The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016

 Help about what version

Pa Fersiwn

  • Y Diweddaraf sydd Ar Gael (Diwygiedig)
  • Gwreiddiol (a wnaed Fel)

Status:

Dyma’r fersiwn wreiddiol (fel y’i gwnaed yn wreiddiol). This item of legislation is currently only available in its original format.

Article 28

SCHEDULE 7LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

(1)

Location

(2)

Plot reference number(s) shown on Land Plans

(3)

Purpose for which temporary possession may be taken

(4)

Relevant part of the authorised development

Land Plans - Sheet 2
Section 1. District of West Berkshire02–16, 02–17, 02–18

At railway level: temporary land required for access for inspection and possible refurbishment of bridge

1a, 1b, 2a, 2b
Section 1. District of West Berkshire02–02a, 02–05

Land within existing highway boundary used for access to Scheme construction site and construction compound including traffic management

All works within Schedule 1
Section 1. District of West Berkshire02–20, 02–20a, 02–20b, 02–22, 02–22a, 02–22b, 02–23, 02–23a, 02–23b, 02–25, 02–25a, 02–25b

At river and river bank level: temporary use for inspection and possible refurbishment of bridge

1a, 1b
Section 1. District of West Berkshire02–08, 02–12

Temporary land required for use as construction compound

All works within Schedule 1
Section 1. District of West Berkshire02–09, 02–10, 02–11

Temporary land required for use for access to construction compound

All works within Schedule 1
Land Plans - Sheet 3
Section 1. District of West Berkshire03–07, 03–12

Temporary use for improvement and realignment of sliproads including traffic management and cross carriageway ducting

3a, 3b, 3c, 3d
Land Plans - Sheet 4
Section 1. District of West Berkshire04–06, 04–08, 04–10

At railway level: temporary land required for access for inspection and possible refurbishment of bridge

1a, 1b
Section 1. District of West Berkshire04–03, 04–04

Temporary use for inspection and possible refurbishment of culvert

1a, 1b
Land Plans - Sheet 6
Section 3. Borough of Reading06–03, 06–04, 06–05, 06–08

Temporary traffic management and for access to Scheme construction site

All works within Schedule 1
Section 3. Borough of Reading06–10, 06–10a, 06–12, 06–12a, 06–12b

Temporary traffic management, including lane restrictions, to create working space for construction of the Scheme including a gantry Type 1 and realignment of Junction 11 Eastbound on slip

1a, 4b
Section 2. Borough of Wokingham06–09b, 06–10b, 06–13, 06–14, 06–14a, 06–14b, 06–20

Temporary traffic management, including lane restrictions, to create working space for construction of the Scheme including a gantry Type 1 and realignment of Junction 11 Eastbound on slip

1a, 4b
Land Plans - Sheet 7
Section 2. Borough of Wokingham07–04, 07–05, 07–06, 07–08

Temporary use to create working space for construction of improved access to Cutbush Lane transmission station

1a
Section 2. Borough of Wokingham07–11

Temporary use to create working space for removal of existing police observation platform

1a
Land Plans - Sheet 10
Section 2. Borough of Wokingham10–07, 10–08, 10–09

At railway level: temporary use for inspection and possible refurbishment of bridge

1a, 1b, 5a
Land Plans - Sheet 17
Section 4. Royal Borough of Windsor and Maidenhead17–12

Temporary use as construction compound

All works within Schedule 1
Land Plans - Sheet 18
Section 4. Royal Borough of Windsor and Maidenhead18–02, 18–03

Temporary use as construction compound

All works within Schedule 1
Section 4. Royal Borough of Windsor and Maidenhead18–07, 18–08Temporary land required for access and working space to construct realigned Ascot Road and new Ascot Road overbridge including retaining wall to east side of Ascot Road7a, 7b
Section 4. Royal Borough of Windsor and Maidenhead18–09, 18–10, 18–17, 18–17a, 18–17b, 18–19

Temporary land required for access and working space to construct realigned Ascot Road and new Ascot Road overbridge

7a
Land Plans - Sheet 19
Section 4. Royal Borough of Windsor and Maidenhead19–19, 19–19b, 19–20, 19–20a, 19–25, 19–27, 19–28a, 19–30, 19–30a, 19–33, 19–33a

At river and river bank level: temporary land required for widening Thames Bray underbridge

1a, 1b, 9a, 9b
Section 6. County of Buckinghamshire, District of South Bucks19–35, 19–35a, 19–37, 19–37a, 19–38, 19–39

At river and river bank level: temporary land required for widening Thames Bray underbridge

1a, 1b, 9a, 9b
Section 4. Royal Borough of Windsor and Maidenhead19-02, 19-02a, 19-02b, 19-06, 19-10

Temporary land required for access and working space for online reconstruction of Monkey Island Lane and Monkey Island Lane overbridge

8c
Section 4. Royal Borough of Windsor and Maidenhead19–11, 19-14

Temporary land required for access and working space for online reconstruction of Monkey Island Lane and Monkey Island Lane overbridge and for widening of Thames Bray underbridge, including widening of the M4 and M4 embankment

8a, 8b, 8c, 9b
Section 6. County of Buckinghamshire, District of South Bucks19-34, 19-36, 19-40, 19-41, 19-45, 19-46, 19-47, 19-49, 19-51, 19-53, 19-54, 19-55

Temporary land for access and working space for widening of Thames Bray underbridge to the North, including widening of the M4 and M4 embankment

9a, 9b
Section 4. Royal Borough of Windsor and Maidenhead19-11a, 19-14a, 19-16, 19-18, 19-28, 19-29, 19-21, 19-22, 19-23, 19-24, 19-26, 19-31, 19-32

Temporary land for access and working space for widening of Thames Bray underbridge to the North, including widening of the M4 and M4 embankment

8a, 8b, 9a, 9b
Section 6. County of Buckinghamshire, District of South Bucks19–56, 19–57, 19–57a

Temporary land for access and working space for widening the M4 and M4 embankment

10b
Section 6. County of Buckinghamshire, District of South Bucks19-58, 19–59, 19–61, 19–62, 19–65, 19–73, 19–75, 19–76, 19–77, 19–79

Temporary land required for access and working space for online reconstruction of Marsh Lane and Marsh Lane overbridge

10c
Section 6. County of Buckinghamshire, District of South Bucks19–80

At river level: temporary land required for access for inspection and possible refurbishment work to Jubilee River Bridge

1a, 1b
Land Plans - Sheet 20
Section 6. County of Buckinghamshire, District of South Bucks20–02, 20–03, 20–03a, 20–07, 20–08, 20–09, 20–10, 20–12, 20–17, 20–20

Temporary land required for access and working space to construct realigned Lake End Road and new Lake End Road overbridge

11a, 11b, 11c
Section 7. Borough of Slough20–27, 20–28

Temporary land required for access and working space to construct realigned Huntercombe Spur and new Huntercombe Spur overbridge

12b, 12e, 12f
Section 6. County of Buckinghamshire, District of South Bucks20–22,

Temporary land required for access and working space to construct realigned Huntercombe Spur and new Huntercombe Spur overbridge

12b, 12c, 12d, 12e
Section 7. Borough of Slough20–30, 20–31, 20–32, 20–32a, 20–33, 20–34, 20–35, 20–36, 20–37, 20–37a, 20–37b, 20–37c, 20–38, 20–41b, 20–41c

Temporary land required for access and working space for online reconstruction of Oldway Lane and Oldway Lane overbridge

13, 13b, 13c
Section 7. Borough of Slough20–41, 20–41a

Temporary land required to enable temporary diversion of Rights of Way between Oldway Lane and Wood Lane

13c, 14c
Land Plans - Sheet 21
Section 7. Borough of Slough21–01, 21–02, 21–02a

Temporary land required to enable temporary diversion of Rights of Way between Oldway Lane and Wood Lane

13c, 14c
Section 7. Borough of Slough21–02b, 21–02c

Temporary land required to enable temporary diversion of Rights of Way between Oldway Lane and Wood Lane and for access and working space to construct and realign Wood Lane and new Wood Lane overbridge

13a, 13c, 14a, 14c
Section 7. Borough of Slough21–02d, 21–04, 21–05, 21–06, 21–07, 21–12a, 21–13, 21–14, 21–15, 21–16, 21–17, 21–18

Temporary land required for access and working space to construct realigned Wood Lane and new Wood Lane overbridge

14a, 14b, 14c
Section 7. Borough of Slough21–20, 21–21

Temporary land required for access and working space for the extension of Chalvey Culvert

15
Land Plans - Sheet 22
Section 7. Borough of Slough22–22, 22–23, 22–24, 22–25

At railway level: temporary land required for access and working space for widening Windsor Branch railway underbridge to the South, including realignment of M4 and Junction 6 Westbound off-slip and embankment strengthening and widening

1a, 1b, 16b, 16c, 17
Section 7. Borough of Slough22–01

Temporary access for inspection and possible refurbishment of culvert

1a, 1b

Section 4. Royal Borough of Windsor and Maidenhead

22–10Temporary use for access to construction compoundAll works within Schedule 1
Section 7. Borough of Slough22–09

Temporary use for access to construction compound and to Scheme construction site

All works within Schedule 1
Section 4. Royal Borough of Windsor and Maidenhead22–11

Temporary use as construction compound

All works within Schedule 1
Section 7. Borough of Slough22–12, 22–26

Temporary land required for access and working space for widening Windsor Branch Railway underbridge to the South, including realignment of M4 and Junction 6 Westbound off-slip and embankment strengthening and widening

1b, 16c, 17
Section 7. Borough of Slough22–18, 22–21

Temporary land required for access and working space for widening Windsor Branch Railway underbridge to the South, including realignment of M4 and Junction 6 Eastbound on-slip

1a, 16b, 17
Land Plans - Sheet 23
Section 7. Borough of Slough23–02, 23–03, 23–04

Temporary land for access and working space to extend Water Main and Gas Main subway

18
Section 4. Royal Borough of Windsor and Maidenhead23–12

Temporary land required for access and working space to construct realigned Datchet Road and new Datchet Road overbridge

19a, 19c
Section 7. Borough of Slough23–11

Temporary land required for access and working space to construct realigned Datchet Road and new Datchet Road overbridge

19a, 19c
Section 7. Borough of Slough23–07, 23–08

Temporary land for possible realignment of private means of access to Datchet Road

19c
Section 4. Royal Borough of Windsor and Maidenhead23–32

Temporary land required for access and working space for online reconstruction of Recreation Ground overbridge

20a, 20c
Section 7. Borough of Slough23–33

Temporary land required for access to finishing works on Recreation Ground road and Recreation Ground overbridge

20c
Section 4. Royal Borough of Windsor and Maidenhead23–34, 23–35

Temporary land required for access and working space to extend Water Main subway

21
Section 4. Royal Borough of Windsor and Maidenhead23–29

Temporary use as construction compound and temporary land required for access and working space to construct realigned Datchet Road and new Datchet Road overbridge, and temporary land required for access and working space for online reconstruction of Recreation Ground overbridge

19c, 20c, All works within Schedule 1
Section 7. Borough of Slough23–19

Temporary use as construction compound and temporary land required for access and working space to construct realigned Datchet Road and new Datchet Road overbridge

19c, All works within Schedule 1
Land Plans - Sheet 24
Section 4. Royal Borough of Windsor and Maidenhead

24-02, 24-03, 24-04, 24-05, 24-06, 24-07, 24-08, 24-09, 24-10, 24-11, 24-12, 24-13, 24-14, 24-15, 24-16, 24-17, 24-18, 24-20, 24-21, 24-22, 24-23, 24-24, 24-25, 24-29, 24-30, 24-32, 24-33, 24-34a

Temporary land required for access and working space to construct realigned Riding Court Road and new Riding Court Road overbridge22a, 22b, 22c
Section 4. Royal Borough of Windsor and Maidenhead24-34, 24-36, 24-40

Temporary traffic management, including lane restrictions on Riding Court Road, to create working space for construction of the Scheme

1a, 23a, 23b
Section 4. Royal Borough of Windsor and Maidenhead24-37, 24-38

Temporary traffic management, including lane restrictions on Majors Farm Road, to create working space for construction of the Scheme

1b
Land Plans - Sheet 25
Section 4. Royal Borough of Windsor and Maidenhead25-01, 25-02

Temporary traffic management, including lane restrictions on Riding Court Road, to create working space for construction of the Scheme

1a, 24a
Section 7. Borough of Slough25-03, 25-06, 25-09

Temporary traffic management, including lane restrictions on Riding Court Road, to create working space for construction of the Scheme

1a, 24a
Section 4. Royal Borough of Windsor and Maidenhead25-11

Temporary traffic management, including lane restrictions on Majors Farm Road, to create working space for construction of the Scheme

1b, 24d
Section 7. Borough of Slough25-15, 25-19

Temporary traffic management, including lane restrictions on Majors Farm Road, to create working space for construction of the Scheme

1b, 24d
Section 7. Borough of Slough25-20, 25-22

Temporary traffic management and access to Scheme construction site

All works within Schedule 1
Section 7. Borough of Slough25-30, 25-31, 25-32, 25-33, 25-34

Temporary use as construction compound

All works within Schedule 1
Land Plans - Sheet 26
Section 7. Borough of Slough26-03, 26-06, 26-09, 26-10, 26-19

Temporary land required for access and working space for online reconstruction of Old Slade Lane and Old Slade Lane overbridge

25, 26a, 26b
Section 6. County of Buckinghamshire, District of South Bucks26-02, 26-18

Temporary land required for access and working space for online reconstruction of Old Slade Lane and Old Slade Lane overbridge

25, 26a
Section 7. Borough of Slough26-09a, 26-10a, 26-11, 26-12, 26-13

Possible temporary access or diversion route for Old Slade Lane

25
Land Plans - Sheet 27
Section 6. County of Buckinghamshire, District of South Buckinghamshire27-12a, 27-12b, 27-12c, 27-12d, 27-12e, 27-12f

At motorway level; land within existing motorway boundaries retained for construction and operation of the Scheme. At railway level: temporary access for inspection and possible refurbishment of the bridge.

1a, 1b, 27a, 27b
Section 7, Borough of Slough27-13a, 27-13b, 27-13c, 27-13d

At motorway level; land within existing motorway boundaries retained for construction and operation of the Scheme. At railway level: temporary access for inspection and possible refurbishment of the bridge.

1a, 1b, 26a, 26b
Land Plans - Sheet 28
Section 8. London Borough of Hillingdon28-04, 28-05, 28-06, 28-07, 28-09, 28-10, 28-11, 28-12

Temporary access and working space for extension of Sipson Road subway

28, 29a, 29d
Land Plans - Sheet 29
Section 8. London Borough of Hillingdon29-01, 29-02, 29-03

Temporary use as construction compound

All works within Schedule 1
Land Plans - Sheet 30
Section 8. London Borough of Hillingdon30-03For inspection and possible refurbishment to St Dunstans Subway1a,1b

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill