SCHEDULE 25Flood risk activities and excluded flood risk activities

PART 2Excluded flood risk activities

SECTION 2Descriptions and conditions

Site investigation boreholes and trial pits

13.—(1) Site investigation boreholes and trial pits within a flood plain.

(2) For the purposes of this paragraph, the specific conditions are—

(a)the works are more than 5 metres from any culvert, remote defence or flood defence structure on the main river and from any sea defence,

(b)the works are more than 8 metres from the banks of a non-tidal main river,

(c)the works are more than 16 metres from the banks of a tidal main river, and

(d)the works are completed, including refilling of the borehole or pit, within 48 hours.