PART 3Requirements

Time limits

1.  The authorised development shall commence no later than the expiration of five years beginning with the date this Order comes into force.

2.  Detailed design parameters

3.—(1) Subject to sub-paragraph (2), no wind turbine generator forming part of the authorised development shall—

(a)exceed a height of 223 metres when measured from MHWS to the tip of the vertical blade;

(b)exceed a height of 123 metres when measured from MHWS to the height of the centreline of the generator shaft forming part of the hub;

(c)exceed a rotor diameter of 200 metres;

(d)be less than 700 metres from the nearest WTG or be greater than 1,960 metres from the nearest WTG in either direction;

(e)have a distance of less than 22 metres between the lowest point of the rotating blade of the wind turbine and MHWS.

(2) References to the location of a wind turbine generator are references to the centre point of the tower of that turbine.

4.—(1) The total number of offshore substations forming part of the authorised development shall not exceed one.

(2) The dimensions of the offshore substation forming part of the authorised development (excluding helihoist facilities, towers, masts and cranes) shall not exceed 50 metres in height when measured from LAT, 40 metres in length and 30 metres in width.

(3) The offshore substation shall have no more than one supporting foundation.

5.  The total length of the cables comprising Work No. 1(b) must not exceed 65 kilometres and the total length of the cables comprising Work No. 3 must not exceed 17 kilometres.

6.—(1) Each steel monopile foundation forming part of the authorised development (excluding scour protection) shall not have a diameter which is greater than 8 metres.

(2) Each gravity base foundation forming part of the authorised development (excluding scour protection) must not have—

(a)a diameter at the level of the seabed which is greater than 35 metres;

(b)in the case of the WTGs, a base height which is greater than 6 metres above the level of the seabed;

(c)in the case of the offshore substation, a base height which is greater than 16 metres above the level of the seabed and less than 1 metre below LAT;

(d)in the case of the WTGs, a column diameter of greater than 9 metres.

(3) Each jacket foundation forming part of the authorised development (excluding scour protection) must not have—

(a)a width spacing between each leg at the level of the seabed which is greater than 35 metres;

(b)a leg diameter which is greater than 3 metres;

(c)a width spacing between each leg at MHWS which is greater than 35 metres;

(d)a pile sleeve height which is greater than 18 metres above the level of the seabed;

(e)a pile diameter which is more than 3 metres;

(f)more than one pile per leg, save in the case of the offshore substation where it shall not have more than four piles per leg;

(g)more than four legs;

(h)in the case of the offshore substation only, a suction caisson per leg which is greater than 15 metres in diameter.

(4) To reduce potential impacts on adult salmon migration—

(a)no more than 69 steel monopile foundations with a pile diameter of 6 metres or less (excluding scour protection) shall be installed as part of the authorised development;

(b)no more than 65 steel monopile foundations with a pile diameter between 6 metres and 6.5 metres (excluding scour protection) shall be installed as part of the authorised development;

(c)no more than 55 steel monopile foundations with a pile diameter between 6.5 metres and 7.5 metres (excluding scour protection) shall be installed as part of the authorised development;

(d)no more than 45 steel monopile foundations with a pile diameter between 7.5 metres and 8 metres (excluding scour protection) shall be installed as part of the authorised development.

Lighting

7.  The undertaker must exhibit such lights, with such shape, colour and character as are required by the Air Navigation Order 2009(1) or as directed by the CAA.

Decommissioning

8.  No authorised development shall commence until a written decommissioning programme in compliance with any notice served upon the undertaker by the Secretary of State pursuant to section 105(2) of the 2004 Act has been submitted to the Secretary of State for approval.

Navigational radar scheme at the Port of Liverpool

9.—(1) No construction of any wind turbine generator forming part of the authorised development shall commence until the Secretary of State having consulted with the Operator is satisfied that appropriate mitigation will be implemented and maintained for the life of the authorised development and that arrangements have been put in place with the Operator to ensure that such appropriate mitigation is implemented.

(2) For the purposes of this requirement—

“appropriate mitigation” means a navigational radar scheme to prevent or remove any adverse impacts which the operation of the authorised development will have on the Operator’s ability to provide safe navigation within the limits of the Port of Liverpool during the life of the authorised development;

“approved mitigation” means the appropriate mitigation measures agreed with the Operator authorised to provide safe navigation within the limits of the Port of Liverpool at the time the Secretary of State confirms in writing that he is satisfied in accordance with sub-paragraph (1);

“Operator” means Mersey Docks and Harbour Company Limited incorporated under the Companies Act (7438262) whose registered office is Maritime Centre, Port of Liverpool, Liverpool, Merseyside, L21 1LA or such other organisation as is authorised from time to time under Docks and Harbours Act 1972 to provide safe navigation within the limits of the Port of Liverpool.

(3) The undertaker shall thereafter comply with all obligations contained within the approved mitigation for the life of the authorised development.

Air traffic services at Warton Aerodrome

10.—(1) No construction of any wind turbine generator forming part of the authorised development shall commence until the Secretary of State, having consulted with the Ministry of Defence and the Operator, confirms in writing that he is satisfied that appropriate mitigation will be implemented and maintained for the life of the authorised development and that arrangements have been put in place with the Operator to ensure that such appropriate mitigation is implemented.

(2) For the purposes of this requirement—

“appropriate mitigation” means measures to prevent or remove any adverse impacts which the operation of the authorised development will have on the Operator’s ability to provide safe and efficient air traffic services for Warton Aerodrome during the life of the authorised development;

“approved mitigation” means the appropriate mitigation measures agreed with the Ministry of Defence and the Operator at the time the Secretary of State confirms in writing that he is satisfied in accordance with sub-paragraph (1);

“Ministry of Defence” means as represented by Defence Infrastructure Organisation – Safeguarding, Kingston Road, Sutton Coldfield, B75 7RL or any successor body;

“Operator” means BAE Systems (Operations) Limited incorporated under the Companies Act (Company Number 01996687) whose registered office is Warwick House, PO Box 87, Farnborough Aerospace Centre, Farnborough, Hants, GU14 6YU or such other organisation as is licensed from time to time under sections 5 and 6 of the Transport Act 2000 to provide air traffic services for Warton Aerodrome.

(3) The undertaker shall thereafter comply with all obligations contained within the approved mitigation for the life of the authorised development.

Primary surveillance radars at Lytham St Annes and Great Dun Fell

11.—(1) No construction of any wind turbine generator forming part of the authorised development shall commence until the Secretary of State in consultation with the Operator is satisfied that a primary radar mitigation scheme has been agreed in order to avoid the impact of the development on the primary radar of the Operator located at St Annes and Great Dun Fell and on associated air traffic management operations.

(2) No construction of any wind turbine generator forming part of the authorised development shall commence until the Operator has confirmed to the Secretary of State that an approved primary radar mitigation scheme has been implemented and the development shall thereafter be operated fully in accordance with such approved scheme.

(3) For the purposes of this requirement—

“Operator” means NATS (En Route) plc, incorporated under the Companies Act (4129273) whose registered office is 4000 Parkway, Whiteley, Fareham, Hants, PO15 7FL or such other organisation licensed from time to time under sections 5 and 6 of the Transport Act 2000 to provide air traffic services to the relevant managed area (within the meaning of section 40 of that Act);

“primary radar mitigation scheme” means a detailed scheme agreed with the Operator which sets out the measures to be taken to avoid at all times the impact of the development on the St Annes and Great Dun Fell primary radars and on air traffic management operations of the Operator.

Air traffic services at Liverpool John Lennon Airport

12.—(1) No construction of any wind turbine generator forming part of the authorised development shall commence until the Secretary of State having consulted with the Operator and the CAA is satisfied that appropriate mitigation will be implemented and maintained for the life of the authorised development and that arrangements have been put in place with the Operator to ensure that such appropriate mitigation is implemented.

(2) For the purposes of this requirement—

“appropriate mitigation” means measures to prevent or remove any adverse impacts which the operation of the authorised development will have on the Operator’s ability to provide safe and efficient air traffic services for Liverpool John Lennon Airport during the life of the authorised development;

“approved mitigation” means the appropriate mitigation measures agreed with the CAA and the Operator licensed to provide safe and efficient air traffic services for Liverpool John Lennon Airport at the time the Secretary of State confirms in writing that he is satisfied in accordance with sub-paragraph (1);

“Operator” means Liverpool Airport Limited incorporated under the Companies Act (2116704) whose registered office is Liverpool John Lennon Airport, Liverpool, L24 1YD or such other organisation as is licensed from time to time under sections 5 and 6 of the Transport Act 2000 to provide air traffic services for Liverpool John Lennon Airport.

(3) The undertaker shall thereafter comply with all obligations contained within the approved mitigation for the life of the authorised development.

Community liaison

13.—(1) No installation of piled foundations shall commence until a community liaison scheme has been submitted to and approved by Wirral Metropolitan Borough Council.

(2) The community liaison scheme shall include—

(a)details of how the undertaker will liaise with the local community to ensure residents are informed of how the installation of the piled foundations is progressing;

(b)a mechanism for dealing with complaints from the local community; and

(c)a nominated representative of the undertaker who will have the lead role in liaising with local residents and Wirral Metropolitan Borough Council.

(3) The undertaker shall comply with the approved community liaison scheme throughout the period during which piling is being undertaken.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill