Chwilio Deddfwriaeth

The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015

 Help about what version

Pa Fersiwn

  • Y Diweddaraf sydd Ar Gael (Diwygiedig)
  • Gwreiddiol (a wnaed Fel)
 Help about opening options

Dewisiadau AgorExpand opening options

Status:

Dyma’r fersiwn wreiddiol (fel y’i gwnaed yn wreiddiol). Dim ond ar ei ffurf wreiddiol y mae’r eitem hon o ddeddfwriaeth ar gael ar hyn o bryd.

Pre-construction plans and documentation

10.—(1) Each programme, statement, plan, protocol, scheme or details required to be approved under Condition 9, and the arrangements required to be approved under Condition 5, must be submitted for approval at least 4 months before the intended commencement of construction, except where otherwise stated or unless otherwise agreed in writing by the MMO.

(2) The licensed activities must be carried out in accordance with the programme, statement, plan, protocol, scheme or details approved under Condition 9.

Yn ôl i’r brig

Options/Cymorth