The Walney Extension Offshore Wind Farm Order 2014

Access to worksE+W

13.  The undertaker may, for the purposes of the authorised project—

(a)form and lay out means of access, or improve existing means of access, in the locations specified in columns (1) and (2) of Schedule 5 (access to works); and

(b)with the approval of the relevant planning authority after consultation with the highway authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised project.

Commencement Information

I1Art. 13 in force at 28.11.2014, see art. 1