- Y Diweddaraf sydd Ar Gael (Diwygiedig)
- Gwreiddiol (a wnaed Fel)
Dyma’r fersiwn wreiddiol (fel y’i gwnaed yn wreiddiol).
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
1, 3, 4, 6, 7, 8, 9, 14, 15, 19, 29, 34, 35, 36, 41, 50, 56, 60, 61, 63, 64, 65, 70, 71, 74, 81, 82, 88, 91 & 94 | Dismantling of redundant infrastructure | Work No. 4B | |
2, 5, 10, 16, 23, 28, 33, 40, 47, 53, 54, 62, 75, 78, 83, 84, 89, 90 & 93 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
11, 12, 13, 17, 18, 20, 21, 22, 24, 25, 26, 27, 30, 31, 32, 37, 38, 39, 42, 43, 44, 45, 46, 48, 49, 51, 52, 55, 57, 58, 59, 66, 67, 68, 69, 72, 73, 76, 77, 79, 80, 85, 86, 87, 92, 97, 98, 101, 157 & 158 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B |
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
4, 8, 9, 14, 36, 38, 39, 78, 84, 120, 125, 126, 127, 131, 132, 133, 134, 142, 153, 159, 160, 167, 171, 172, 174, 177.2, 178, 186, 187, 190, 193, 194, 251, 252, 253, 254, 273, 274, 278, 279, 281, 286, 371, 378, 380, 383, 385, 392, 394, 399, 400, 401, 402, 403, 404, 407, 411, 412, 417, 420, 421, 422, 423, 425, 434, 455, 462, 463, 465, 470, 471, 472, 476, 481, 485, 491, 494, 495, 498, 499, 500, 513, 514, 528, 530, 531, 532, 533, 534, 538, 540, 542, 543, 546, 547, 548, 551, 560, 572, 579, 587, 588, 589, 602, 603.2, 603.3, 604.2, 615, 619, 625, 626, 630, 631, 660, 666, 677 & 678 | Dismantling of redundant infrastructure | Work No. 4B | |
5, 12, 15, 37, 76, 81, 86, 119, 135, 140, 151, 170, 177.1, 179, 185, 188, 191, 266, 269, 271, 272, 277, 280, 285, 288, 370, 386, 393, 397, 406, 408, 413, 419, 424, 426, 454, 461, 477, 482, 492, 501, 510, 527, 535, 537, 545, 558, 568, 578, 591, 603.1, 604.1, 611, 612, 620, 627, 641, 654, 659 & 676 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
10, 11, 13, 16, 17, 18, 19, 20, 22, 23, 24, 34, 40, 42, 45, 46, 73, 79, 80, 82, 83, 115, 118, 121, 122, 129, 130, 138, 139, 154, 156, 165, 166, 168, 169, 173, 175, 176, 180, 181, 182, 183, 184, 189, 192, 255, 256, 257, 258, 259, 260, 261, 262, 263, 264, 265, 267, 268, 270, 275, 276, 282, 283, 284, 287, 359, 368, 373, 381, 384, 388, 391, 395, 396, 398, 405, 409, 410, 414, 415, 416, 418, 427, 428, 429, 433, 435, 437, 439, 450, 459, 460, 464, 466, 469, 478, 479, 480, 483, 484, 486, 488, 489, 490, 496, 502, 503, 504, 506, 507, 508, 509, 511, 512, 515, 516, 518, 520, 525, 526, 536.1, 536.2, 539, 541, 544, 549, 550, 556, 559, 562, 569, 581, 582, 584, 586, 593, 595, 596, 597, 599, 609.1, 609.2, 609.3, 609.4, 614, 616, 617, 618, 621, 622, 623, 624, 632, 633, 634, 640, 642, 643, 644, 649, 650, 652, 653, 665, 675, 679, 681 & 682 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B |
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
664 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B |
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
1 & 2 | Dismantling of redundant infrastructure | Work No. 4B | |
6, 13, 15 & 19 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
14 & 18 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
25 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
29 & 30 | Dismantling of redundant infrastructure | Work No. 4B |
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
33, 34, 37, 42, 43, 44, 47, 53, 56, 61, 64, 65, 66, 67, 71, 76, 77, 78, 91, 96, 99, 106, 107, 114, 115, 117, 119, 122, 123, 125, 128, 129, 132, 134, 139, 145, 146, 154, 160, 161, 162, 167, 168, 171, 172, 176, 181, 182, 183, 184, 185, 186, 196, 202.1, 202.2, 204, 208, 210, 211, 219, 220, 221, 225, 233, 234, 249, 255, 256, 257, 267, 268, 273, 274, 277, 280 & 281 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
41, 51, 58, 59, 62, 83, 84, 85, 86, 88, 89, 93, 94, 98, 108, 111, 136, 137, 152, 153, 156, 157, 166, 180, 187, 188, 189, 190, 191, 207, 212, 213, 214, 215, 216, 227, 228, 231, 252, 253, 271, 276, 282, 283, 284 & 285 | Dismantling of redundant infrastructure | Work No. 4B | |
50, 68, 112, 116, 147, 158, 159, 169, 205, 206, 209, 217, 240, 242, 244, 247, 248, 251 & 272 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
3, 15 & 57 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4B and 4C | |
4 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4A and 4B | |
7, 8, 9, 11, 12, 13, 17, 52, 53, 54, 55, 56, 61, 66, 68, 75, 88, 89, 112.1, 112.2, 112.3, 115, 117, 118, 188, 189, 190, 196, 197, 203, 204, 205, 210, 211, 213, 229, 231, 237.1, 237.2, 240, 243, 248, 249, 251, 253, 254, 255, 278, 279, 283, 284, 285, 286, 289, 290, 296, 304, 306, 318.1, 318.2, 319, 321, 329, 341, 348, 349, 351, 352, 367, 372, 394, 416, 419, 422, 424, 434, 452, 453, 467, 484, 485, 492, 504, 506, 514, 517, 529, 544.1, 544.2, 548, 557, 558, 559, 560, 561, 566, 567, 571, 572, 574, 575, 591, 592, 593, 594, 595, 602, 604, 605, 611, 612, 613, 615, 616, 620, 621, 623, 672, 674, 675, 677, 678, 775, 776, 828, 900, 901, 902, 904, 961, 962, 963, 964, 965, 966, 967, 968, 969 & 970 | Dismantling of redundant infrastructure | Work No. 4B | |
10, 62, 76, 106, 187, 194, 198, 199, 212, 232, 236, 247, 252, 288, 297, 308, 339, 345, 361, 371, 391, 413, 430, 438, 455, 464, 494, 511, 521, 522, 530, 545, 573, 596, 606, 617, 622, 673, 827, 832 & 903 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
18 & 20 | Construction of authorised development | Works Nos. 4B and 4C | |
19 | Construction of authorised development | Works Nos. 4B and 4C | Removal of pylon foundations only to a depth of 1 metre |
21, 23, 24, 27, 28, 29, 31, 33, 34, 35, 40, 41, 42, 43, 44, 45, 46 & 48 | Construction of authorised development | Work No. 4C | |
22, 30, 38 & 39 | Dismantling of redundant infrastructure | Work No. 4C | |
25 & 47 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4C | |
26 & 32 | Construction of authorised development | Work No. 4C | Removal of pylon foundations only to a depth of 1 metre |
63, 67, 69, 74.1, 74.2, 77, 83, 86, 87, 102, 200, 208, 217, 218, 219, 220.1, 220.2, 221, 223, 224, 225, 226, 227, 228, 233, 234, 235, 241, 242, 244, 245, 246, 250, 257, 258, 262, 263, 264, 265, 267, 268, 269, 270.1, 270.2, 271, 272, 274, 277, 280, 282, 287, 291, 292, 293, 294, 295, 299.1, 299.2, 301.1, 301.2, 302, 303, 305.1, 305.2, 307, 311, 315.1, 315.2, 316, 317, 320, 322, 323, 324, 325, 332.1, 332.2, 333, 336, 337, 338, 340, 343, 344, 346, 350, 354, 355, 356, 357.1, 357.2, 358, 359, 362, 363, 364, 365, 366, 369, 370, 373, 376, 377, 378, 383, 384, 385, 386, 387, 388, 390, 392, 393, 395, 396, 397, 398, 399, 400, 402, 407, 408.1, 408.2, 409, 410, 411, 414, 417, 418, 420, 425, 427, 428, 429, 431, 432, 436, 437, 439, 440, 441, 442, 445, 446, 447, 448, 449, 450, 451, 454, 456, 457, 458, 459, 460, 461, 462, 466, 468.1, 468.2, 469, 472, 473, 474, 477, 478, 479, 481, 482, 483, 486, 490, 491, 500, 502, 503, 505, 507, 510, 512, 513, 515, 516, 518, 523, 531, 532, 546, 547, 550, 555, 556, 562, 564, 568, 569, 570, 576, 585, 587, 588, 589, 590, 597, 598, 599, 600, 601, 603, 607, 608, 609, 618, 619, 676, 680, 685, 686, 687 & 826 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
65 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4A, 4B and 4C | |
104, 105.1, 105.2, 105.3, 110, 111.1, 111.2, 120, 121, 122, 123, 126, 127, 129, 130, 133, 153, 156, 159, 160, 161, 162, 165, 169, 172, 175, 176 & 177 | Construction of authorised development | Work No. 4A | |
131, 140, 141, 148, 163, 166, 167, 170, 181, 182 & 184 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4A | |
173, 178, 179, 180, 185, 186, 192 & 193 | Dismantling of redundant infrastructure | Work No. 4A | |
183 | Dismantling of redundant infrastructure | Work No. 4A | Removal of pylon foundations only to a depth of 1 metre |
256, 266, 273, 275, 276, 326, 327, 328, 330, 331, 470.1, 470.2, 471.1, 471.2, 475, 476, 480, 488, 489, 493, 495, 549, 551, 552, 563 & 565 | Construction of authorised development | Work No. 4B | |
624, 702, 703, 704, 707, 759, 760, 762, 772, 782.1, 782.2, 783, 784, 785, 816, 817, 833, 976.1 & 976.2 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4B and 4D | |
625, 628, 629, 630, 636, 660.1, 660.2, 660.3, 660.4, 660.5, 661, 662, 663.1, 663.2, 664, 665, 666, 667, 668, 669, 768, 786, 787, 788, 789, 790, 791, 792, 793, 794, 795, 796, 797, 798, 799, 800, 801, 802, 803, 804, 805, 806, 807, 808, 809, 810, 811, 812, 813, 814, 836, 837, 838, 839, 840, 841, 842, 843, 844, 845, 846, 847, 848, 849, 850, 851, 852, 853, 854, 855, 856, 857, 858, 859, 860, 861, 862, 863, 864, 865, 866, 867, 868, 869, 870, 871, 872, 874, 875, 876, 877, 878, 879, 880, 881, 882, 884, 885, 886, 906, 908, 909, 910, 911, 912, 913, 914, 915, 916, 917, 918, 919, 920, 921, 922, 923, 924, 925, 926, 927, 928, 929, 930, 931, 932, 933, 934, 935, 936, 937, 938, 939, 943, 944, 949, 950, 951, 952, 953, 954, 955, 956, 957, 958 & 959 | Dismantling of redundant infrastructure | Work No. 4D | |
626.1, 626.2, 627, 634, 635, 637, 643, 648, 649, 658, 659, 723, 729, 731, 737, 739, 740, 741, 742, 743, 744, 745, 748, 750, 752, 753, 754, 818, 829, 831, 834, 887, 888, 889, 945, 946, 948, 978, 979 & 980 | Construction of authorised development | Work No. 4D | |
631, 633, 670, 769, 835, 873 & 907 | Dismantling of redundant infrastructure | Work No. 4D | Removal of pylon foundations only to a depth of 1 metre |
632, 639, 640, 641, 642, 650, 651, 671, 905 & 960 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4D | |
758 | Construction of authorised development | Works Nos. 4B and 4D | |
764, 765, 770, 777, 780 & 781.2 | Dismantling of redundant infrastructure | Works Nos. 4B and 4D | |
771, 781.1 & 815 | Dismantling of redundant infrastructure | Works Nos. 4B and 4D | Removal of pylon foundations only to a depth of 1 metre |
981, 982, 987, 988, 989, 990, 991, 992, 993, 994, 1002, 1004, 1008, 1009, 1011, 1012, 1013, 1015, 1016, 1017, 1019 & 1020 | Construction of authorised development | Work No. 4F | |
995 & 996 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4F | |
999 & 1000 | Dismantling of redundant infrastructure | Work No. 4F | |
1001 | Construction of authorised development | Work No. 4F | Removal of pylon foundations only to a depth of 1 metre |
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
1, 4, 6, 7, 33, 37, 40, 49, 50, 59, 60, 63, 132, 133, 138, 146, 149, 162, 163, 191, 194, 222, 232, 238 & 239 | Construction of authorised development | Work No. 4D | |
10, 34, 43, 46, 53, 94, 103, 104, 109, 110, 112, 113, 154, 167 & 176 | Construction of authorised development | Works Nos. 4B and 4D | |
11, 16, 19, 29 & 93 | Dismantling of redundant infrastructure | Works Nos. 4B and 4D | |
13, 14, 68, 70, 77, 79, 105, 127, 128, 135, 136, 145, 159, 168, 169, 170, 174 & 175 | Dismantling of redundant infrastructure | Work No. 4B | |
23, 30, 45, 54 & 66 | Dismantling of redundant infrastructure | Works Nos. 4B and 4D | Removal of pylon foundations only to a depth of 1 metre |
44, 57, 65, 96, 116 & 120 | Dismantling of redundant infrastructure | Work No. 4D | Removal of pylon foundations only to a depth of 1 metre |
78, 126, 142, 143, 155 & 171 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
95.1, 95.2, 97, 98, 99.1, 99.2, 100.1, 100.2, 101, 115, 119, 207, 208, 209 & 210 | Dismantling of redundant infrastructure | Work No. 4D | |
117, 118, 121, 122, 123, 134 & 144 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4D | |
160 | Construction of authorised development | Works Nos. 4B and 4D | |
131, 137, 172 & 173 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B |
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
1, 2, 3, 4, 18, 19, 21, 22, 23, 29, 30, 34, 35, 36 & 202 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
5, 6, 7, 8, 10, 11, 12, 13, 14, 15, 16, 17, 24, 25, 26, 27, 31, 32, 33, 138, 139, 140, 141, 142, 143, 144, 145, 146, 149 156, 158, 159, 219.1, 222, 224, 225, 228 & 229 | Dismantling of redundant infrastructure | Work No. 4B | |
9, 20, 28, 37, 157, 201 & 219.2 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
38, 40, 41, 45, 60, 160, 161, 162 & 165 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4D | |
39, 64, 79, 81, 200, 218 & 249 | Dismantling of redundant infrastructure | Work No. 4D | Removal of pylon foundations only to a depth of 1 metre |
43, 67, 95, 98, 137, 176, 177, 178, 179, 186, 188, 192, 194, 196, 213 & 217 | Construction of authorised development | Work No. 4D | |
46, 47, 48, 57, 58, 59, 69, 72, 74, 76, 78, 82, 83, 84, 88, 89, 90, 91, 150, 151, 152, 153, 154, 155, 166, 167, 168, 169, 170, 172, 199, 214.1, 214.2 & 223 | Dismantling of redundant infrastructure | Work No. 4D | |
148, 163, 203 & 204 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4B and 4D | |
226, 230, 231, 233, 247 & 248 | Construction of authorised development | Work No. 4E | |
227 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4B, 4D, 4E, 4G and 4P | |
232, 278, 298 & 320 | Dismantling of redundant infrastructure | Work No. 4G | Removal of pylon foundations only to a depth of 1 metre |
234, 235, 240, 243, 276, 282, 293, 302 & 304 | Dismantling of redundant infrastructure | Work No. 4G | |
253, 255 & 285 | Dismantling of redundant infrastructure | Work No. 4P | |
258 | Dismantling of redundant infrastructure | Work No. 4P | Removal of pylon foundations only to a depth of 1 metre |
260 & 264 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4P | |
267, 269, 279, 280, 281, 288, 294, 296, 300, 307, 312, 314, 316, 317, 322, 326, 327, 328, 329 & 330 | Construction of authorised development | Work No. 4P | |
284 | Construction of authorised development | Work No. 4P | Removal of pylon foundations only to a depth of 1 metre |
303, 313 & 325 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4G and 4P |
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
38, 39.1, 39.2, 42, 43, 45, 46, 47.1, 47.2, 48, 52,57, 58.1, 58.2, 59, 64, 69, 84, 107, 118, 134 & 137 | Dismantling of redundant infrastructure | Work No. 4G | |
53, 61, 65, 108, 111, 116 & 138 | Dismantling of redundant infrastructure | Work No. 4G | Removal of pylon foundations only to a depth of 1 metre |
23.1, 23.2, 24.1, 24.2, 25, 82, 112, 113, 119, 120, 121, 122, 124, 125, 127, 128 & 130 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4G |
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
139 | Dismantling of redundant infrastructure | Work No. 4G |
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
143, 144, 145, 146, 148, 151, 248, 249, 250, 251, 252.1, 252.2, 253, 254, 255, 256, 257, 258, 259, 262, 263, 264, 265, 266, 267, 268, 270, 271, 272, 273, 274.1, 274.2, 275, 276, 277, 278, 279, 280, 281, 282, 283, 284, 285, 286, 287, 288, 289, 290, 291, 292, 293, 294, 295, 296, 297, 298, 299, 300, 301, 303, 304, 305, 306, 307, 308, 309, 310, 311, 312, 313, 315, 316, 317, 318, 322, 323, 324, 325, 326, 327, 329, 330, 331, 332, 333 & 334 | Dismantling of redundant infrastructure | Work No. 4G | |
147.1, 147.2, 260, 269, 302, 314 & 328 | Dismantling of redundant infrastructure | Work No. 4G | Removal of pylon foundations only to a depth of 1 metre |
261, 319, 320 & 321 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4G | |
335 | Dismantling of redundant infrastructure | Works Nos. 4G and 4H | Removal of pylon foundations only to a depth of 1 metre |
336 | Construction of authorised development | Work No. 4K | |
337 | Construction of authorised development | Works Nos. 4I and 4K | |
338, 339, 340, 341, 342, 343, 344, 345, 346, 347, 359, 378, 437, 438, 439, 474, 475, 476, 477, 478, 479, 480, 481, 482, 498, 499, 500, 501, 503, 504, 514, 515, 517, 518 & 519 | Dismantling of redundant infrastructure | Work No. 4H | |
351, 352.1, 352.2, 353.1, 353.2, 355, 380, 383, 384, 399, 400, 401, 402, 403, 404, 406, 407, 408 & 441 | Construction of authorised development | Work No. 4I | |
397 & 409 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4H | |
398, 405, 440 & 502 | Dismantling of redundant infrastructure | Work No. 4H | Removal of pylon foundations only to a depth of 1 metre |
562 & 564 | Construction of authorised development | Works Nos. 4M and 4N | |
563, 570, 571, 572 & 575 | Construction of authorised development | Works Nos. 4L, 4M and 4N | |
565 | Dismantling of redundant infrastructure | Work No. 4N | |
572 | Construction of authorised development | Works Nos. 4L, 4M and 4N | |
599 | Dismantling of redundant infrastructure | Work No. 4L | Removal of pylon foundations only to a depth of 1 metre |
604, 605, 606, 607, 609 & 610 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4L, 4M, 4N and 4O | |
608 & 611 | Construction of authorised development | Works Nos. 4L, 4M, 4N and 4O |
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
558 & 559 | Construction of authorised development | Works Nos. 4M and 4N | |
560 | Construction of authorised development | Works Nos. 4L, 4M and 4N | |
573 | Construction of authorised development | Work No. 4L |
(1) Plot number of land shown on Land Plan | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development | (4) Element of Work in respect of which land is not required to be re-instated |
---|---|---|---|
561 | Construction of authorised development | Works Nos. 4M and 4N | |
574 | Construction of authorised development | Work No. 4L |
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys