The Ferrybridge Multifuel 2 Power Station Order 2015

Travel plan – operational staff

33.—(1) The authorised development must not be brought into commercial use until a written travel plan for operational staff has been submitted to and, after consultation with the relevant highway authorities, approved by the planning authority.

(2) The plan submitted and approved must be in accordance with the principles set out in chapter 7 of the environmental statement and the operational travel plan framework contained in Appendix 7C to the environmental statement.

(3) The plan submitted and approved must include—

(a)details of the travel plan budget;

(b)measures to promote the use of sustainable transport modes to and from the authorised development by operational staff;

(c)provision as to the responsibility for, and timescales of, the implementation of those measures;

(d)a monitoring and review regime.

(4) The approved plan must be implemented within six months after the authorised development is brought into commercial use and must be maintained throughout the operation of the authorised development.