- Y Diweddaraf sydd Ar Gael (Diwygiedig)
- Pwynt Penodol mewn Amser (01/01/2017)
- Gwreiddiol (a wnaed Fel)
Version Superseded: 07/01/2019
Point in time view as at 01/01/2017.
There are currently no known outstanding effects for the The Environmental Permitting (England and Wales) Regulations 2016, Cross Heading: SECTION 2.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
2.—(1) Any activity carried on in an emergency.
(2) For the purposes of this paragraph, the specific conditions are that—
(a)the activity is not a pre-planned emergency activity, and
(b)the person carrying on the activity provides the regulator with notice in writing as soon as practicable of the carrying on of the activity and the circumstances in which it was carried on.
(3) For the purposes of sub-paragraph (2)(a), a “pre-planned emergency activity” means any activity which has been planned in response to an emergency before it occurs.
(4) The power of the regulator to serve a remediation notice under paragraph 8 of Part 1 of this Schedule applies where an activity has been carried on in reliance on this exclusion as if that activity were an unauthorised activity.
3.—(1) A licensable marine activity in England.
(2) For the purposes of this paragraph, the specific conditions are that—
(a)an application for a marine licence has been made in respect of that activity,
(b)the Agency has received notice that the application has been made,
(c)in view of the terms and conditions that will be included in the marine licence, the Agency considers that an environmental permit is not necessary, and
(d)a notice to that effect has been issued by the Agency to the applicant.
4.—(1) A licensable marine activity in Wales.
(2) For the purposes of this paragraph, the specific condition is that an application for a marine licence has been made in respect of that activity.
5.—(1) The erection and use of ladders and scaffold towers (“equipment”).
(2) For the purposes of this paragraph, the specific conditions are—
(a)the suitability of river conditions is reviewed by the operator each working day,
(b)the equipment is erected on each working day on which it is required, and
(c)the equipment is removed at the end of each working day and is stored outside the river and its banks.
6.—(1) The construction and use of service crossings within an existing structure.
(2) For the purposes of this paragraph, the specific conditions are—
(a)the crossing is entirely within the original profile of the existing structure,
(b)the regulator has not sent a notification to the landowner that the structure has been identified for removal or modification in order to achieve the measures set out in the relevant River Basin Management Plan, within the meaning of Article 13 of the Water Framework Directive, that are designed to move a water body to good status pursuant to Article 4 of that Directive,
(c)equipment associated with the works is not stored on the bed or banks of the main river, and
(d)no works are carried out from the main river or from the banks of the main river.
7.—(1) The attachment of a flood protection device directly to a building in order to protect the interior of that building.
(2) For the purposes of this paragraph, the specific condition is that the flood protection provided by the device extends only to the building to which the device is fitted.
8.—(1) The carrying out of minor works on or affecting bridges and culverts for highways and public rights of way (“minor works”).
(2) For the purposes of this paragraph, the specific conditions are—
(a)the minor works do not affect, or have the potential to affect, the bed, banks, water level, normal flow or flood flow in the main river,
(b)equipment associated with the minor works is not stored on the bed or banks of the main river, and
(c)no works are carried out from the main river or from the banks of the main river.
9.—(1) The erection of fencing.
(2) For the purposes of this paragraph, the specific conditions are—
(a)the fencing is not located on the bed or banks of the main river, and
(b)the fencing is constructed of—
(i)post and rail,
(ii)post and wire mesh of at least 100 mm spacing, or
(iii)post and wire strands.
10.—(1) The temporary use of fish traps.
(2) For the purposes of this paragraph, the specific conditions are—
(a)the trap has dimensions of no greater than 2 metres x 1 metre x 0.75 metre,
(b)any trap, or combination of traps, placed in the main river is less than one third of the width of the channel,
(c)the trap is not used when the main river is in a condition of high flow, and
(d)the trap is located more than 50 metres upstream or downstream from any dam or other obstruction.
11.—(1) Erection of notice boards.
(2) For the purposes of this paragraph, the specific conditions are—
(a)the board is attached to existing fencing or freestanding, permanent posts,
(b)the board is more than 2 metres from any culvert, remote defence or flood defence structure on the main river and from any sea defence, and
(c)the board is more than 2 metres from the landward side of the bank.
12.—(1) Clearance of purpose-built sediment traps.
(2) For the purposes of this paragraph, the specific conditions are—
(a)only sand and silt is cleared from the trap,
(b)the works do not result in sand or silt being transmitted downstream, and
(c)where the sand and silt from the clearance is spread on the floodplain, it is spread to a depth of no more than 100mm and no closer than 8 metres from the landward side of either bank.
13.—(1) Site investigation boreholes and trial pits within a flood plain.
(2) For the purposes of this paragraph, the specific conditions are—
(a)the works are more than 5 metres from any culvert, remote defence or flood defence structure on the main river and from any sea defence,
(b)the works are more than 8 metres from the banks of a non-tidal main river,
(c)the works are more than 16 metres from the banks of a tidal main river, and
(d)the works are completed, including refilling of the borehole or pit, within 48 hours.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys