There are currently no known outstanding effects for the The London Underground (Northern Line Extension) Order 2014, PART 7. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 7E+W+SPROTECTION FOR THE MARINE MANAGEMENT ORGANISATION

77.—(1) The following provisions of this Part of this Schedule have effect unless otherwise agreed in writing between LUL and the MMO.E+W+S

(2) In this Part of this Schedule—

“the MMO” means the Marine Management Organisation;

“construction” includes execution, placing, altering, replacing, relaying and removal and “construct” and “constructed” are to be construed accordingly;

“plans” includes sections, drawings, specifications and method statements;

“specified work” means so much of any authorised work as is—

(a)

a licensable marine activity under section 66 (licensable marine activities) of the 2009 Act;

(b)

not exempt from requiring a marine licence by virtue of an order made under section 74 (exemptions specified by order) of the 2009 Act; and

(c)

over, in, on, or under that part of the UK marine area that is within the river area; and

“UK marine area” has the definition given to it in section 42 (UK marine area) of the 2009 Act.

Commencement Information

I1Sch. 8 para. 77 in force at 15.12.2014, see art. 1

78.—(1) Before beginning to construct or carry out any specified work, LUL must submit to the MMO plans of the specified work and such further particulars available to LUL as the MMO may within 28 days of the submission of the plans reasonably require.E+W+S

(2) Any specified work must not be constructed or carried out except in accordance with such plans as may be approved in writing by the MMO, or determined under paragraph 85.

(3) Any approval of the MMO required under this paragraph—

(a)must not be unreasonably withheld;

(b)must be given or refused within 3 months of the specified day, and in the case of a refusal, will be accompanied by a statement of the grounds of refusal; and

(c)may be given subject to such reasonable requirements as the MMO may make for the protection of the cleanliness, safety, productivity and biological diversity of the River Thames or otherwise in the discharge of the MMO’s statutory duties.

(4) The MMO must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (3)(b).

(5) In this paragraph, “the specified day” means, in relation to any specified work—

(a)the day on which plans of that work are submitted to the MMO under sub-paragraph (1); or

(b)the day on which LUL provides the MMO with all further particulars of the specified work that have been requested by the MMO under that sub-paragraph,

whichever is the later.

Commencement Information

I2Sch. 8 para. 78 in force at 15.12.2014, see art. 1

79.  Without limitation on the scope of paragraph 78, the requirements which the MMO may make under that paragraph include conditions in relation to any specified work as to—E+W+S

(a)the method or manner in which it is carried out;

(b)the times of year at which it may be carried out;

(c)the handling (other than disposal) of dredged material; and

(d)appropriate and proportionate mitigation measures to minimise any adverse impacts on the marine environment, marine biota (in particular, migratory fish species) and archaeological and heritage assets.

Commencement Information

I3Sch. 8 para. 79 in force at 15.12.2014, see art. 1

80.  Where any specified work involves dredging, the plans submitted under paragraph 78(1) must include the results of laboratory testing of the material to be dredged. This testing must be undertaken by a laboratory which is accredited to the standard required by the MMO and the tests undertaken must be to the standard accepted by the MMO.E+W+S

Commencement Information

I4Sch. 8 para. 80 in force at 15.12.2014, see art. 1

81.—(1) Subject to sub-paragraph (2), any specified work must be constructed or carried out—E+W+S

(a)in accordance with the plans approved in writing by the MMO or determined under this Part of this Schedule; and

(b)to the reasonable satisfaction of the MMO.

(2) LUL must give to the MMO not less than 14 days’ notice in writing of LUL’s intention to commence construction or the carrying out of any specified work and LUL must also give to the MMO notice in writing of the completion of the work not later than 7 days after the date on which the work is completed.

Commencement Information

I5Sch. 8 para. 81 in force at 15.12.2014, see art. 1

82.  Where there is any actual or potential conflict between any requirements imposed by the Environment Agency under Part 3 of this Schedule and any requirement made by the MMO under paragraph 78, the MMO must liaise with the Environment Agency in order to seek expeditiously to remove that actual or potential conflict but if it persists, then the requirement of the MMO may be referred for determination under paragraph 85.E+W+S

Commencement Information

I6Sch. 8 para. 82 in force at 15.12.2014, see art. 1

83.  Where there is any actual or potential conflict between any terms and conditions imposed by the Port of London Authority under Part 6 of this Schedule and any requirement made by the MMO under paragraph 78, the MMO must liaise with the Port of London Authority in order to seek expeditiously to remove that actual or potential conflict but if it persists, then the requirement of the MMO may be referred for determination under paragraph 85.E+W+S

Commencement Information

I7Sch. 8 para. 83 in force at 15.12.2014, see art. 1

84.  LUL must indemnify the MMO in respect of all costs, charges and expenses which the MMO may reasonably incur or have to pay or which it may sustain—E+W+S

(a)for any sediment analyses and testing including the interpretation of the results;

(b)in the examination or approval of plans under this Part of this Schedule; and

(c)in the inspection of the construction of the specified works under sections 246 (power to board and inspect vessels and marine installations) to 248 (power to enter and inspect vehicles) of the 2009 Act.

Commencement Information

I8Sch. 8 para. 84 in force at 15.12.2014, see art. 1

85.  Any dispute arising between LUL and the MMO under this Part of this Schedule is to be determined by arbitration under article 48 (arbitration) if the parties agree, but otherwise is to be determined by the Secretary of State for Environment, Food and Rural Affairs and the Secretary of State for Transport acting jointly on a reference to them by LUL or the MMO, after giving notice in writing by one to the other.E+W+S

Commencement Information

I9Sch. 8 para. 85 in force at 15.12.2014, see art. 1

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill