Rail gives notice to the undertaker that Network Rail desires itself to construct that part of the specified work which in the opinion of the engineer is endangering the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker decides that part of the specified work is to be constructed, Network Rail shall assume construction of that part of the specified work and the undertaker shall, notwithstanding any such approval of a specified work under paragraph 5(3), pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may suffer by reason of the execution by Network Rail of that specified work.

(3) The engineer shall, in respect of the capitalised sums referred to in this paragraph and paragraph 10(a) provide such details of the formula by which those sums have been calculated as the undertaker may reasonably require.

(4) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions a capitalised sum representing such saving shall be set off against any sum payable by the undertaker to Network Rail under this paragraph.

10.  The undertaker shall repay to Network Rail all reasonable fees, costs, charges and expenses reasonably incurred by Network Rail—

(a)in constructing any part of a specified work on behalf of the undertaker as provided by paragraph 5(3) or in constructing any protective works under the provisions of paragraph 5(4) including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;

(b)in respect of the approval by the engineer of plans submitted by the undertaker and the supervision by the engineer of the construction of a specified work;

(c)in respect of the employment or procurement of the services of any inspectors, signalmen, watchmen and other persons whom it shall be reasonably necessary to appoint for inspecting, signalling, watching and lighting railway property and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of a specified work;

(d)in respect of any special traffic working resulting from any speed restrictions which may in the opinion of the engineer, require to be imposed by reason or in consequence of the construction or failure of a specified work or from the substitution or diversion of services which may be reasonably necessary for the same reason; and

(e)in respect of any additional temporary lighting of railway property in the vicinity of the specified works, being lighting made reasonably necessary by reason or in consequence of the construction or failure of a specified work.

11.—(1) In this paragraph—

“EMI” means, subject to sub-paragraph (2), electromagnetic interference with Network Rail apparatus generated by the operation of the authorised development where such interference is of a level which adversely affects the safe operation of Network Rail’s apparatus; and

“Network Rail’s apparatus” means any lines, circuits, wires, apparatus or equipment (whether or not modified or installed as part of the authorised development) which are owned or used by Network Rail for the purpose of transmitting or receiving electrical energy or of radio, telegraphic, telephonic, electric, electronic or other like means of signalling or other communications.

(2) This paragraph shall apply to EMI only to the extent that such EMI is not attributable to any change to Network Rail’s apparatus carried out after approval of plans under paragraph 5(1) for the relevant part of the authorised development giving rise to EMI (unless the undertaker has been given notice in writing before the approval of those plans of the intention to make such change).

(3) Subject to sub-paragraph (5), the undertaker shall in the design and construction of the authorised development take all measures necessary to prevent EMI and shall establish with Network Rail (both parties acting reasonably) appropriate arrangements to verify their effectiveness.

(4) In order to facilitate the undertaker’s compliance with sub-paragraph (3)—

(a)the undertaker shall consult with Network Rail as early as reasonably practicable to identify all Network Rail’s apparatus which may be at risk of EMI, and thereafter shall continue to consult with Network Rail (both before and after formal submission of plans under paragraph 5(1)) in order to identify all potential causes of EMI and the measures required to eliminate them;

(b)Network Rail shall make available to the undertaker all information in the possession of Network Rail reasonably requested by the undertaker in respect of Network Rail’s apparatus identified pursuant to sub-paragraph (a); and

(c)Network Rail shall allow the undertaker reasonable facilities for the inspection of Network Rail’s apparatus identified pursuant to sub-paragraph (a).

(5) In any case where it is established that EMI can only reasonably be prevented by modifications to Network Rail’s apparatus, Network Rail shall not withhold its consent unreasonably to modifications of Network Rail’s apparatus, but the means of prevention and the method of their execution shall be selected in the reasonable discretion of Network Rail, and in relation to such modifications paragraph 5(1) shall have effect subject to this sub-paragraph.

(6) If at any time prior to the commencement of commercial operation of the authorised development and notwithstanding any measures adopted pursuant to sub-paragraph (3), the testing or commissioning of the authorised development causes EMI then the undertaker shall immediately upon receipt of notification by Network Rail of such EMI either in writing or communicated orally (such oral communication to be confirmed in writing as soon as reasonably practicable after it has been issued) forthwith cease to use (or procure the cessation of use of) the undertaker’s apparatus causing such EMI until all measures necessary have been taken to remedy such EMI by way of modification to the source of such EMI or (in the circumstances, and subject to the consent, specified in sub-paragraph (5)) to Network Rail’s apparatus.

(7) In the event of EMI having occurred—

(a)the undertaker shall afford reasonable facilities to Network Rail for access to the undertaker’s apparatus in the investigation of such EMI;

(b)Network Rail shall afford reasonable facilities to the undertaker for access to Network Rail’s apparatus in the investigation of such EMI; and

(c)Network Rail shall make available to the undertaker any additional material information in its possession reasonably requested by the undertaker in respect of Network Rail’s apparatus or such EMI.

(8) Where Network Rail approves modifications to Network Rail’s apparatus pursuant to sub-paragraphs (5) or (6)—

(a)Network Rail shall allow the undertaker reasonable facilities for the inspection of the relevant part of Network Rail’s apparatus;

(b)any modifications to Network Rail’s apparatus approved pursuant to those sub-paragraphs shall be carried out and completed by the undertaker in accordance with paragraph 6.

(9) To the extent that it would not otherwise do so, the indemnity in paragraph 15(1) shall apply to the costs and expenses reasonably incurred or losses suffered by Network Rail through the implementation of the provisions of this paragraph (including costs incurred in connection with the consideration of proposals, approval of plans, supervision and inspection of works and facilitating access to Network Rail’s apparatus) or in consequence of any EMI to which sub-paragraph (6) applies.

(10) For the purpose of paragraph 10(a) any modifications to Network Rail’s apparatus under this paragraph shall be deemed to be protective works referred to in that paragraph.

(11) In relation to any dispute arising under this paragraph the reference in article 34 to an arbitrator to be agreed shall be read as a reference to an arbitrator being a member of the Institution of Electrical Engineers to be agreed.

12.  If at any time after the completion of a specified work, not being a work vested in Network Rail, Network Rail gives notice to the undertaker informing it that the state of maintenance of any part of the specified work appears to be such as adversely affects the operation of railway property, the undertaker shall, on receipt of such notice, take such steps as may be reasonably necessary to put that specified work in such state of maintenance as not adversely to affect railway property.

13.  The undertaker shall not provide any illumination or illuminated sign or signal on or in connection with a specified work in the vicinity of any railway belonging to Network Rail unless it shall have first consulted Network Rail and it shall comply with Network Rail’s reasonable requirements for preventing confusion between such illumination or illuminated sign or signal and any railway signal or other light used for controlling, directing or securing the safety of traffic on the railway.

14.  Any additional expenses which Network Rail may reasonably incur in altering, reconstructing or maintaining railway property under any powers existing at the making of this Order by reason of the existence of a specified work shall, provided that 56 days’ previous notice of the commencement of such alteration, reconstruction or maintenance has been given to the undertaker, be repaid by the undertaker to Network Rail.

15.—(1) The undertaker shall pay to Network Rail all reasonable costs, charges, damages and expenses not otherwise provided for in this Schedule which may be occasioned to or reasonably incurred by Network Rail—

(a)by reason of the construction or maintenance of a specified work or the failure thereof; or

(b)by reason of any act or omission of the undertaker or of any person in its employ or of its contractors or others whilst engaged upon a specified work,

and the undertaker shall indemnify and keep indemnified Network Rail from and against all claims and demands arising out of or in connection with a specified work or any such failure, act or omission: and the fact that any act or thing may have been done by Network Rail on behalf of the undertaker or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under his supervision shall not (if it was done without negligence on the part of Network Rail or of any person in its employ or of its contractors or agents) excuse the undertaker from any liability under the provisions of this sub-paragraph.

(2) Network Rail shall give the undertaker reasonable notice of any such claim or demand and no settlement or compromise of such a claim or demand shall be made without the prior consent of the undertaker.

(3) The sums payable by the undertaker under sub-paragraph (1) shall include a sum equivalent to the relevant costs.

(4) Subject to the terms of any agreement between Network Rail and a train operator regarding the timing or method of payment of the relevant costs in respect of that train operator, Network Rail shall promptly pay to each train operator the amount of any sums which Network Rail receives under sub-paragraph (3) which relates to the relevant costs of that train operator.

(5) The obligation under sub-paragraph (3) to pay Network Rail the relevant costs shall, in the event of default, be enforceable directly by any train operator concerned to the extent that such sums would be payable to that operator pursuant to sub-paragraph (4).

(6) In this paragraph—

“the relevant costs” means the costs, direct losses and expenses (including loss of revenue) reasonably incurred by each train operator as a consequence of any restriction of the use of Network Rail’s railway network as a result of the construction, maintenance or failure of a specified work or any such act or omission as mentioned in sub-paragraph (1); and

“train operator” means any person who is authorised to act as the operator of a train by a licence under section 8 of the Railways Act 1993.

16.  Network Rail shall, on receipt of a request from the undertaker, from time to time provide the undertaker free of charge with written estimates of the costs, charges, expenses and other liabilities for which the undertaker is or will become liable under this Schedule (including the amount of the relevant costs mentioned in paragraph 15) and with such information as may reasonably enable the undertaker to assess the reasonableness of any such estimate or claim made or to be made pursuant to this Schedule (including any claim relating to those relevant costs).

17.  In the assessment of any sums payable to Network Rail under this Schedule there shall not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Network Rail if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by the undertaker under this Schedule or increasing the sums so payable.

18.  The undertaker and Network Rail may, subject in the case of Network Rail to compliance with the terms of its network licence, enter into, and carry into effect, agreements for the transfer to the undertaker of—

(a)any railway property shown on the works and land plans and described in the book of reference;

(b)any lands, works or other property held in connection with any such railway property; and

(c)any rights and obligations (whether or not statutory) of Network Rail relating to any railway property or any lands, works or other property referred to in this paragraph.

19.  Nothing in this Order, or in any enactment incorporated with or applied by this Order, shall prejudice or affect the operation of Part I of the Railways Act 1993.

20.  The undertaker shall give written notice to Network Rail where any application is proposed to be made by the undertaker for the decision-maker’s consent under article 7 of this Order and any such notice shall be given no later than 28 days before any such application is made and shall describe or give (as appropriate)—

(a)the nature of the application to be made;

(b)the extent of the geographical area to which the application relates; and

(c)the name and address of the person acting for the decision-maker to whom the application is to be made.

21.  The undertaker shall no later than 28 days from the date that the plans submitted to and certified by the decision-maker in accordance with article 32, provide a set of those plans to Network Rail in the form of a computer disc with read only memory.