Article 2
Work No. 1 — A railway comprising an elevated chord, 1,183 metres in length, commencing at a point on the Bolton Lines railway (on the existing Castlefield Manchester, South Junction & Altrincham Railway viaduct (“Castlefield MSJ&AR viaduct”)) 21 metres north-west of the bridge carrying that railway over Potato Wharf, passing north-west over Water Street, the 1830 Viaduct, Prince’s Bridge (to be removed), the River Irwell and over the Trinity Way, tying into the east side of the existing Middlewood Liverpool & Manchester Railway viaduct (“Middlewood L&MR viaduct”) carrying the Chat Moss Lines and terminating at a point on that railway 20 metres north-east of Bury Street.
Work No. 1 includes—
a viaduct including a bridge over the River Irwell, a bridge over Water Street replacing the existing single span Cast Iron bridge and a new deck on the Middlewood L&MR viaduct at DSE 146(19A) and partial demolition of the viaduct where the new chord ties in;
widening of the Castlefield MSJ&AR viaduct on its north-eastern side;
strengthening and overstraddling of the existing 1830 Viaduct;
widening of the Middlewood L&MR viaduct on its eastern side; and
placing of piers of the proposed viaduct and safety barriers in Trinity Way and the placing of bridge abutments in Water Street.
Work No. 2 — A railway 300 metres in length, being a realignment of the Bolton Lines railway commencing at a point on that railway 20 metres south-east of Potato Wharf passing north-westwards and terminating at a point 21 metres south-east of Trinity Way.
Work No. 2 includes the widening of the Castlefield MSJ&AR viaduct on its south-west side and a bridge over Water Street replacing the existing single span Cast Iron bridge.
Work No. 3 — A railway 914 metres in length being a realignment of the Chat Moss Lines railway commencing on that railway at a point north of Trinity Way passing north-eastwards and terminating 43 metres south-west of Bury Street.
Work No. 3 includes the widening of the existing Middlewood L&MR viaduct on its north-western side and a new deck over the existing arch at DSE 146(19A).
Work No. 4 — A bridge to carry a footpath and cycle track over the River Irwell (being a replacement for Prince’s Bridge) commencing at a point on Water Street and terminating at a point on Trinity Way.
Work No. 5 — A bridge to carry utility apparatus together with a footpath and cycle track over the River Irwell commencing at a point 39 metres north-west of Water Street and terminating at a point on Trinity Way.
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys