xmlns:atom="http://www.w3.org/2005/Atom"

PART 3Streets

Temporary stopping up of streets

13.—(1) Network Rail, during and for the purposes of carrying out the authorised development, may temporarily stop up, alter or divert any street and may for any reasonable time—

(a)divert the traffic from the street; and

(b)subject to paragraph (3), prevent all persons from passing along the street.

(2) Without limitation on the scope of paragraph (1), Network Rail may use any street stopped up under the powers conferred by this article within the Order limits as a temporary working site.

(3) Network Rail must provide reasonable access for pedestrians going to or from premises abutting a street affected by the temporary stopping up, alteration or diversion of a street under this article if there would otherwise be no such access.

(4) Network Rail must not temporarily stop up, alter or divert or use as a temporary working site any street without the consent of the street authority which may attach reasonable conditions to any consent, but such consent must not be unreasonably withheld.

(5) Any person who suffers loss by the suspension of any private right of way under this article is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.