SCHEDULE 2REQUIREMENTS

Provision of landscaping

10.—(1) No stage of the authorised development, other than the restoration of the temporary laydown area, is to commence until a landscaping scheme for that stage has been submitted to and approved by the relevant planning authority.

(2) The landscaping scheme submitted for approval must be in accordance with the design code principles and the environmental commitments and mitigation schedule and must include details of all proposed hard and soft landscaping works in the relevant stage including—

(a)location, number, species, size and planting density of any proposed planting;

(b)cultivation, importing of materials and other operations to ensure plant establishment;

(c)permanent boundary fencing or other means of permanent enclosure;

(d)expected finished ground levels;

(e)any trees proposed to be retained, with measures for their protection during the construction period of the relevant stages; and

(f)implementation timetable.

(3) The authorised development must be carried out in accordance with the details approved under paragraph (1), to a reasonable standard in accordance with the relevant recommendations of appropriate British Standards, and in all cases must comply with the measures set out in the environmental commitments and mitigation schedule.