Chwilio Deddfwriaeth

The Offshore Installations (Offshore Safety Directive) (Safety Case etc.) Regulations 2015

Status:

Dyma’r fersiwn wreiddiol (fel y’i gwnaed yn wreiddiol).

Design notification and safety case for non-production installation to be converted

This adran has no associated Memorandwm Esboniadol

19.—(1) Where a non-production installation is to be converted to enable it to be operated as a production installation, the owner must—

(a)prepare a design notification in respect of the proposed conversion containing, subject to paragraph (5), the particulars specified in Schedule 5 not contained in any current safety case for that installation; and

(b)send the design notification to the competent authority.

(2) The duties in paragraph (1) must be completed at such time before completion of the design of the proposed conversion as will enable the owner to take account—

(a)in the design, and

(b)in the safety case prepared pursuant to regulation 17,

of any matters raised by the competent authority within three months (or such shorter period as the competent authority may specify) of that time.

(3) The competent authority must respond to the design notification—

(a)with comments to be taken into account by the operator in the safety case; or

(b)where it has no such comments to make, with a statement to that effect.

(4) For the purposes of this regulation the particulars specified in Schedule 5 have effect as if any reference to the operator were a reference to the owner of the non-production installation to be converted.

(5) Paragraph (1) only requires the design notification to contain the particulars referred to in that paragraph to the extent that it is reasonable to expect the duty holder to address them at the time of sending the design notification to the competent authority.

(6) Where there is a material change in any of the particulars notified pursuant to paragraph (1) prior to the operator sending—

(a)a safety case to the competent authority in accordance with regulation 17(1); or

(b)revisions to the current safety case to the competent authority in accordance with paragraph (7),

the operator must notify the competent authority of that change as soon as practicable.

(7) Where a non-production installation operated pursuant to a current safety case is converted to a production installation, the operator of that production installation must ensure that it is not operated as a production installation in external waters unless—

(a)the operator has prepared revisions to the current safety case for that installation containing the particulars specified in regulation 16 and Schedule 6 not contained in that current safety case;

(b)the operator has sent a version of the current safety case which incorporates the proposed revisions, showing clearly where they are to be made, to the competent authority at least three months (or such shorter period as the competent authority may specify) before commencing the operation; and

(c)the competent authority has accepted those revisions to the current safety case.

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Asesiadau Effaith

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill