Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Articles 2(1) and 28

SCHEDULE 2E+WGREENHOUSE GAS CRITERIA FOR SOLID AND GASEOUS BIOMASS

This Atodlen has no associated Memorandwm Esboniadol

Articles 2(1), 28 and 82

PART 1E+WGreenhouse gas criteria

InterpretationE+W

1.  In this Schedule—

actual value method” means the calculation method provided for in Part 2;

default value method” means the calculation method provided for in Part 3;

post-2013 dedicated biomass station” means a generating station which—

(a)

was not accredited on or before 31st March 2013, and

(b)

has, in any month after March 2013, generated electricity in the way described as “dedicated biomass” [F1(including “dedicated biomass with CHP”)] in Schedule 5;

relevant biomass” means biomass other than animal excreta, bioliquid, landfill gas, sewage gas or waste;

relevant ceiling” means—

(a)

in relation to biomass used by a post-2013 dedicated biomass station to generate electricity before 1st April 2020, 79.2 grams per megajoule of electricity,

(b)

in relation to biomass used to generate electricity on or after 1st April 2020 and before 1st April 2025, 75 grams per megajoule of electricity,

(c)

in relation to biomass used to generate electricity on or after 1st April 2025, 72.2 grams per megajoule of electricity;

relevant target” means—

(a)

in relation to biomass used to generate electricity before 1st April 2020 by a station other than a post-2013 dedicated biomass station, 79.2 grams per megajoule of electricity,

(b)

in relation to biomass used by a post-2013 dedicated biomass station to generate electricity before 1st April 2020, 66.7 grams per megajoule of electricity,

(c)

in relation to biomass used to generate electricity on or after 1st April 2020 and before 1st April 2025, 55.6 grams per megajoule of electricity,

(d)

in relation to biomass used to generate electricity on or after 1st April 2025, 50 grams per megajoule of electricity.

The greenhouse gas criteriaE+W

2.  Biomass meets the greenhouse gas criteria—

(a)if the greenhouse gas emissions from its use are equal to, or less than, the relevant target, or

(b)if—

(i)the biomass is used by a post-2013 dedicated biomass station or the biomass is used to generate electricity after 1st April 2020,

(ii)the greenhouse gas emissions from its use are equal to, or less than, the relevant ceiling, and

(iii)the biomass is used in an obligation period in which the average greenhouse gas emissions from the relevant biomass used by the station to generate electricity during that obligation period are equal to, or less than, the relevant target.

Calculating the greenhouse gas emissionsE+W

3.  For the purposes of paragraph 2, and subject to paragraph 4, the greenhouse gas emissions from the use of biomass to generate electricity—

(a)is to be calculated by the operator of the generating station using the actual value method or the default value method, or

(b)is 91 grams per megajoule of electricity.

4.  The default value method must not be used to calculate the greenhouse gas emissions from the use of biomass unless—E+W

(a)the biomass was used in a generating station with a total installed capacity of less than 1 megawatt,

(b)the biomass is described in the first column of the table in Part 4, and

(c)in relation to the biomass, the result of the calculation in paragraph 7 of Part C of Annex 5 to the Renewables Directive is equal to, or less than, zero.

5.  For the purposes of paragraph 4(c), paragraph 7 of Part C of Annex 5 to the Renewables Directive is to be read as if—E+W

(a)for each reference to “biofuel” there was substituted “ biomass ”; and

(b)the words “or bioliquid” were omitted in each place in which those words occur.

PART 2E+WActual value method

6.  Where the greenhouse gas emissions from the use of biomass are calculated using the actual value method the greenhouse gas emissions from the use of the biomass are equal to—E+W

(a)in the case of biomass used by a CHP station,

(b)in any other case,

7.  In paragraph 6—E+W

(i)A is the total amount of electricity generated by the generating station during the month, and

(ii)F is the energy content of all of the fuels used in generating that electricity during the month;

(i)F has the same meaning as in sub-paragraph (a)(ii), and

(ii)H is the energy content of all of the heat supplied to any premises by the generating station during the month;

(i)where the maximum temperature in degrees kelvin of heat or steam which is (or may be) supplied by the generating station to any premises (“

(ii)in any other case,

(d)E is the greenhouse gas emissions from the production of the biomass and is to be calculated in accordance with Part C of Annex 5 of the Renewables Directive but as if the following modifications were made to Part C of that Annex—

(i)in paragraph 1—

(aa)for “and use of transport fuels, biofuels and bioliquids” there was substituted “ of biomass ”,

(bb)for “E = total emissions from the use of the fuel” there was substituted “ E = greenhouse gas emissions from the production of the biomass ”, and

(cc)for “

(ii)in paragraph 2, for the references to “fuels” and “fuel” there was substituted in each case “ biomass ”;

(iii)paragraphs 3 and 4 were omitted;

(iv)in paragraph 7—

(aa)for each reference to “biofuel” there was substituted “ biomass ”, and

(bb)the words “or bioliquid” were omitted in each place in which those words occur;

(v)in paragraph 11, for “fuel” there was substituted “ biomass ”;

(vi)paragraph 13 was omitted;

(vii)in paragraph 14, for “fuel” there was substituted “ biomass ”;

(viii)for paragraph 16 there was substituted—

16.  Emission saving from excess electricity from cogeneration shall be taken to be zero. ;

(ix)in paragraph 17, for each reference to “fuel” there was substituted “ biomass ”;

(x)in paragraph 18—

(aa)for “fuel” there was substituted “ biomass ”,

(bb)the words “In case of biofuels and bioliquids,” were omitted,

(cc)before “and residues from processing” there was inserted “residues from aquaculture, arboriculture, fisheries and forestry”, and

(dd)for “fuels” there was substituted “ biomass ”; and

(xi)for paragraph 19 there was substituted—

19.  Where material is added to the biomass to act as a binding agent or to reduce the emissions of dust, carbon dioxide, methane or nitrous oxide from the use of the biomass, the material so added shall be considered to have zero greenhouse gas emissions, provided that the material so added does not exceed 2% by weight of the biomass..

PART 3E+WDefault value method

8.  The greenhouse gas emissions from the use of biomass are calculated using the default value method where the greenhouse gas emissions from the use of the biomass are equal to—E+W

(a)in the case of biomass used by a CHP station,

(b)in any other case,

9.  In paragraph 8—E+W

(b)E, in relation to a type of biomass described in the first column of the table in Part 4, is the number of grams which corresponds to that description in the second column of that table.

PART 4E+WDefault greenhouse gas emissions from the production of biomass

BiomassDefault greenhouse gas emissions from the production of biomass (in grams)
Wood chips made from residue from forestry carried out in European temperate continental forest1
Wood chips made from residue from forestry carried out in tropical or subtropical forest25
Wood chips from short rotation forestry carried out in European temperate continental forest4
Wood chips from short rotation forestry carried out in tropical or subtropical forest28

Wood briquettes or wood pellets—

(a) which are made from residue from forestry carried out in European temperate continental forest, and

(b) where the process to produce the wood briquettes or wood pellets was fuelled by wood

2

Wood briquettes or wood pellets—

(a) which are made from residue from forestry carried out in tropical or subtropical forest, and

(b) where the process to produce the wood briquettes or wood pellets was fuelled by natural gas

20

Wood briquettes or wood pellets—

(a) which are made from residue from forestry carried out in tropical or subtropical forest, and

(b) where the process to produce the wood briquettes or wood pellets was fuelled by wood

17

Wood briquettes or wood pellets—

(a) which are made from residue from forestry carried out in European temperate continental forest, and

(b) where the process to produce the wood briquettes or wood pellets was fuelled by natural gas

35

Wood briquettes or wood pellets—

(a) which are made from short rotation forestry carried out in European temperate continental forest, and

(b) where the process to produce the wood briquettes or wood pellets was fuelled by wood

4

Wood briquettes or wood pellets—

(a) which are made from short rotation forestry carried out in European temperate continental forest, and

(b) where the process to produce the wood briquettes or wood pellets was fuelled by natural gas

22

Wood briquettes or wood pellets—

(a) which are made from short rotation forestry carried out in tropical or subtropical forest, and

(b) where the process to produce the wood briquettes or wood pellets was fuelled by wood

22

Wood briquettes or wood pellets—

(a) which are made from short rotation forestry carried out in tropical or subtropical forest, and

(b) where the process to produce the wood briquettes or wood pellets was fuelled by natural gas

40
Charcoal made from residue from forestry carried out in European temperate continental forest41
Charcoal made from residue from forestry carried out in tropical or subtropical forest50
Charcoal made from short rotation forestry carried out in European temperate continental forest46
Charcoal made from short rotation forestry carried out in tropical or subtropical forest57
Wheat straw2
Bagasse briquettes where the process to produce the bagasse briquettes was fuelled by wood17
Bagasse briquettes where the process to produce the bagasse briquettes was fuelled by natural gas35
Bagasse bales20
Palm kernel27
Rice husk briquettes28
Miscanthus bales7
Biogas produced from wet manure8
Biogas produced from dry manure7
Biogas produced from wheat, where the whole plant was used to produce the biogas21
Biogas produced from straw21

Biogas produced from maize, where—

(a) the whole maize plant was used in the process to produce the biogas, and

(b) the maize was not grown by organic farming methods

34

Biogas produced from maize, where—

(a) the whole maize plant was used in the process to produce the biogas, and

(b) the maize was grown by organic farming methods

19

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Asesiadau Effaith

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill