xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULE 1E+WAuthorised development, ancillary and necessary works and Requirements

PART 3E+WRequirements

Construction Environmental Management PlansE+W

5.—(1) No authorised development are to commence until a CEMP substantially in accordance with the outline Construction Environmental Management Plan, has been submitted to and approved by the relevant planning authorities in consultation with Natural Resources Wales.

(2) All construction work must be carried out in accordance with the CEMP approved under sub-paragraph (1).

(3) No operation of the authorised development is to commence until an OEMP, substantially in accordance with the outline Operational Environmental Management Plan, has been submitted to and approved by the relevant planning authorities.

(4) Operation of the authorised development must be in accordance with the approved OEMP.

(5) The CEMP and OEMP must include, but not be limited to, mechanisms for the provision and implementation of the following mitigation matters—

(a)lagoon wardens during the operational phase, whose responsibilities include (but are not limited to) securing the delivery of the OEMP and managing public access;

(b)a Reptile Strategy which provides for their habitat retention and management, and where necessary, their translocation to suitable receptor sites;

(c)access for otters, which is to be maintained at all times between the docks, River Tawe and the coastline;

(d)providing that reversing alarms which are not audible beyond the development site boundaries must be fitted on any Heavy Goods Vehicles (HGVs) and mobile plant that are active during the construction phase during hours of darkness, weekends (Saturdays and Sundays) and bank holidays.

Commencement Information

I1Sch. 1 para. 5 in force at 30.6.2015, see art. 1