Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Temporary possession of landE+W+S

Temporary use of land for carrying out the authorised developmentE+W+S

29.—(1) TfL may, in connection with the carrying out of the authorised development but subject to article 21(1) (time limit for exercise of powers to possess land temporarily or to acquire land compulsorily)—

(a)enter on and take temporary possession of—

(i)the land specified in columns (1) and (2) of Schedule 7 (land of which only temporary possession may be taken) for the purpose specified in relation to that land in column (3) of that Schedule relating to the part of the authorised development specified in column (4) of that Schedule; and

(ii)any of the Order land in respect of which no notice of entry has been served under section 11 M1(powers of entry) of the 1965 Act (other than in connection with the acquisition of rights only) and no declaration has been made under section 4 M2 (execution of declaration) of the 1981 Act;

(b)remove any buildings and vegetation from that land;

(c)construct temporary works (including the provision of means of access) and buildings on that land;

(d)construct any works on that land as are mentioned in Schedule 1 (authorised development); and

(e)provide any temporary car parking or storage facilities on that land for the benefit of landowners or occupiers temporarily displaced as a result of the carrying out of the authorised development.

(2) TfL's temporary possession of any part of the river Thames under paragraph (1) is limited to what is reasonably necessary for TfL safely to construct the authorised development but TfL is not permitted by this article to take temporary possession of the entire width of the river Thames within the Order limits except in an emergency.

(3) At times and places where TfL has taken temporary possession of any part of the river Thames under this article, on the coming into effect of a notice to mariners in accordance with article 17(7) (work in the river Thames: conditions), the public right of navigation over that part of the river Thames is suspended and unenforceable against the PLA.

(4) Any person who suffers loss as a result of the suspension of any private right of navigation under this article is entitled to be paid compensation for such loss by TfL, to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5) Not less than 14 days before entering on and taking temporary possession of land under this article TfL must serve notice of the intended entry on the owners and occupiers of the land and that notice must state the works, facilities or other purpose for which TfL intends to take possession of the land.

(6) TfL may not, without the agreement of the owners of the land, remain in possession of any land under this article—

(a)in the case of any land specified in paragraph (1)(a)(i), after the end of the period of one year beginning with the date of completion of the part of the authorised development specified in relation to that land in column (4) of Schedule 7; or

(b)in the case of any land referred to in paragraph (1)(a)(ii), after the end of the period of one year beginning with the date of completion of the works, use of facilities or other purpose for which temporary possession of the land was taken unless TfL has, by the end of that period, served a notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act in relation to that land.

(7) Before giving up possession of land of which temporary possession has been taken under this article, TfL must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but TfL is not required to—

(a)replace a building removed under this article;

(b)restore the land on which any permanent works have been constructed under paragraph (1)(d);

(c)remove any ground strengthening works which have been placed on the land to facilitate construction of the authorised development; or

(d)remove any measures installed over or around statutory undertakers' apparatus to protect that apparatus from the authorised development.

(8) TfL must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

(9) Any dispute as to a person's entitlement to compensation under paragraph (8), or as to the amount of the compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(10) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (8) and nothing in this article affects any liability to pay compensation to the PLA under paragraph 49 of Schedule 13 (protective provisions).

(11) Where TfL takes possession of land under this article, TfL is not required to acquire the land or any interest in it.

(12) Section 13 M3 (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

Marginal Citations

M1As amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67), section 3 of, and part 1 of Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c. 71), section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (No. 1) and S.I. 2009/1307.

M2As amended by section 184 and 185 of, and paragraphs 1 and 2 of Schedule 18 to, the Housing and Planning Act 2016 (c. 22).

M3As amended by sections 62(3) and 139 of, and paragraph 27 and 28 of Schedule 13, and part 3 of Schedule 23, to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).

Temporary use of land for maintaining the authorised developmentE+W+S

30.—(1) Subject to paragraph (5), at any time during the maintenance period relating to any of the authorised development, TfL may—

(a)enter upon and take temporary possession of any land within the Order limits if possession is reasonably required for the purpose of maintaining the authorised development;

(b)enter on any land within the Order limits for the purpose of gaining such access as is reasonably required for the purpose of maintaining the authorised development; and

(c)construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.

(2) TfL's temporary possession of any part of the river Thames under paragraph (1) is limited to what is reasonably necessary for TfL safely to carry out any maintenance of the authorised development but TfL is not permitted by this article to take temporary possession of the entire width of the river Thames within the Order limits except in an emergency.

(3) At times and places where TfL has taken temporary possession of any part of the river Thames under this article, on the coming into effect of a notice to mariners in accordance with article 17(7) (work in the river Thames: conditions) the public right of navigation over that part of the river Thames will be suspended and unenforceable against the PLA.

(4) Any person who suffers loss as a result of the suspension of any private right of navigation under this article is entitled to be paid compensation for such loss by TfL, to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5) Paragraph (1) does not authorise TfL to take temporary possession of—

(a)any house or garden belonging to a house; or

(b)any building (other than a house) if it is for the time being occupied.

(6) Not less than 28 days before entering upon and taking temporary possession of land under this article TfL must serve notice of the intended entry on the owners and occupiers of the land and that notice must state the purpose for which TfL intends to take possession of the land including the particulars of the part of the authorised development for which possession is to be taken.

(7) TfL may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised development for which possession of the land was taken.

(8) Before giving up possession of land of which temporary possession has been taken under this article, TfL must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.

(9) TfL must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.

(10) Any dispute as to a person's entitlement to compensation under paragraph (9), or as to the amount of the compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(11) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (9) and nothing in this article affects any liability to pay compensation to the PLA under paragraph 49 of Schedule 13 (protective provisions).

(12) Where TfL takes possession of land under this article, it is not required to acquire the land or any interest in it.

(13) Section 13 (refusal to give possession to the acquiring authority) of the 1965 Act applies to the temporary use of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

(14) In this article “the maintenance period”, in relation to any part of the authorised development, means the period of 5 years beginning with the date on which—

(a)that part of the authorised development is first opened for public use (where that part of the authorised development is intended to be used by the public); or

(b)in respect of any other part of the authorised development, that part is first brought into operational use by TfL.

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill