The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014

Status:

Dyma’r fersiwn wreiddiol (fel y’i gwnaed yn wreiddiol). This item of legislation is currently only available in its original format.

Barn Elms

5.  The table below sets out the specific requirements for the Barn Elms site—

TitleRefText
CoCP Part BBAREL1Until completion of construction the authorised development shall be carried out in accordance with the CoCP Part A subject to the site specific variations set out in CoCP Part B for this site, unless otherwise agreed with the relevant planning authority in consultation with other relevant stakeholders.
Detailed design approval for permanent above-ground structuresBAREL2

(1) Construction of any permanent above-ground structure shall not commence until details of the design (including size, external appearance and samples of materials), which shall accord with the design principles for this site, the Site works parameter plan and the indicative Kiosk and ventilation column design intent plan (Drawing No. DCO-PP-04X-BAREL-070017), are submitted to and approved by the relevant planning authority.

(2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority.

Contaminated landBAREL3

Site-specific remediation strategy

(1) No works shall be carried out at this site (except for demolition of existing buildings, works in the highway including site access, works to trees and installation of monitoring equipment), unless otherwise agreed, until the following are submitted to and approved by the relevant planning authority in consultation with the Environment Agency—

a. a preliminary risk assessment and site investigation scheme which identifies—

all previous uses

potential contaminants associated with those uses

a conceptual model of the site indicating sources, pathways and receptors

a qualitative risk assessment of any potentially unacceptable risks arising from contamination at the site

a proposed site investigation scheme providing information for a detailed quantitative assessment of the risk to all receptors that may be affected, including those off-site.

b. a remediation strategy which includes—

(i) a detailed quantitative risk assessment

(ii) an options appraisal giving full details of the remediation measures required and how they shall be carried out

(iii) a verification plan providing details of the data to be collected in order to demonstrate that the works set out in the remediation strategy are complete and identifying any requirements for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action

(iv) a programme for the submission of elements detailed in (3) and (4) below.

(2) The authorised development shall be carried out in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency.

Verification report

(3) Prior to completion of the works, a verification report demonstrating completion of the works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The report shall include results of sampling and monitoring carried out in accordance with the approved details to demonstrate that the site remediation criteria were met. It shall also include a plan for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action as identified in the verification plan.

(4) The long-term monitoring and maintenance plan shall be implemented in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency.

Unexpected contamination

(5) If, in carrying out any works on this site, contamination not previously identified is found to be present, then unless otherwise agreed by the relevant planning authority, no further development or works shall be carried out in the part of the site in which the contamination is identified until a remediation strategy is submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority.

ArchaeologyBAREL4

Site-specific archaeological written scheme of investigation

(1) No excavation shall be carried out until a SSAWSI (which shall accord with the OAWSI) is submitted to and approved by the relevant planning authority in consultation with the HBMCE.

(2) The authorised development shall be carried out in accordance with the approved details by a suitably qualified person or body.

Landscaping worksBAREL5

(1) Construction of the permanent above-ground structures shall not commence until details of the landscaping, which shall accord with the indicative Proposed landscape plan (Drawing No. DCO-PP-04X-BAREL-070013) and the design principles for this site, are submitted to and approved by the relevant planning authority.

(2) Unless otherwise agreed by the relevant planning authority, the landscaping information required in paragraph (1) above shall comprise details of all hard and soft landscaping works including:

a. location, quantity, species, size and density of any proposed planting

b. cultivation, importation of materials and other operations to ensure plant establishment

c. monitoring and maintenance (including any maintenance or restoration of landscaping required after tunnel commissioning)

d. proposed finished ground levels

e. hard-surfacing materials

f. minor structures such as furniture, refuse or other storage units, signs and lighting

g. retained historic landscape features and proposals for restoration, where relevant

h. a programme for implementation of all landscaping works

i. details of fencing/enclosures

j. vehicular and pedestrian access, parking and circulation areas, (including details of areas of public access)

k. proposed and existing functional services above and below ground, including drainage, power and communications cables and pipelines, manholes and supports

l. details of existing trees to be retained

(3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority.

(4) The approved landscaping works shall be carried out by suitably trained or qualified personnel to a reasonable standard in accordance with the relevant recommendations of appropriate British Standards or other recognised codes of good practice.

Replacement trees and shrubs

(5) If, within a period of five years from the date of the planting of any tree or shrub, that tree or shrub (or any tree or shrub planted to replace it) is uprooted or destroyed or dies, another tree or shrub of the same species and size as that originally planted shall be planted in the same place, unless the relevant planning authority approves any variation.

Construction traffic management planBAREL6

(1) Work No. 4a shall not commence until a traffic management plan (which shall accord with the CoCP) is submitted to and approved by the relevant planning authority in consultation with TfL.

(2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with TfL.

Travel planBAREL7

(1) Work No. 4a shall not commence until a site-specific construction workforce travel plan, which shall accord with the Draft Project Framework Travel Plan, is submitted to and approved by the relevant planning authority in consultation with TfL.

(2) The approved travel plan(s) shall be implemented from commencement of development of Work Nos. 4a and 4b and remain in place for the duration of the construction works, unless otherwise approved by the relevant planning authority in consultation with TfL.

Specification of accesses (construction and operational)BAREL8

(1) Authorised development consisting of construction in or alteration of Rocks Lane or the construction or alteration of any highway structures which form part of Rocks Lane shall not commence until details of the design, which shall accord with the design principles for this site, are submitted to and approved by the local highway authority. Any such works shall be completed prior to their use.

(2) The information required in paragraph 1 above shall include details of any permanent works for a new or altered surface and foul water drainage system for Rocks Lane and any permanent works for a new or modified highway lighting scheme for Rocks Lane.

(3) The authorised development shall be carried out in accordance with the approved details, unless otherwise agreed by the highway authority.

Surface water drainageBAREL9

(1) Construction of the permanent above-ground structures or landscaping shall not commence until details of the surface water drainage system for this site (including means of pollution control, an assessment of the hydrological and hydrogeological context and how the scheme shall be maintained and managed following completion), which shall accord with the design principles for this site, are submitted to and approved by the relevant planning authority in consultation with the Environment Agency.

(2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the Environment Agency, and completed prior to use of the authorised development.

Re-provision of changing roomsBAREL10

(1) Construction of the permanent replacement changing room shall not commence until details (including its location), which shall accord with the appropriate design principles, are submitted to and approved by the relevant planning authority.

(2) The existing changing room facility shall not be demolished until the replacement changing room is complete and available for use, or a temporary replacement facility is installed and available for use. Any temporary replacement changing room facility shall not be installed until details are submitted to and approved by the relevant planning authority.

(3) If any temporary replacement facility is installed, then a permanent replacement changing room shall subsequently be provided prior to the completion of the works at the site.

Relocation of track and field facilitiesBAREL11Construction of the access road (Work No. 4c (ii)) shall not commence until details of the relocated track and field facilities are submitted to and approved by the relevant planning authority. The authorised development shall be carried out in accordance with the approved details.
Construction and operational access roadBAREL12

(1) Construction of the proposed construction access road (Work No. 4c (ii)) shall not commence until details of the design of the construction access road including its alignment, vehicle passing points and hoarding arrangements, are submitted to and approved by the relevant planning authority in consultation with the landowner (the London Borough of Wandsworth).

(2) Construction of the proposed permanent access road shall not commence until details of the design of the permanent access road, including its alignment and surface materials, are submitted to and approved by the relevant planning authority in consultation with the landowner (the London Borough of Wandsworth).

(3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority.

Commissioning worksBAREL13

(1) On or before the completion of the landscaping works approved further to requirement BAREL5 (landscaping), the undertaker shall give notice to the relevant planning authority.

(2) (Save for works carried out in accordance with (5) below) within 1 month of the notice under (1) the undertaker shall:

a. remove all hoarding or other temporary enclosure from the site; and

b. make the site available for sports use in accordance with the approved landscape scheme.

(3) The undertaker shall provide a ‘commissioning notice’ to the relevant planning authority at least 2 months before undertaking any commissioning works. The notice shall include:

a. a programme for the commissioning works; and

b. a location plan for any fencing or hoarding associated with those works (including identifying areas to be available for sports use).

(4) The undertaker shall provide a ‘commissioning confirmation notice’ 21 days prior to starting the commissioning works, confirming the date of commencement of commissioning.

(5) The commissioning works shall be undertaken in accordance with the programme in the commissioning notice and the location plan unless otherwise agreed with the relevant planning authority.

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill