There are currently no known outstanding effects for the The Town and Country Planning (Environmental Impact Assessment) Regulations 2017, PART 1 . Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 1 E+WGeneral

Citation, commencement and applicationE+W

1.—(1) These Regulations may be cited as the Town and Country Planning (Environmental Impact Assessment) Regulations 2017 and come into force on 16th May 2017.

(2) Subject to paragraph (3), these Regulations apply in relation to England only.

(3) Regulations 60, 61 and 62 apply in relation to Scotland, Wales and Northern Ireland respectively M1.

Marginal Citations

M1Regulations 60 to 62 relate to the Secretary of State's power to direct that the Regulations shall not apply to development that constitutes or forms part of a project having national defence as its sole purpose. The decision as to whether a direction should be made in respect of projects situated in the devolved administrations will be taken by the Secretary of State.

InterpretationE+W

2.—(1) In these Regulations—

the 1991 Act” means the Planning and Compensation Act 1991 M2;

the 1995 Act” means the Environment Act 1995 M3;

the Act” means the Town and Country Planning Act 1990 M4;

appropriate register” means the register on which particulars of an application for planning permission for the relevant development or an application for subsequent consent have been placed or would fall to be placed if such an application were made;

the consultation bodies” means—

(a)

any body which the relevant planning authority is required to consult, or would, if an application for planning permission for the development in question were before them, be required to consult by virtue of article 18 (consultations before the grant of permission) of the Order or of any direction under that article;

(b)

the Marine Management Organisation M5, in any case where the proposed development would affect, or would be likely to affect, any of the following areas—

(i)

waters in or adjacent to England up to the seaward limits of the territorial sea;

(ii)

an exclusive economic zone M6, except any part of an exclusive economic zone in relation to which the Scottish Ministers have functions;

(iii)

a Renewable Energy Zone M7, except any part of a Renewable Energy Zone in relation to which the Scottish Ministers have functions;

(iv)

an area designated under section 1(7) of the Continental Shelf Act 1964 M8, except any part of that area which is within a part of an exclusive economic zone or Renewable Energy Zone in relation to which the Scottish Ministers have functions; and

(c)

the following bodies if not referred to in paragraph (a) or (b)—

(i)

any principal council for the area where the land is situated, if not the relevant planning authority;

(ii)

Natural England M9;

(iii)

the Environment Agency M10;

(iv)

other bodies designated by statutory provision as having specific environmental responsibilities and which the relevant planning authority or the Secretary of State, as the case may be, considers are likely to have an interest in the application;

the Directive” means Council Directive 2011/92/EU M11;

EIA” has the meaning given by regulation 4;

EIA application” means—

(a)

an application for planning permission for EIA development; or

(b)

a subsequent application in respect of EIA development;

EIA development” means development which is either—

(a)

Schedule 1 development; or

(b)

Schedule 2 development likely to have significant effects on the environment by virtue of factors such as its nature, size or location;

EIA order proposal” means an order proposal which relates to EIA development;

environmental information” means the environmental statement, including any further information and any other information, any representations made by any body required by these Regulations to be invited to make representations, and any representations duly made by any other person about the environmental effects of the development;

environmental statement” has the meaning given by regulation 18;

European site” means a site within the meaning of regulation 8 of the Conservation of Habitats and Species Regulations 2010 M12;

EU environmental assessment” means an assessment carried out—

(a)

under an obligation to which section 2(1) of the European Communities Act 1972 M13 applies (other than the Directive); or

(b)

under the law of any part of the United Kingdom implementing an EU obligation other than an obligation arising under the Directive,

of the effect of anything on the environment;

exempt development” means development in respect of which the Secretary of State has made a direction under regulation 63;

further information” has the meaning given in regulation 25;

inspector” means a person appointed by the Secretary of State pursuant to paragraph 1 of Schedule 6 M14 to the Act to determine an appeal;

the land” means the land on which the development would be carried out or, in relation to development already carried out, has been carried out;

by local advertisement”, in relation to a notice, means—

(a)

by publication of the notice in a newspaper circulating in the locality in which the land to which the application or appeal relates is situated; and

(b)

publication of the notice on a website maintained by or on behalf of the authority;

local development order” means a local development order made pursuant to section 61A M15 (Local development orders) of the Act;

monitoring measure” means a provision requiring the monitoring of any significant adverse effects on the environment of proposed development including any measures contained in—

(a)

a condition imposed on the grant of planning permission; or

(b)

a planning obligation;

neighbourhood development order” means a neighbourhood development order made pursuant to section 61E M16 (Neighbourhood development orders) of the Act;

the Order” means the Town and Country Planning (Development Management Procedure) (England) Order 2015 M17;

order proposal” means a proposal for the making of a neighbourhood development order by a qualifying body under paragraph 1 of Schedule 4B M18 to the Act;

any other information” means any other substantive information relating to the environmental statement and provided by the applicant or the appellant as the case may be;

any particular person” includes any non-governmental organisation promoting environmental protection;

principal council” has the meaning given by section 270(1) (general provisions as to interpretation) of the Local Government Act 1972 M19;

qualifying body” has the meaning given by section 61E(6) (Neighbourhood development Orders) of the Act;

register” means a register kept pursuant to article 40 of the Order (register of applications) and references to a “Part” of the register are to be taken as references to the Parts of the register as described in article 40 of the Order;

relevant mineral planning authority” means the body to whom it falls, fell, or would, but for a direction under—

(a)

paragraph 7 of Schedule 2 (registration of old mining permissions) to the 1991 Act;

(b)

paragraph 13 of Schedule 13 (review of old mineral planning permissions) to the 1995 Act; or

(c)

paragraph 8 of Schedule 14 (periodic review of mineral planning permissions) to the 1995 Act,

fall to determine the ROMP application in question;

relevant planning authority” means the body to whom it falls, fell, or would, but for an application made directly to the Secretary of State under section 62A M20 of the Act (applications made directly to the Secretary of State) or a direction under section 77 M21 of the Act (reference of applications to Secretary of State), fall to determine an application for planning permission for the development in question;

ROMP application” means an application to a relevant mineral planning authority to determine the conditions to which a planning permission is to be subject under—

(a)

paragraph 2(2) of Schedule 2 (registration of old mining permissions) to the 1991 Act;

(b)

paragraph 9(1) of Schedule 13 (review of old mineral planning permissions) to the 1995 Act M22; or

(c)

paragraph 6(1) of Schedule 14 (periodic review of mineral planning permissions) to the 1995 Act M23;

ROMP development” means development which has yet to be carried out and which is authorised by a planning permission in respect of which a ROMP application has been or is to be made;

ROMP subsequent application” means an application for approval of a matter where the approval—

(a)

is required by or under a condition to which a planning permission is subject following determination of a ROMP application; and

(b)

must be obtained before all or part of the minerals development permitted by the planning permission may be begun or continued;

ROMP subsequent consent” means consent granted pursuant to a ROMP subsequent application;

“Schedule 1 application” and “Schedule 2 application” mean an application for planning permission for Schedule 1 development and Schedule 2 development respectively;

Schedule 1 development” means development, other than exempt development, of a description mentioned in Schedule 1;

Schedule 2 development” means development, other than exempt development, of a description mentioned in column 1 of the table in Schedule 2 where—

(a)

any part of that development is to be carried out in a sensitive area; or

(b)

any applicable threshold or criterion in the corresponding part of column 2 of that table is respectively exceeded or met in relation to that development;

“scoping direction” and “scoping opinion” have the meanings given in regulation 15;

screening direction” means a direction made by the Secretary of State as to whether development is EIA development;

screening opinion” means a written statement of the opinion of the relevant planning authority as to whether development is EIA development;

sensitive area” means any of the following—

(a)

land notified under section 28(1) (sites of special scientific interest) of the Wildlife and Countryside Act 1981 M24;

(b)

a National Park within the meaning of the National Parks and Access to the Countryside Act 1949 M25;

(c)

the Broads M26;

(d)

a property appearing on the World Heritage List kept under article 11(2) of the 1972 UNESCO Convention Concerning the Protection of the World Cultural and Natural Heritage M27;

(e)

a scheduled monument within the meaning of the Ancient Monuments and Archaeological Areas Act 1979 M28;

(f)

an area of outstanding natural beauty designated as such by an order made by Natural England under section 82(1) (areas of outstanding natural beauty) of the Countryside and Rights of Way Act 2000 M29 as confirmed by the Secretary of State;

(g)

a European site;

subsequent application” means an application for approval of a matter where the approval—

(a)

is required by or under a condition to which a planning permission is subject; and

(b)

must be obtained before all or part of the development permitted by the planning permission may be begun;

subsequent consent” means consent granted pursuant to a subsequent application;

UK environmental assessment” means an assessment carried out in accordance with an obligation under the law of any part of the United Kingdom of the effect of anything on the environment.

(2) Subject to paragraph (3), expressions used both in these Regulations and in the Act have the same meaning for the purposes of these Regulations as they have for the purposes of the Act.

(3) Expressions used both in these Regulations and in the Directive (whether or not also used in the Act) have the same meaning for the purposes of these Regulations as they have for the purposes of the Directive.

(4) In these Regulations references to the Secretary of State must not be construed as references to an inspector.

Marginal Citations

M5Established under section 1 of the Marine and Coastal Access Act 2009 (c. 23).

M6See section 41 of the Marine and Coastal Access Act 2009.

M7See section 84(4) of the Energy Act 2004 (c. 20), substituted by the Marine and Coastal Access Act 2009.

M81964 c. 29. Section 1(7) was amended by section 37 of, and paragraph 1 of Schedule 3 to, the Oil and Gas (Enterprise) Act 1982 (c. 23) and section 103 of the Energy Act 2011 (c. 16).

M10Established under section 1 of the Environment Act 1995 (c. 25).

M11OJ No. L 26, 28.1.2012, p. 1-21. Council Directive 2011/92/EU has been amended by Council Directive 2014/52/EU, OJ No. L 124, 25.4.2014, p. 1–18.

M12S.I. 2010/490. See regulation 8 which was amended by S.I. 2012/1927.

M131972 c. 68. Section 2(1) was amended by section 3(3), and Part 1 of the Schedule to, the European Union (Amendment) Act 2008 (c.7).

M14Schedule 6 was amended by sections 32 and 84 of, paragraph 54 of Schedules 7, and Part I of Schedule 19 to the 1991 Act; paragraph 44 of Schedule 22 to the 1995 Act; sections 196 and 198 of, and paragraphs 1 and 14 of Schedule 10 to, the Planning Act 2008 (c. 29); sections 2 and 7 of, and paragraphs 1 and 9 of Schedule 2 to, the Growth and Infrastructure Act 2013 (c. 27); and section 51 of and paragraphs 8 and 16 of Schedule 5 to the Planning (Wales) Act 2015 (anwa. 4).

M15Section 61A of the Act was inserted by section 40 of the Planning and Compulsory Purchase Act 2004 (c. 5) and amended by sections 188 and 238 of, and Schedule 13 to, the Planning Act 2008 (c. 29).

M16Section 61E of the Act was inserted by section 116(1) of, and paragraphs 1 and 2 of Schedule 9 to, the Localism Act 2011 (c. 20) and amended by section 140 of the Housing and Planning Act 2016 (c. 22).

M18Schedule 4B to the Act was inserted by section 116 of, and Schedule 10 to, the Localism Act 2011 and amended by sections 140 and 141 of the Housing and Planning Act 2016.

M20Section 62A of the Act was inserted by section 1 of the Growth and Infrastructure Act 2013 and amended by section 153 of the Housing and Planning Act 2016.

M21Section 77 of the Act was amended by section 32 of, and paragraph 18 of Schedule 7 to, the 1991 Act; section 112 of, and paragraphs 1 and 10 of Schedule 12 to, the Localism Act 2011; section 190 of the Planning Act 2008; section 30 of, and paragraphs 2 and 11 of Part 2 of Schedule 4 to, the Infrastructure Act 2015 (c. 7); and section 150 of, and paragraphs 1 and 20 of Schedule 12 to, the Housing and Planning Act 2016.

M22Paragraph 9 of Schedule 13 to the 1995 Act was amended by S.I. 2003/956.

M23Paragraph 6 of Schedule 14 to the 1995 Act was amended by S.I. 2003/956.

M241981 c. 69. Section 28 was substituted by section 75(1) of, and paragraph 1 of Schedule 9 to, the Countryside and Rights of Way Act 2001 (c. 37) and amended by section 105(1) of, and paragraph 79 of Part 1 of Schedule 11 to, the Natural Environment and Rural Communities Act 2006 (c. 16); and section 148 of, and paragraph 2 of Part 2 of Schedule 13 to, the Marine and Coastal Access Act 2009 (c. 23).

M251948 c. 97. See section 5(3).

M27See Command Paper 9424.

M281979 c. 46. See the definition in section 1(11).

M292000 c. 37. Section 82 was amended by section 105 of, and paragraph 163 of Part I of Schedule 11 to, the Natural Environment and Rural Communities Act 2006; and S.I. 2013/755.

Prohibition on granting planning permission or subsequent consent for EIA developmentE+W

3.  The relevant planning authority, the Secretary of State or an inspector must not grant planning permission or subsequent consent for EIA development unless an EIA has been carried out in respect of that development.

Environmental impact assessment processE+W

4.—(1) The environmental impact assessment (“ EIA”) is a process consisting of—

(a)the preparation of an environmental statement;

(b)any consultation, publication and notification required by, or by virtue of, these Regulations or any other enactment in respect of EIA development; and

(c)the steps required under regulation 26.

(2) The EIA must identify, describe and assess in an appropriate manner, in light of each individual case, the direct and indirect significant effects of the proposed development on the following factors—

(a)population and human health;

(b)biodiversity, with particular attention to species and habitats protected under Directive 92/43/EEC M30 and Directive 2009/147/EC M31;

(c)land, soil, water, air and climate;

(d)material assets, cultural heritage and the landscape;

(e)the interaction between the factors referred to in sub-paragraphs (a) to (d).

(3) The effects referred to in paragraph (2) on the factors set out in that paragraph must include the operational effects of the proposed development, where the proposed development will have operational effects.

(4) The significant effects to be identified, described and assessed under paragraph (2) include the expected significant effects arising from the vulnerability of the proposed development to major accidents or disasters that are relevant to that development.

(5) The relevant planning authority or the Secretary of State must ensure that they have, or have access as necessary to, sufficient expertise to examine the environmental statement.

Marginal Citations

M30OJ No. L 206, 22.7.1992, p. 7.

M31OJ No. L 20, 26.1.2010, p. 7.

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill