The Public Contracts Regulations 2015, Cross Heading: SECTION 5 is up to date with all changes known to be in force on or before 04 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

SECTION 5U.K.Conduct of the Procedure

SUB-SECTION 5U.K.Preparation
Preliminary market consultationsU.K.

40.—(1) Before commencing a procurement procedure, contracting authorities may conduct market consultations with a view to preparing the procurement and informing economic operators of their procurement plans and requirements.

(2) For this purpose, contracting authorities may, for example, seek or accept advice from independent experts or authorities or from market participants.

(3) Such advice may be used in the planning and conduct of the procurement procedure, provided that it does not have the effect of distorting competition and does not result in a violation of the principles of non-discrimination and transparency.

Prior involvement of candidates or tenderersU.K.

41.—(1) Where a candidate or tenderer, or an undertaking related to a candidate or tenderer—

(a)has advised the contracting authority, whether in the context of regulation 40 or not, or

(b)has otherwise been involved in the preparation of the procurement procedure,

the contracting authority shall take appropriate measures to ensure that competition is not distorted by the participation of that candidate or tenderer.

(2) Such measures shall include—

(a)the communication to the other candidates and tenderers of relevant information exchanged in the context of or resulting from the involvement of the candidate or tenderer in the preparation of the procurement procedure; and

(b)the fixing of adequate time limits for the receipt of tenders.

(3) The candidate or tenderer concerned shall only be excluded from the procedure where there are no other means to ensure compliance with the duty to treat economic operators equally in accordance with regulation 18(1).

(4) Prior to any such exclusion, candidates or tenderers shall be given the opportunity to prove that their involvement in preparing the procurement procedure is not capable of distorting competition.

(5) The measures taken under this regulation shall be documented in the report referred to in regulation 84(1).

Technical specificationsU.K.

42.—(1) The technical specifications shall be set out in the procurement documents.

Scope of the technical specifications

(2) The technical specifications shall lay down the characteristics required of works, services or supplies.

(3) In the case of a public works contract, the technical specifications shall define any characteristics required of a material, product or supply so that it fulfils the use for which it is intended by the contracting authority.

(4) The characteristics referred to in paragraph (3) may include—

(a)levels of environmental and climate performance, design for all requirements (including accessibility for disabled persons) and conformity assessment, performance, safety or dimensions, including the procedures concerning quality assurance, terminology, symbols, testing and test methods, packaging, marking and labelling, user instructions and production processes and methods at any stage of the life cycle of the works;

(b)rules relating to design and costing, the test, inspection and acceptance conditions for works and methods or techniques of construction and all other technical conditions which the contracting authority is in a position to prescribe, under general or specific regulations, in relation to the finished works and to the materials or parts which they involve.

(5) In the case of public supply or service contracts, the required characteristics may include quality levels, environmental and climate performance levels, design for all requirements (including accessibility for disabled persons) and conformity assessment, performance, use of the product, safety or dimensions, including requirements relevant to the product as regards the name under which the product is sold, terminology, symbols, testing and test methods, packaging, marking and labelling, user instructions, production processes and methods at any stage of the life cycle of the supply or service and conformity assessment procedures.

(6) In the case of any public contract, the required characteristics may also refer to—

(a)the specific process or method of production or provision of the requested works, supplies or services, or

(b)a specific process for another stage of its life cycle,

even where such factors do not form part of the characteristics' material substance provided that they are linked to the subject-matter of the contract and proportionate to its value and its objectives.

(7) The technical specifications may also specify whether the transfer of intellectual property rights will be required.

Formulating the technical specifications

(8) For all procurement which is intended for use by natural persons, whether the general public or staff of the contracting authority, the technical specifications shall, except in duly justified cases, be drawn up so as to take into account accessibility criteria for disabled persons or design for all users.

(9) Where mandatory accessibility requirements are adopted by a legal act of the EU, technical specifications shall, as far as accessibility criteria for disabled persons or design for all users are concerned, be defined by reference thereto.

(10) Technical specifications shall afford equal access of economic operators to the procurement procedure and shall not have the effect of creating unjustified obstacles to the opening up of public procurement to competition.

(11) Without prejudice to mandatory national technical rules, to the extent that they are compatible with EU law, the technical specifications shall be formulated in one of the following ways:—

(a)in terms of performance or functional requirements, including environmental characteristics, provided that the parameters are sufficiently precise to allow tenderers to determine the subject-matter of the contract and to allow contracting authorities to award the contract;

(b)by reference to technical specifications and, in order of preference, to—

(i)national standards transposing European standards,

(ii)European Technical Assessments,

(iii)common technical specifications,

(iv)international standards,

(v)other technical reference systems established by the European standardisation bodies, or

(vi)when none of the above exist, national standards, national technical approvals or national technical specifications relating to the design, calculation and execution of the works and use of the supplies,

but each reference shall be accompanied by the words ‘or equivalent’;

(c)in terms of performance or functional requirements as referred to in sub-paragraph (a), with reference to the technical specifications referred to in sub-paragraph (b) as a means of presuming conformity with such performance or functional requirements;

(d)by reference to the technical specifications referred to in sub-paragraph (b) for certain characteristics, and by reference to the performance or functional requirements referred to in sub-paragraph (a) for other characteristics.

(12) Unless justified by the subject-matter of the contract, technical specifications shall not refer to a specific make or source, or a particular process which characterises the products or services provided by a specific economic operator, or to trade marks, patents, types or a specific origin or production with the effect of favouring or eliminating certain undertakings or certain products.

(13) But such reference is permitted on an exceptional basis, where a sufficiently precise and intelligible description of the subject-matter of the contract in accordance with paragraph (11) is not possible, in which case the reference shall be accompanied by the words “or equivalent”.

Applying the technical specifications

(14) Where a contracting authority uses the option of referring to the technical specifications referred to in paragraph (11)(b), it shall not reject a tender on the grounds that the works, supplies or services tendered for do not comply with the technical specifications to which it has referred, once the tenderer proves in its tender by any appropriate means, including the means of proof referred to in regulation 44, that the solutions proposed satisfy in an equivalent manner the requirements defined by the technical specifications.

(15) Where a contracting authority uses the option laid down in paragraph (11)(a) to formulate technical specifications in terms of performance or functional requirements, it shall not reject a tender for works, supplies or services which comply with a national standard transposing a European standard, a European technical approval, a common technical specification, an international standard or a technical reference system established by a European standardisation body, where those address the performance or functional requirements which it has laid down.

(16) In its tender, the tenderer shall prove by any appropriate means, including those referred to in regulation 44, that the work, supply or service in compliance with the standard meets the performance or functional requirements of the contracting authority.

LabelsU.K.

43.—(1) Where contracting authorities intend to purchase works, supplies or services with specific environmental, social or other characteristics they may, in the technical specifications, the award criteria or the contract performance conditions, require a specific label as means of proof that the works, services or supplies correspond to the required characteristics, provided that all of the following conditions are fulfilled:—

(a)the label requirements only concern criteria which are linked to the subject-matter of the contract and are appropriate to define characteristics of the works, supplies or services that are the subject-matter of the contract;

(b)the label requirements are based on objectively verifiable and non-discriminatory criteria;

(c)the labels are established in an open and transparent procedure in which all relevant stakeholders, including government bodies, consumers, social partners, manufacturers, distributors and non-governmental organisations, may participate;

(d)the labels are accessible to all interested parties;

(e)the label requirements are set by a third party over which the economic operator applying for the label cannot exercise a decisive influence.

(2) Where contracting authorities do not require the works, supplies or services to meet all of the label requirements, they shall indicate which label requirements are required.

(3) Contracting authorities requiring a specific label shall accept all labels that confirm that the works, supplies or services meet equivalent label requirements.

(4) Where an economic operator had demonstrably no possibility of obtaining the specific label indicated by the contracting authority, or an equivalent label, within the relevant time limits for reasons that are not attributable to that economic operator, the contracting authority shall accept other appropriate means of proof, which may include a technical dossier from the manufacturer, provided that the economic operator concerned proves that the works, supplies or services to be provided by it fulfil the requirements of the specific label or the specific requirements indicated by the contracting authority.

(5) Where a label fulfils the conditions mentioned in paragraph (1)(b), (c), (d) and (e) but also sets out requirements not linked to the subject-matter of the contract, contracting authorities shall not require the label as such but may define the technical specification by reference to those of the detailed specifications of that label, or, where necessary, parts of it, that are linked to the subject-matter of the contract and are appropriate to define characteristics of that subject-matter.

Test reports, certificates and other means of proofU.K.

44.—(1) Contracting authorities may require that economic operators provide a test report from a conformity assessment body or a certificate issued by such a body as means of proof of conformity with requirements or criteria set out in the technical specifications, the award criteria or the contract performance conditions.

(2) Where contracting authorities require the submission of certificates drawn up by a specific conformity assessment body, certificates from equivalent other conformity assessment bodies shall also be accepted by the contracting authorities.

(3) In paragraphs (1) and (2), “conformity assessment body” means a body that performs conformity assessment activities including calibration, testing, certification and inspection accredited in accordance with Regulation (EC) No 765/2008 of the European Parliament and of the Council M1.

(4) Contracting authorities shall accept appropriate means of proof other than those referred to in paragraphs (1) and (2), such as a technical dossier of the manufacturer, where the economic operator concerned had no access to the certificates or test reports referred to in paragraphs (1) and (2), or no possibility of obtaining them within the relevant time limits, provided that—

(a)the lack of access is not attributable to the economic operator concerned, and

(b)the economic operator concerned thereby proves that the works, supplies or services provided by it meet the requirements or criteria set out in the technical specifications, the award criteria or the contract performance conditions.

Marginal Citations

M1OJ No L 218, 13.8.2008, p30.

VariantsU.K.

45.—(1) Contracting authorities may authorise or require tenderers to submit variants.

(2) Contracting authorities shall indicate, in the contract notice or in the invitation to confirm interest, whether or not they authorise or require variants.

(3) Variants shall not be authorised or required without such an indication and shall be linked to the subject-matter of the contract.

(4) Contracting authorities authorising or requiring variants shall state in the procurement documents the minimum requirements to be met by the variants and any specific requirements for their presentation, in particular whether variants may be submitted only where a tender which is not a variant has also been submitted.

(5) Contracting authorities shall ensure that the chosen award criteria can be applied to variants meeting those minimum requirements as well as to conforming tenders which are not variants.

(6) Only variants meeting the minimum requirements laid down by the contracting authorities shall be taken into consideration.

(7) In procedures for awarding public supply or service contracts, contracting authorities that have authorised or required variants shall not reject a variant on the sole ground that it would, where successful, lead to either a public service contract rather than a public supply contract or a public supply contract rather than a public service contract.

Division of contracts into lotsU.K.

46.—(1) Contracting authorities may decide to award a contract in the form of separate lots and may determine the size and subject-matter of such lots.

(2) Contracting authorities shall provide an indication of the main reasons for their decision not to subdivide into lots, which shall be included in the procurement documents or the report referred to in regulation 84(1).

(3) Contracting authorities shall indicate, in the contract notice or in the invitation to confirm interest, whether tenders may be submitted for one, for several or for all of the lots.

(4) Contracting authorities may, even where tenders may be submitted for several or all lots, limit the number of lots that may be awarded to one tenderer, provided that the maximum number of lots per tenderer is stated in the contract notice or in the invitation to confirm interest.

(5) Contracting authorities shall indicate in the procurement documents the objective and non-discriminatory criteria or rules they intend to apply for determining which lots will be awarded where the application of the award criteria would result in one tenderer being awarded more lots than the maximum number.

(6) Where more than one lot may be awarded to the same tenderer, contracting authorities may award contracts combining several or all lots where they have specified in the contract notice or in the invitation to confirm interest that they reserve the possibility of doing so and indicate the lots or groups of lots that may be combined.

Setting time limitsU.K.

47.—(1) When fixing the time limits for the receipt of tenders and requests to participate, contracting authorities shall take account of the complexity of the contract and the time required for drawing up tenders, without prejudice to the minimum time limits set out in regulations 27 to 31.

(2) Where tenders can be made only after a visit to the site or after on-the-spot inspection of the documents supporting the procurement documents, the time limits for the receipt of tenders, which shall be longer than the minimum time limits set out in regulations 27 to 31, shall be fixed so that all economic operators concerned may be aware of all the information needed to produce tenders.

(3) Contracting authorities shall extend the time limits for the receipt of tenders so that all economic operators concerned may be aware of all the information needed to produce tenders in the following cases:—

(a)where, for whatever reason, additional information, although requested by the economic operator in good time, is not supplied at the latest 6 days before the time limit fixed for the receipt of tenders;

(b)where significant changes are made to the procurement documents.

(4) The length of the extension shall be proportionate to the importance of the information or change.

(5) In the case of an accelerated procedure, the period mentioned in paragraph (3)(a) shall be 4 days.

(6) Where additional information has either not been requested in good time or its importance with a view to preparing responsive tenders is insignificant, contracting authorities are not required to extend the time limits.

SUB-SECTION 6U.K.Publication and transparency
Prior information noticesU.K.

48.—(1) Contracting authorities may make known their intentions of planned procurements through the publication of a prior information notice.

(2) Such notices shall contain the information set out in section I of part B of Annex V to the Public Contracts Directive.

(3) A contracting authority wishing to publish a prior information notice shall—

(a)send it for publication in accordance with regulation 51; or

(b)publish it on the contracting authority's buyer profile in accordance with regulation 52.

(4) Where the prior information notice is published by the contracting authority on its buyer profile—

(a)the prior information notice shall contain the information set out in part A of Annex V to the Public Contracts Directive, and

(b)the contracting authority shall send for publication, in accordance with regulation 51, a notice of the publication on its buyer profile.

(5) Where sub-central contracting authorities use a prior information notice as a call for competition in accordance with regulation 26(9), the notice shall fulfil all of the following conditions:—

(a)it refers specifically to the supplies, works or services that will be the subject-matter of the contract to be awarded;

(b)it indicates that the contract will be awarded by restricted procedure or competitive procedure with negotiation without further publication of a call for competition and invites interested economic operators to express their interest;

(c)it contains, in addition to the information set out in section 1 of part B of Annex V to the Public Contracts Directive, the information set out in section 2 of that part;

(d)it has been sent for publication between 35 days and 12 months prior to the date on which an invitation is sent for the purposes of regulation 54(1) or (2).

(6) Where paragraph (5) applies, paragraph (3)(b) shall not apply to the notice, but additional publication at national level under regulation 52, if any, may be made on a buyer profile.

(7) The period covered by the prior information notice shall be a maximum of 12 months from the date on which the notice is transmitted for publication.

(8) In the case of public contracts for social and other specific services, the prior information notice referred to in regulation 75(1)(b) may cover a period which is longer than 12 months.

Contract noticesU.K.

49.  Contract notices shall contain the information set out in part C of Annex 5 to the Public Contracts Directive and shall be sent for publication in accordance with regulation 51.

Contract award noticesU.K.

50.—(1) Not later than 30 days after the award of a contract or the conclusion of a framework agreement, following the decision to award or conclude it, contracting authorities shall send for publication a contract award notice on the results of the procurement procedure.

(2) Such notices shall contain the information set out in part D of Annex 5 to the Public Contracts Directive and shall be sent for publication in accordance with regulation 51.

(3) Where the call for competition for the contract concerned has been made in the form of a prior information notice and the contracting authority has decided that it will not award further contracts during the period covered by the prior information notice, the contract award notice shall contain a specific indication to that effect.

(4) In the case of framework agreements, contracting authorities shall not be bound to send a notice of the results of the procurement procedure for each contract based on such an agreement.

(5) In the case of dynamic purchasing systems, contracting authorities shall either—

(a)send a contract award notice within 30 days after the award of each contract based on a dynamic purchasing system, or

(b)group such notices on a quarterly basis, in which case they shall send the grouped notices within 30 days of the end of each quarter.

(6) Certain information on the award of the contract or the conclusion of the framework agreement may be withheld from publication where its release—

(a)would impede law enforcement or would otherwise be contrary to the public interest,

(b)would prejudice the legitimate commercial interests of a particular economic operator, whether public or private, or

(c)might prejudice fair competition between economic operators.

Form and manner of sending notices for publication at EU levelU.K.

51.—(1) The notices required by regulations 48, 49, 50, 72, 75 and 79 to be sent for publication in accordance with this regulation shall be sent by electronic means to the EU Publications Office for publication.

(2) Contracting authorities shall ensure that they are able to supply proof of the dates on which notices are sent to the EU Publications Office for publication.

(3) Where the EU Publications Office has given the contracting authority confirmation of the receipt of the notice and of the publication of the information sent, indicating the date of that publication, that confirmation shall constitute proof of publication.

(4) Contracting authorities may send notices in respect of public contracts to the EU Publications Office for publication even where they are not required by this Part to do so, provided that the notices are sent by electronic means.

Publication at national levelU.K.

Publication on buyer profiles

52.—(1) In addition to the publication of the notices refered to in regulations 48, 49, 50, 75 and 79 by the EU Publications Office, contracting authorities may publish the information contained in them on the internet on a buyer profile.

(2) A buyer profile may also include (in addition to the prior information notices referred to in regulation 48(3)(b))—

(a)information on ongoing invitations to tender, scheduled purchases, contracts concluded, procedures cancelled; and

(b)any useful general information, such as a contact point, a telephone and a fax number, a postal address and an e-mail address.

Timing and content of publication at national level

(3) The notices referred to in regulations 48, 49, 50, 72 and 79, and the information contained in them, shall not be published at national level before they are published by the EU Publications Office.

(4) But publication may in any event take place at national level where contracting authorities have not been notified of the publication by the EU Publications Office within 48 hours after confirmation of the receipt of the notice in accordance with Article 51(5) of the Public Contracts Directive.

(5) Notices published at national level shall not contain information other than that contained in the notices sent to the EU Publications Office or published on a buyer profile, but shall indicate the date of sending of the notice to the EU Publications Office or its publication on the buyer profile.

(6) Where a prior information notice is to be published on a buyer profile for the purposes of regulation 48(3)(b)—

(a)the prior information notice may not be so published before the notice referred to in regulation 48(4)(b) is sent to the EU Publications Office; and

(b)the prior information notice shall indicate the date of that sending.

Electronic availability of procurement documentsU.K.

53.—(1) Contracting authorities shall, by means of the internet, offer unrestricted and full direct access free of charge to the procurement documents from the date of the publication in the Official Journal of a notice sent in accordance with regulation 51 or the date on which an invitation to confirm interest is sent.

(2) The text of the notice or the invitation to confirm interest shall specify the internet address at which the procurement documents are accessible.

(3) Where unrestricted and full direct access free of charge to certain procurement documents cannot be offered by means of the internet for one of the reasons set out in regulation 22(3), contracting authorities may indicate in the notice or the invitation to confirm interest that the procurement documents concerned will be transmitted by means other than the internet in accordance with paragraphs (6) and (7).

(4) Where unrestricted and full direct access free of charge to certain procurement documents cannot be offered by means of the internet because contracting authorities intend to apply regulation 21(3), contracting authorities shall indicate in the notice or the invitation to confirm interest which measures aimed at protecting the confidential nature of the information they require and how access can be obtained to the documents concerned.

(5) In the cases referred to in paragraphs (3) and (4), the time limit for the submission of tenders shall be prolonged by 5 days, except in the cases of duly substantiated urgency referred to in regulations 27(5), 28(10) and 29(10).

(6) Provided that it has been requested in good time, contracting authorities shall supply to all tenderers taking part in the procurement procedure additional information relating to the specifications and any supporting documents not later than 6 days before the time limit fixed for the receipt of tenders.

(7) In the case of an accelerated procedure, the period mentioned in paragraph (6) shall be 4 days.

Invitations to candidatesU.K.

54.—(1) In restricted procedures, competitive dialogue procedures, innovation partnerships and competitive procedures with negotiation, contracting authorities shall simultaneously and in writing invite the selected candidates to submit their tenders or, in the case of a competitive dialogue, to take part in the dialogue.

(2) Where a prior information notice is used as a call for competition in accordance with regulation 26(9), contracting authorities shall simultaneously and in writing invite the economic operators which have expressed their interest to confirm their continuing interest.

(3) The invitations required by paragraphs (1) and (2) shall—

(a)include a reference to the electronic address at which the procurement documents have been made directly available by electronic means, and

(b)be accompanied by the procurement documents, where those documents have not been the subject of unrestricted and full direct access, free of charge, for the reasons referred to in regulation 53(3) or (4) and have not already been made otherwise available.

(4) The invitations required by paragraph (1) shall also contain at least the following information:—

(a)a reference to the call for competition published;

(b)the deadline for the receipt of the tenders, the address to which the tenders must be sent and the language or languages in which the tenders must be drawn up;

(c)in the case of competitive dialogue, the date and the address set for the start of consultation and the language or languages to be used;

(d)a reference to any documents to be submitted, either in support of verifiable declarations by the tenderer in accordance with regulations 59 and 60 and, where appropriate, 62 or to supplement the information referred to in those regulations, and under the conditions laid down in regulations 59, 60 and 62;

(e)the relative weighting of criteria for the award of the contract or, where appropriate, the descending order of importance for such criteria, where they are not given in the contract notice, in the invitation to confirm interest, in the technical specifications or the descriptive document.

(5) But in the case of contracts awarded through a competitive dialogue or an innovation partnership, the information referred to in paragraph (4)(b) shall not appear in the invitation to participate in the dialogue or to negotiate but it shall appear in the invitation to submit a tender.

(6) The invitations required by paragraph (2) shall also contain at least the following information:—

(a)nature and quantity, including all options concerning complementary contracts and, where possible, the estimated time available for exercising these options for renewable contracts, the nature and quantity and, where possible, the estimated publication dates of future notices of competition for works, supplies or services to be put out to tender;

(b)type of procedure, namely restricted procedure or competitive procedure with negotiation;

(c)where applicable, the date on which the delivery of supplies or the execution of works or services is to commence or terminate;

(d)where electronic access cannot be offered, the address and closing date for the submission of requests for procurement documents and the language or languages in which they are to be drawn up;

(e)the address of the contracting authority which is to award the contract;

(f)economic and technical conditions, financial guarantees and information required from economic operators;

(g)the form of the contract which is the subject of the invitation to tender, namely purchase, lease, hire or hire-purchase, or any combination of these; and

(h)the contract award criteria and their weighting or, where appropriate, the order of importance of such criteria, where this information is not given in the prior information notice or the technical specifications or in the invitation to tender or to negotiate.

Informing candidates and tenderersU.K.

55.—(1) Contracting authorities shall as soon as possible inform each candidate and tenderer of decisions reached concerning the conclusion of a framework agreement, the award of a contract or admittance to a dynamic purchasing system, including the grounds for any decision—

(a)not to conclude a framework agreement,

(b)not to award a contract for which there has been a call for competition,

(c)to recommence the procedure, or

(d)not to implement a dynamic purchasing system.

(2) On request from the candidate or tenderer concerned, the contracting authority shall as quickly as possible, and in any event within 15 days from receipt of a written request, inform—

(a)any unsuccessful candidate of the reasons for the rejection of its request to participate;

(b)any unsuccessful tenderer of the reasons for the rejection of its tender, including, for the cases referred to in regulation 42(14) and (15), the reasons for its decision of non-equivalence or its decision that the works, supplies or services do not meet the performance or functional requirements;

(c)any tenderer that has made an admissible tender of the characteristics and relative advantages of the tender selected as well as the name of the successful tenderer or the parties to the framework agreement;

(d)any tenderer that has made an admissible tender of the conduct and progress of negotiations and dialogue with tenderers.

(3) Contracting authorities may decide to withhold certain information referred to in paragraphs (1) and (2) where the release of such information—

(a)would impede law enforcement or would otherwise be contrary to the public interest;

(b)would prejudice the legitimate commercial interests of a particular economic operator, whether public or private; or

(c)might prejudice fair competition between economic operators.

SUB-SECTION 7U.K.Choice of participants and award of contracts
General principles in awarding contracts etcU.K.

56.—(1) Contracts shall be awarded on the basis of criteria laid down in accordance with regulations 67 to 69, provided that the contracting authority has verified in accordance with regulations 59 to 61 that all of the following conditions are fulfilled:—

(a)the tender complies with the requirements, conditions and criteria set out in the contract notice or the invitation to confirm interest and in the procurement documents, taking into account, where applicable, regulation 45;

(b)the tender comes from a tenderer that—

(i)is not excluded in accordance with regulation 57, and

(ii)meets—

(aa)the selection criteria, and

(bb)where applicable, the non-discriminatory rules and criteria referred to in regulation 65.

(2) Contracting authorities may decide not to award a contract to the tenderer submitting the most economically advantageous tender where they have established that the tender does not comply with applicable obligations in the fields of environmental, social and labour law established by EU law, national law, collective agreements or by the international environmental, social and labour law provisions listed in Annex X to the Public Contracts Directive as amended from time to time.

(3) In open procedures—

(a)contracting authorities may decide to examine tenders before verifying the absence of grounds for exclusion and the fulfilment of the selection criteria in accordance with regulations 57 to 64; and

(b)where contracting authorities make use of that possibility, they shall ensure that the verification of absence of grounds for exclusion and of fulfilment of the selection criteria is carried out in an impartial and transparent manner so that no contract is awarded to a tenderer that—

(i)should have been excluded under regulation 57, or

(ii)does not meet the selection criteria set out by the contracting authority.

(4) Where information or documentation to be submitted by economic operators is or appears to be incomplete or erroneous, or where specific documents are missing, contracting authorities may request the economic operators concerned to submit, supplement, clarify or complete the relevant information or documentation within an appropriate time limit, provided that such requests are made in full compliance with the principles of equal treatment and transparency.

Exclusion groundsU.K.

Mandatory exclusions

57.—(1) Contracting authorities shall exclude an economic operator from participation in a procurement procedure where they have established, by verifying in accordance with regulations 59, 60 and 61, or are otherwise aware, that that economic operator has been convicted of any of the following offences:—

(a)conspiracy within the meaning of section 1 or 1A of the Criminal Law Act 1977 M2 or article 9 or 9A of the Criminal Attempts and Conspiracy (Northern Ireland) Order 1983 M3 where that conspiracy relates to participation in a criminal organisation as defined in Article 2 of Council Framework Decision 2008/841/JHA on the fight against organised crime M4;

(b)corruption within the meaning of section 1(2) of the Public Bodies Corrupt Practices Act 1889 M5 or section 1 of the Prevention of Corruption Act 1906 M6;

(c)the common law offence of bribery;

(d)bribery within the meaning of sections 1, 2 or 6 of the Bribery Act 2010 M7, or section 113 of the Representation of the People Act 1983 M8;

(e)where the offence relates to fraud affecting the European Communities' financial interests as defined by Article 1 of the Convention on the protection of the financial interests of the European Communities M9:—

(i)the common law offence of cheating the Revenue;

(ii)the common law offence of conspiracy to defraud;

(iii)fraud or theft within the meaning of the Theft Act 1968 M10, the Theft Act (Northern Ireland) 1969 M11, the Theft Act 1978 M12 or the Theft (Northern Ireland) Order 1978 M13;

(iv)fraudulent trading within the meaning of section 458 of the Companies Act 1985 M14, article 451 of the Companies (Northern Ireland) Order 1986 M15 or section 993 of the Companies Act 2006 M16;

(v)fraudulent evasion within the meaning of section 170 of the Customs and Excise Management Act 1979 M17 or section 72 of the Value Added Tax Act 1994 M18;

(vi)an offence in connection with taxation in the European Union within the meaning of section 71 of the Criminal Justice Act 1993 M19;

(vii)destroying, defacing or concealing of documents or procuring the execution of a valuable security within the meaning of section 20 of the Theft Act 1968 M20 or section 19 of the Theft Act (Northern Ireland) 1969 M21;

(viii)fraud within the meaning of section 2, 3 or 4 of the Fraud Act 2006 M22; or

(ix)the possession of articles for use in frauds within the meaning of section 6 of the Fraud Act 2006, or the making, adapting, supplying or offering to supply articles for use in frauds within the meaning of section 7 of that Act;

(f)any offence listed—

(i)in section 41 of the Counter Terrorism Act 2008 M23; or

(ii)in Schedule 2 to that Act where the court has determined that there is a terrorist connection;

(g)any offence under sections 44 to 46 of the Serious Crime Act 2007 M24 which relates to an offence coverered by subparagraph (f);

(h)money laundering within the meaning of sections 340(11) and 415 of the Proceeds of Crime Act 2002 M25;

(i)an offence in connection with the proceeds of criminal conduct within the meaning of section 93A, 93B or 93C of the Criminal Justice Act 1988 M26 or article 45, 46 or 47 of the Proceeds of Crime (Northern Ireland) Order 1996 M27;

(j)an offence under section 4 of the Asylum and Immigration (Treatment of Claimants, etc.) Act 2004 M28;

(k)an offence under section 59A of the Sexual Offences Act 2003 M29;

(l)an offence under section 71 of the Coroners and Justice Act 2009 M30;

(m)an offence in connection with the proceeds of drug trafficking within the meaning of section 49, 50 or 51 of the Drug Trafficking Act 1994 M31; or

(n)any other offence within the meaning of Article 57(1) of the Public Contracts Directive—

(i)as defined by the law of any jurisdiction outside England and Wales and Northern Ireland; or

(ii)created, after the day on which these Regulations were made, in the law of England and Wales or Northern Ireland.

(2) The obligation to exclude an economic operator also applies where the person convicted is a member of the administrative, management or supervisory body of that economic operator or has powers of representation, decision or control in the economic operator.

Mandatory and discretionary exclusions for non-payment of taxes etc

(3) An economic operator shall be excluded from participation in a procurement procedure where—

(a)the contracting authority is aware that the economic operator is in breach of its obligations relating to the payment of taxes or social security contributions; and

(b)the breach has been established by a judicial or administrative decision having final and binding effect in accordance with the legal provisions of the country in which it is established or with those of any of the jurisdictions of the United Kingdom.

(4) Contracting authorities may exclude an economic operator from participation in a procurement procedure where the contracting authority can demonstrate by any appropriate means that the economic operator is in breach of its obligations relating to the payment of taxes or social security contributions.

(5) Paragraphs (3) and (4) cease to apply when the economic operator has fulfilled its obligations by paying, or entering into a binding arrangement with a view to paying, the taxes or social security contributions due, including, where applicable, any interest accrued or fines.

Exceptions to mandatory exclusion

(6) A contracting authority may disregard any of the prohibitions imposed by paragraphs (1) to (3), on an exceptional basis, for overriding reasons relating to the public interest such as public health or protection of the environment.

(7) A contracting authority may also disregard the prohibition imposed by paragraph (3) where an exclusion would be clearly disproportionate, in particular—

(a)where only minor amounts of taxes or social security contributions are unpaid; or

(b)where the economic operator was informed of the exact amount due following its breach of its obligations relating to the payment of taxes or social security contributions at such time that it did not have the possibility of fulfilling its obligations in a manner described in paragraph (5) before expiration of the deadline for requesting participation or, in open procedures, the deadline for submitting its tender.

Discretionary exclusions

(8) Contracting authorities may exclude from participation in a procurement procedure any economic operator in any of the following situations:—

(a)where the contracting authority can demonstrate by any appropriate means a violation of applicable obligations referred to in regulation 56(2);

(b)where the economic operator is bankrupt or is the subject of insolvency or winding-up proceedings, where its assets are being administered by a liquidator or by the court, where it is in an arrangement with creditors, where its business activities are suspended or it is in any analogous situation arising from a similar procedure under the laws and regulations of any State;

(c)where the contracting authority can demonstrate by appropriate means that the economic operator is guilty of grave professional misconduct, which renders its integrity questionable;

(d)where the contracting authority has sufficiently plausible indications to conclude that the economic operator has entered into agreements with other economic operators aimed at distorting competition;

(e)where a conflict of interest within the meaning of regulation 24 cannot be effectively remedied by other, less intrusive, measures;

(f)where a distortion of competition from the prior involvement of the economic operator in the preparation of the procurement procedure, as referred to in regulation 41, cannot be remedied by other, less intrusive, measures;

(g)where the economic operator has shown significant or persistent deficiencies in the performance of a substantive requirement under a prior public contract, a prior contract with a contracting entity, or a prior concession contract, which led to early termination of that prior contract, damages or other comparable sanctions;

(h)where the economic operator—

(i)has been guilty of serious misrepresentation in supplying the information required for the verification of the absence of grounds for exclusion or the fulfilment of the selection criteria; or

(ii)has withheld such information or is not able to submit supporting documents required under regulation 59; or

(i)where the economic operator has—

(i)undertaken to—

(aa)unduly influence the decision-making process of the contracting authority, or

(bb)obtain confidential information that may confer upon it undue advantages in the procurement procedure; or

(ii)negligently provided misleading information that may have a material influence on decisions concerning exclusion, selection or award.

Exclusion during procedure

(9) Contracting authorities shall exclude an economic operator where they become aware, at any time during a procurement procedure, that the economic operator is, in view of acts committed or omitted either before or during the procedure, in one of the situations referred to in paragraphs (1) to (3).

(10) Contracting authorities may exclude an economic operator where they become aware, at any time during a procurement procedure, that the economic operator is, in view of acts committed or omitted either before or during the procedure, in one of the situations referred to in paragraphs (4) or (8).

Duration of exclusion

(11) In the cases referred to in paragraphs (1) to (3), the period during which the economic operator shall (subject to paragraphs (6), (7) and (14)) be excluded is 5 years from the date of the conviction.

(12) In the cases referred to in paragraphs (4) and (8), the period during which the economic operator may (subject to paragraph (14)) be excluded is 3 years from the date of the relevant event.

Self-cleaning

(13) Any economic operator that is in one of the situations referred to in paragraph (1) or (8) may provide evidence to the effect that measures taken by the economic operator are sufficient to demonstrate its reliability despite the existence of a relevant ground for exclusion.

(14) If the contracting authority considers such evidence to be sufficient, the economic operator concerned shall not be excluded from the procurement procedure.

(15) For that purpose, the economic operator shall prove that it has—

(a)paid or undertaken to pay compensation in respect of any damage caused by the criminal offence or misconduct;

(b)clarified the facts and circumstances in a comprehensive manner by actively collaborating with the investigating authorities; and

(c)taken concrete technical, organisational and personnel measures that are appropriate to prevent further criminal offences or misconduct.

(16) The measures taken by the economic operator shall be evaluated taking into account the gravity and particular circumstances of the criminal offence or misconduct.

(17) Where the contracting authority considers such measures to be insufficient, the contracting authority shall give the economic operator a statement of the reasons for that decision.

Marginal Citations

M21977 c.45; section 1 was amended by the Criminal Attempts Act 1981 (c.47), section 5(1), by the Criminal Justice (Terrorism and Conspiracy) Act 1998 (c.40), Schedule 2, Part 2, and by the Trade Union and Labour Relations (Consolidation) Act 1992 (c.52), Schedule 1; section 1A was inserted by the Criminal Justice (Terrorism and Conspiracy) Act 1998, section 5(1), and was amended by the Coroners and Justice Act 2009 (c.25), section 72(1)(a).

M3S.I. 1983/1120 (N.I.13); article 9 was amended by Part 2 of Schedules 1 and 2 to the Criminal Justice (Terrorism and Conspiracy) Act 1998 (c.40), and article 9A was inserted by section 6(1) of that Act; there are other amendments but none is relevant.

M4OJ No L 300, 11.11.2008, p42.

M51889 c.69; this Act was repealed by the Bribery Act 2010 (c.23), Schedule 2.

M61906 c.34; this Act was repealed by the Bribery Act 2010 (c.23), Schedule 2.

M9OJ No C 316, 27.11.1995, p48.

M141985 c.6; section 458 was modified by S.I. 2001/1090 and repealed by the Companies Act 2006 (c.46), Schedule 16.

M15S.I. 1986/1032 (N.I.6), amended by S.R. (NI) 2004/307 (and other instruments that were not relevant) and revoked by the Companies Act 2006 (c.46), Schedule 16.

M162006 c.46; section 993 is applied (with modifications) by S.I. 2009/1804, regulation 47, and by S.I. 2009/2436, regulation 3 and Schedule 1.

M201968 c.60; section 20 was amended by the Fraud Act 2006 (c.35), Schedules 1 and 3.

M211969 c.16 (N.I.); section 19 was amended by the Fraud Act 2006 (c.35), Schedules 1 and 3.

M252002 c.29; sections 340(11) and 415 were modified by the Serious Crime Act 2007 (c.27), section 63(1) and Schedule 6, paragraph 44(a); section 415 was amended by the Serious Organised Crime and Police Act 2005 (c.15), section 107(4).

M261988 c.33; sections 93A, 93B and 93C were inserted by sections 29, 30 and 31 of the Criminal Justice Act 1993 (c.36) and repealed by the Proceeds of Crime Act 2002 (c.29), Schedule 11, paragraph 17(2).

M311994 c.37; sections 49, 50 and 51 were repealed by the Proceeds of Crime Act 2002 (c.29), Schedule 11, paragraphs 1 and 25(1) and (2)(a), and by Schedule 12.

Selection criteriaU.K.

General principles

58.—(1) — Selection criteria may relate to—

(a)suitability to pursue a professional activity;

(b)economic and financial standing;

(c)technical and professional ability.

(2) Contracting authorities may impose on economic operators as requirements for participation only the criteria referred to in paragraphs (5) to (18).

(3) Contracting authorities shall limit any requirements to those that are appropriate to ensure that a candidate or tenderer has the legal and financial capacities and the technical and professional abilities to perform the contract to be awarded.

(4) All requirements shall be related and proportionate to the subject-matter of the contract.

(5) With regard to suitability to pursue a professional activity, contracting authorities may require economic operators to be enrolled in one of the professional or trade registers kept in their member State of establishment, as described in Schedule 5, or to comply with any other request set out in that Schedule.

(6) In procurement procedures for services, in so far as economic operators have to possess a particular authorisation or to be members of a particular organisation in order to be able to perform in their country of origin the service concerned, contracting authorities may require them to prove that they hold such authorisation or membership.

Economic and financial standing

(7) With regard to economic and financial standing, contracting authorities may impose requirements ensuring that economic operators possess the necessary economic and financial capacity to perform the contract.

(8) In particular, contracting authorities may require that economic operators—

(a)have a certain minimum yearly turnover, including a certain minimum turnover in the area covered by the contract;

(b)provide information on their annual accounts showing the ratios, for example, between assets and liabilities; and

(c)have an appropriate level of professional risk indemnity insurance.

(9) The minimum yearly turnover that economic operators are required to have shall not exceed twice the estimated contract value, except in duly justified cases, such as by reference to special risks attached to the nature of the works, services or supplies, in which case the contracting authority shall indicate their main reasons in the procurement documents or in the report referred to in regulation 84(1).

(10) Ratios, for example that between assets and liabilities, may be taken into consideration where the contracting authority specifies the methods and criteria for such consideration in the procurement documents, but such methods and criteria shall be transparent, objective and non-discriminatory.

Application to lots, framework agreements and dynamic purchasing systems

(11) Where a contract is divided into lots this regulation shall apply in relation to each individual lot.

(12) But the contracting authority may set the minimum yearly turnover that economic operators are required to have by reference to groups of lots in the event that the successful tenderer is awarded several lots to be executed at the same time.

(13) Where contracts based on a framework agreement are to be awarded following a reopening of competition, the maximum yearly turnover requirement referred to in paragraph (9) shall be calculated on the basis of the expected maximum size of specific contracts that will be performed at the same time, or, where it is not known, on the basis of the estimated value of the framework agreement.

(14) In the case of a dynamic purchasing system, the maximum yearly turnover requirement referred to in paragraph (9) shall be calculated on the basis of the expected maximum size of specific contracts to be awarded under that system.

Technical and professional ability

(15) With regard to technical and professional ability, contracting authorities may impose requirements ensuring that economic operators possess the necessary human and technical resources and experience to perform the contract to an appropriate quality standard.

(16) Contracting authorities may require, in particular, that economic operators have a sufficient level of experience demonstrated by suitable references from contracts performed in the past.

(17) A contracting authority may assume that an economic operator does not possess the required professional abilities where the contracting authority has established that the economic operator has conflicting interests which may negatively affect the performance of the contract.

(18) In procurement procedures for supplies requiring siting or installation work, or for services or works, the professional ability of economic operators to provide the service or to execute the installation or the work may be evaluated with regard to their skills, efficiency, experience and reliability.

Indicating requirements for participation

(19) Contracting authorities shall indicate the requirements for participation, which may be expressed as minimum levels of ability, together with the appropriate means of proof, in the contract notice or in the invitation to confirm interest.

European Single Procurement DocumentU.K.

Use, content and form of the ESPD

59.—(1) At the time of submission of requests to participate or of tenders, contracting authorities shall accept the European Single Procurement Document, consisting of an updated self-declaration as preliminary evidence instead of certificates issued by public authorities or third parties confirming that the relevant economic operator fulfils the following conditions:—

(a)it is not in one of the situations referred to in regulation 57 in which economic operators shall or may be excluded;

(b)it meets the relevant selection criteria that have been set out under regulation 58;

(c)where applicable, it fulfils the objective rules and criteria that have been set out under regulation 65.

(2) Where the economic operator relies on the capacities of other entities under regulation 63, the ESPD shall also contain the information referred to in paragraph (1) in respect of such entities.

(3) The ESPD shall consist of a formal statement by the economic operator that the relevant ground for exclusion does not apply and, or alternatively, that the relevant selection criterion is fulfilled and shall provide the relevant information as required by the contracting authority.

(4) The ESPD shall further identify the public authority or third party responsible for establishing the supporting documents and contain a formal statement to the effect that the economic operator will be able, upon request and without delay, to provide those supporting documents.

(5) Where the contracting authority can obtain the supporting documents directly by accessing a database as mentioned in paragraph (11), the ESPD shall also contain the information required for this purpose, such as the internet address of the database, any identification data and, where applicable, the necessary declaration of consent.

(6) Economic operators may reuse an ESPD which has already been used in a previous procurement procedure, provided that they confirm that the information contained in it continues to be correct.

(7) The ESPD shall be provided exclusively in electronic form.

Supporting documentation

(8) A contracting authority may require candidates and tenderers at any moment during the procedure to submit all or any of the supporting documents where this is necessary to ensure the proper conduct of the procedure.

(9) Before awarding the contract, the contracting authority shall, except in respect of contracts based on framework agreements where such contracts are concluded in accordance with regulation 33(7) or (8)(a), require the tenderer to which it has decided to award the contract to submit up-to-date supporting documents in accordance with regulation 60 and, where appropriate, regulation 62.

(10) The contracting authority may invite economic operators to supplement or clarify the certificates received under regulations 60 and 62.

(11) Despite paragraphs (8) and (9), economic operators shall not be required to submit—

(a)supporting documents or other documentary evidence where and in so far as the contracting authority has the possibility of obtaining the certificates or the relevant information directly by accessing a national database in any member State that is available free of charge, such as a national procurement register, a virtual company dossier, an electronic document storage system or a prequalification system; or

(b)a supporting document which the contracting authority already possesses.

Means of proofU.K.

General principles

60.—(1) —Contracting authorities may require the certificates, statements and other means of proof referred to in this regulation as evidence for the absence of grounds for exclusion under regulation 57 and for the fulfilment of the selection criteria.

(2) Contracting authorities shall not require from economic operators means of proof other than those referred to in this regulation and in regulations 58(16) and 62.

(3) In respect of regulation 63, economic operators may rely on any appropriate means to prove to the contracting authority that they will have the necessary resources at their disposal.

Proving the absence of grounds for exclusion

(4) Contracting authorities shall accept the following as sufficient evidence that none of the cases specified in regulation 57 apply to the economic operator:—

(a)as regards regulation 57(1) and (2), the production of an extract from the relevant register, such as judicial records or, failing that, of an equivalent document issued by a competent judicial or administrative authority in the member State or country of origin or the country where the economic operator is established showing that those requirements have been met;

(b)as regards regulation 57(3) to (5) and (8)(b), a certificate issued by the competent authority in the member State or country concerned.

(5) Where the member State or country in question does not issue such documents or certificates, or to the extent that these do not cover all the cases specified in regulation 57(1) to (5) and (8)(b), they may be replaced by a declaration on oath or, in member States or countries where there is no provision for declarations on oath, by a solemn declaration made by the person concerned before a competent judicial or administrative authority, a notary or a competent professional or trade body, in the member State or country of origin or in the member State or country where the economic operator is established.

Proving economic and financial standing

(6) Proof of the economic operator's economic and financial standing may be provided by one or more of the following references:—

(a)appropriate statements from banks or, where appropriate, evidence of relevant professional risk indemnity insurance;

(b)the presentation of financial statements or extracts from the financial statements, where publication of financial statements is required under the law of the country in which the economic operator is established;

(c)a statement of the undertaking's overall turnover and, where appropriate, of turnover in the area covered by the contract for a maximum of the last 3 financial years available, depending on the date on which the undertaking was set up or the economic operator started trading, as far as the information on those turnovers is available.

(7) Where the references mentioned in paragraph (6) are not appropriate in a particular case, the contracting authority may require the economic operator to provide other information to prove its economic and financial standing.

(8) Where, for any valid reason, the economic operator is unable to provide the references or other information required by the contracting authority, it may prove its economic and financial standing by any other document which the contracting authority considers appropriate.

Proving technical and professional ability

(9) Proof of the economic operator's technical and professional ability may, subject to regulation 58(16), be provided by one or more of the following means, in accordance with the nature, quantity or importance, and the use, of the works, supplies or services:—

(a)the following lists:—

(i)a list of the works carried out over at the most the past 5 years, accompanied by certificates of satisfactory execution and outcome for the most important works; but, where necessary in order to ensure an adequate level of competition, contracting authorities may indicate that evidence of relevant works carried out more than 5 years before will be taken into account;

(ii)a list of the principal deliveries effected or the main services provided over at the most the past 3 years, with the sums, dates and recipients, whether public or private, involved; but, where necessary in order to ensure an adequate level of competition, contracting authorities may indicate that evidence of relevant supplies or services delivered or performed more than 3 years before will be taken into account;

(b)an indication of the technicians or technical bodies involved, whether or not belonging directly to the economic operator's undertaking, especially those responsible for quality control and, in the case of public works contracts, those upon whom the contractor can call in order to carry out the work;

(c)a description of the technical facilities and measures used by the economic operator for ensuring quality and the undertaking's study and research facilities;

(d)an indication of the supply chain management and tracking systems that the economic operator will be able to apply when performing the contract;

(e)where the products or services to be supplied are complex or, exceptionally, are required for a special purpose, a check carried out by the contracting authority, or on its behalf, by a competent official body of the country in which the supplier or service provider is established, subject to that body's agreement, on the production capacities of the supplier or the technical capacity of the service provider and, where necessary, on the means of study and research which are available to it and the quality control measures it will operate;

(f)the educational and professional qualifications of the service provider or contractor or those of the undertaking's managerial staff, provided that they are not to be evaluated as an award criterion;

(g)an indication of the environmental management measures that the economic operator will be able to apply when performing the contract;

(h)a statement of the average annual manpower of the service provider or contractor and the number of managerial staff for the last 3 years;

(i)a statement of the tools, plant or technical equipment available to the service provider or contractor for carrying out the contract;

(j)an indication of the proportion of the contract which the economic operator intends possibly to subcontract;

(k)with regard to the products to be supplied:—

(i)samples, descriptions or photographs, the authenticity of which must be certified where the contracting authority so requests;

(ii)certificates drawn up by official quality control institutes or agencies of recognised competence attesting the conformity of products clearly identified by references to technical specifications or standards.

Recourse to e-CertisU.K.

61.—(1) Contracting authorities shall have recourse to e-Certis and shall require primarily such types of certificates or forms of documentary evidence as are covered by e-Certis.

(2) In this regulation, “e-Certis” means the online repository established by the Commission and referred to as “e-Certis” in the Public Contracts Directive.

Quality assurance standards and environmental management standardsU.K.

62.—(1) —Contracting authorities shall, where they require the production of certificates drawn up by independent bodies attesting that the economic operator complies with certain quality assurance standards, including on accessibility for disabled persons, refer to quality assurance systems based on the relevant European standards series certified by accredited bodies.

(2) Contracting authorities shall recognise equivalent certificates from bodies established in other member States.

(3) Contracting authorities shall also accept other evidence of equivalent quality assurance measures where the economic operator concerned had no possibility of obtaining such certificates within the relevant time limits for reasons that are not attributable to that economic operator, provided that the economic operator proves that the proposed quality assurance measures comply with the required quality assurance standards.

(4) Where contracting authorities require the production of certificates drawn up by independent bodies attesting that the economic operator complies with certain environmental management systems or standards, they shall refer to—

(a)the Eco-Management and Audit Scheme of the EU,

(b)other environmental management systems as recognised in accordance with Article 45 of Regulation (EC) No 1221/2009 M32, or

(c)other environmental management standards based on the relevant European or international standards by accredited bodies,

and shall recognise equivalent certificates from bodies established in other member States.

(5) Where an economic operator had demonstrably no access to the certificates referred to in paragraph (4), or no possibility of obtaining them within the relevant time limits for reasons that are not attributable to that economic operator, the contracting authority shall accept other evidence of environmental management measures, provided that the economic operator proves that these measures are equivalent to those required under the applicable environmental management system or standard.

Marginal Citations

M32OJ No L 342, 22.12.2009, p1, amended by Council Regulation (EU) No 517/2013 (OJ No L 158, 10.6.2013, p1).

Reliance on the capacities of other entitiesU.K.

63.—(1) With regard to—

(a)criteria relating to economic and financial standing as set out under regulation 58(7) to (14), and

(b)criteria relating to technical and professional ability as set out under regulation 58(15) to (18),

an economic operator may, where appropriate and for a particular contract, rely on the capacities of other entities, regardless of the legal nature of the links which it has with them, subject to the following provisions of this regulation.

(2) With regard to criteria relating to the educational and professional qualifications mentioned in regulation 60(9)(f), or to relevant professional experience, economic operators may however only rely on the capacities of other entities where those entities will perform the works or services for which these capacities are required.

(3) Where an economic operator wants to rely on the capacities of other entities, it shall prove to the contracting authority that it will have at its disposal the resources necessary, for example by producing a commitment by those entities to that effect.

(4) The contracting authority shall, in accordance with regulations 59 to 61, verify whether the entities on whose capacity the economic operator intends to rely fulfil the relevant selection criteria and whether there are grounds for exclusion under regulation 57, and—

(a)the contracting authority shall require that the economic operator replaces an entity which does not meet a relevant selection criterion, or in respect of which there are compulsory grounds for exclusion; and

(b)the contracting authority may require that the economic operator substitutes an entity in respect of which there are non-compulsory grounds for exclusion.

(5) Where an economic operator relies on the capacities of other entities with regard to criteria relating to economic and financial standing, the contracting authority may require that the economic operator and those entities be jointly liable for the execution of the contract.

(6) A group of economic operators within the meaning of regulation 19(3) may rely on the capacities of participants in the group or of other entities, and paragraphs (1) to (5) apply in relation to such a group in the same way that they apply in relation to an economic operator.

(7) In the case of works contracts, service contracts and siting or installation operations in the context of a supply contract, contracting authorities may require that certain critical tasks be performed directly by the tenderer itself or, where the tender is submitted by a group of economic operators within the meaning of regulation 19(3), by a participant in that group.

Recognition of official lists of approved economic operators and certification by certification bodiesU.K.

64.—(1) Economic operators registered on an official list or having a certificate issued by a certification body may, for each contract, submit to the contracting authority a certificate of registration issued by the competent authority or the certificate issued by the certification body.

(2) A certificate of either kind shall constitute a presumption of suitability with regard to requirements for qualitative selection encompassed by the certificate or the official list to which it relates.

(3) Information that can be deduced from registration on official lists or certification by certification bodies shall not be questioned without justification.

(4) With regard to the payment of social security contributions and taxes, an additional certificate may be required of any registered economic operator whenever a contract is to be awarded.

(5) In relation to an official list established or maintained by a member State other than the United Kingdom, paragraphs (1) and (3) apply only in favour of economic operators established in the member State holding the official list.

(6) The requirements of proof for the criteria for qualitative selection encompassed by the official list or certificate shall comply with regulation 60 and, where appropriate, regulation 62.

(7) Economic operators shall not be obliged to be registered on an official list or to provide a certificate issued by a certification body in order to participate in a public contract.

(8) Contracting authorities shall—

(a)recognise equivalent certificates from bodies established in other member States, and

(b)accept other equivalent means of proof.

(9) In this regulation—

official list” means an official list of approved contractors, suppliers or service providers established or maintained by a member State under to Article 64 of the Public Contracts Directive; and

certification body” means a certification body complying with European standards of certification, and “certificate issued by a certification body” means a certificate issued by such a body in accordance with certification arrangements for which a member State has provided for the purposes of Article 64 of the Public Contracts Directive.

(10) For the purposes of this regulation, no official list or certification arrangements are established, maintained or provided for in relation to the jurisdictions to which this Part extends and, accordingly, in paragraph (9), “member State” includes the United Kingdom only insofar as the official list or the certification arrangements are established, maintained or provided for in respect of any other jurisdiction.

Reduction of the number of otherwise qualified candidates to be invited to participateU.K.

65.—(1) In restricted procedures, competitive procedures with negotiation, competitive dialogue procedures and innovation partnerships, contracting authorities may limit the number of candidates meeting the selection criteria that they will invite to tender or to conduct a dialogue, provided that the minimum number of qualified candidates is available, in accordance with the following paragraphs of this regulation.

(2) Contracting authorities shall indicate, in the contract notice or in the invitation to confirm interest, the objective and non-discriminatory criteria or rules they intend to apply, the minimum number of candidates they intend to invite and, where applicable the maximum number.

(3) In the restricted procedure, the minimum number of candidates shall be 5.

(4) In the competitive procedure with negotiation, the competitive dialogue procedure and the innovation partnership procedure, the minimum number of candidates shall be 3.

(5) In any event the number of candidates invited shall be sufficient to ensure genuine competition.

(6) Contracting authorities shall invite a number of candidates at least equal to the minimum number indicated in accordance with paragraph (2).

(7) But where the number of candidates meeting the selection criteria and the minimum levels of ability as referred to in regulation 58(19) is below that minimum number, the contracting authority may continue the procedure by inviting the candidates with the required capabilities.

(8) In the context of the same procedure, the contracting authority shall not include economic operators that did not request to participate, or candidates that do not have the required capabilities.

Reduction of the number of tenders and solutionsU.K.

66.—(1) Where contracting authorities exercise the option of reducing the number of tenders to be negotiated in accordance with regulation 29(19) and (20) or of solutions to be discussed in accordance with regulation 30(12) and (13), they shall do so by applying the award criteria stated in the procurement documents.

(2) In the final stage, the number arrived at shall make for genuine competition in so far as there are enough tenders, solutions or qualified candidates.

Contract award criteriaU.K.

67.—(1) Contracting authorities shall base the award of public contracts on the most economically advantageous tender assessed from the point of view of the contracting authority.

(2) That tender shall be identified on the basis of the price or cost, using a cost-effectiveness approach, such as life-cycle costing in accordance with regulation 68, and may include the best price-quality ratio, which shall be assessed on the basis of criteria, such as qualitative, environmental and/or social aspects, linked to the subject-matter of the public contract in question.

(3) Such criteria may comprise, for example—

(a)quality, including technical merit, aesthetic and functional characteristics, accessibility, design for all users, social, environmental and innovative characteristics and trading and its conditions;

(b)organisation, qualification and experience of staff assigned to performing the contract, where the quality of the staff assigned can have a significant impact on the level of performance of the contract; or

(c)after-sales service and technical assistance, delivery conditions such as delivery date, delivery process and delivery period or period of completion.

(4) The cost element may also take the form of a fixed price or cost on the basis of which economic operators will compete on quality criteria only.

(5) Award criteria shall be considered to be linked to the subject-matter of the public contract where they relate to the works, supplies or services to be provided under that contract in any respect and at any stage of their life cycle, including factors involved in—

(a)the specific process of production, provision or trading of those works, supplies or services, or

(b)a specific process for another stage of their life cycle,

even where those factors do not form part of their material substance.

(6) Award criteria shall not have the effect of conferring an unrestricted freedom of choice on the contracting authority.

(7) Award criteria shall—

(a)ensure the possibility of effective competition; and

(b)be accompanied by specifications that allow the information provided by the tenderers to be effectively verified in order to assess how well the tenders meet the award criteria.

(8) In case of doubt, contracting authorities shall verify effectively the accuracy of the information and proof provided by the tenderers.

Weighting

(9) The contracting authority shall specify, in the procurement documents, the relative weighting which it gives to each of the criteria chosen to determine the most economically advantageous tender, except where this is identified on the basis of price alone.

(10) Those weightings may be expressed by providing for a range with an appropriate maximum spread.

(11) Where weighting is not possible for objective reasons, the contracting authority shall indicate the criteria in decreasing order of importance.

Life-cycle costingU.K.

68.—(1) Life-cycle costing shall, to the extent relevant, cover part or all of the following costs over the life cycle of a product, service or works:—

(a)costs, borne by the contracting authority or other users, such as—

(i)costs relating to acquisition,

(ii)costs of use, such as consumption of energy and other resources,

(iii)maintenance costs,

(iv)end of life costs, such as collection and recycling costs;

(b)costs imputed to environmental externalities linked to the product, service or works during its life cycle, provided their monetary value can be determined and verified.

(2) The costs mentioned in paragraph (1)(b) may include the cost of emissions of greenhouse gases and of other pollutant emissions and other climate change mitigation costs.

(3) The method used for the assessment of costs imputed to environmental externalities shall fulfil all of the following conditions:—

(a)it is based on objectively verifiable and non-discriminatory criteria and, in particular, where it has not been established for repeated or continuous application, it shall not unduly favour or disadvantage certain economic operators;

(b)it is accessible to all interested parties;

(c)the data required can be provided with reasonable effort by normally diligent economic operators, including economic operators from third countries party to the GPA or other international agreements by which the EU is bound.

(4) Where contracting authorities assess costs using a life-cycle costing approach, they shall indicate in the procurement documents—

(a)the data to be provided by the tenderers, and

(b)the method which the contracting authority will use to determine the life-cycle costs on the basis of those data.

(5) Whenever a common method for the calculation of life-cycle costs has been made mandatory by a legislative act of the EU, that common method shall be applied for the assessment of life-cycle costs.

(6) A list of such legislative acts, and where necessary the delegated acts supplementing them, is set out in Annex XIII to the Public Contracts Directive as amended from time to time.

Abnormally low tendersU.K.

69.—(1) Contracting authorities shall require tenderers to explain the price or costs proposed in the tender where tenders appear to be abnormally low in relation to the works, supplies or services.

(2) The explanations given in accordance with paragraph (1) may in particular relate to—

(a)the economics of the manufacturing process, of the services provided or of the construction method;

(b)the technical solutions chosen or any exceptionally favourable conditions available to the tenderer for the supply of the products or services or for the execution of the work;

(c)the originality of the work, supplies or services proposed by the tenderer;

(d)compliance with applicable obligations referred to in regulation 56(2);

(e)compliance with obligations referred to in regulation 71;

(f)the possibility of the tenderer obtaining State aid.

(3) The contracting authority shall assess the information provided by consulting the tenderer.

(4) The contracting authority may only reject the tender where the evidence supplied does not satisfactorily account for the low level of price or costs proposed, taking into account the elements referred to in paragraph (2).

(5) The contracting authority shall reject the tender where it has established that the tender is abnormally low because it does not comply with applicable obligations referred to in regulation 56(2).

(6) Where the contracting authority establishes that a tender is abnormally low because the tenderer has obtained State aid, the tender may be rejected on that ground alone only—

(a)after consultation with the tenderer, and

(b)where the tenderer is unable to prove, within a sufficient time limit fixed by the contracting authority, that the aid in question was compatible with the internal market within the meaning of Article 107 of TFEU.

(7) Where the contracting authority rejects a tender in the circumstances referred to in paragraph (6), it shall inform the Commission.

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill