SCHEDULE 2Deemed marine licence under the Marine and Coastal Access Act 2009 – generation assets

PART 2Conditions

Pre-construction plans and documentation

11.—(1) Each programme, statement, plan, protocol or scheme required to be approved under condition 10 shall be submitted for approval at least four months prior to the intended start of construction, except where otherwise stated or unless otherwise agreed in writing by the MMO.

(2) The licensed activities shall be carried out in accordance with the approved plans, protocols, statements, schemes and details approved under condition 10, unless otherwise agreed in writing by the MMO.