SCHEDULE 8E+W

PART 1E+WFor the protection of Associated British Ports

Notice of worksE+W

5.  The undertaker must give to AB Ports not less than 56 days’ written notice of its intention to commence the construction of a specified work and, not more than 14 days after completion of such construction, must give to AB Ports written notice of such completion.

Commencement Information

I1Sch. 8 para. 5 in force at 30.6.2015, see art. 1