16.—(1) Subject to Schedule 9 (protection of interests), the undertaker may, for the purpose of or in connection with the carrying out and maintenance of the authorised development, regardless of any interference with any public or private rights—
(a)temporarily alter, interfere with, occupy and use the banks, bed, foreshores, waters and walls of a relevant navigation or watercourse;
(b)remove or relocate any moorings so far as may be reasonably necessary for the purposes of carrying out and of maintaining the authorised development;
(c)temporarily moor or anchor vessels and structures;
(d)construct, place, maintain and remove temporary works and structures within the banks, bed, foreshores, waters and walls of a relevant navigation or watercourse; and
(e)interfere with the navigation of any relevant navigation or watercourse,
in such manner and to such extent as may appear to it to be necessary or convenient.
(2) Except in the case of emergency, the undertaker must use reasonable endeavours to notify the owner of any mooring affected by the proposal to exercise the powers conferred by paragraph (1)(b) before the exercise of those powers.
(3) The undertaker must pay compensation to any person entitled to compensation under the 1961 Act who suffers any loss or damage from the exercise of the powers conferred by paragraph (1)(b).
(4) Any dispute as to a person’s entitlement to compensation under paragraph (3), or as to the amount of compensation, is to be determined under Part 1 of the 1961 Act.
(5) In this article, “relevant navigation” means so much of—
(a)The Kennet and Holy River;
(b)The Kennet and Avon Canal;
(c)The River Thames;
(d)The River Crane;
(e)The Jubilee River;
(f)The Cut; and
(g)River Colne,
as the context requires.
(6) Nothing in this article overrides the requirement to obtain necessary consents under the Water Resources Act 1991(1), the Environmental Permitting (England and Wales) Regulations 2010(2) or the Thames Water Authority Land Drainage Byelaws 1981.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys